Permit Information
Permit NumberBLD18-00254
StatusFinaled
Name SHADOW MOUNTAIN CONST INC
Site Address 4015 N SANDPOINT WAY
Project Name 
Customer Number 
ePlanReviewYes
Description
HILLSIDE, WUI FOOTHILLS, ZONE "A" REQUIREMENTS, CLASS "A" ROOF REQUIRED. Permit for the construction of a new 2538 sq. ft., one story single family dwelling with 3 bedrooms, 2 bathrooms, approximately 424 sq. ft. of covered patio/porch and a 876 sq. ft. attached garage per the approved plans, plan review report and any notations. A-1 zoning and setbacks per planning. ***BJM***

A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.

An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call 208-608-7070 to schedule an inspection.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/9/20194/10/20194/10/2019APASS
DetailsTony Young
Scott- please call for access Phone #: ###-####
DOC - Permit Finaled4/10/20194/10/20194/10/2019PPASS
DetailsTony Young
c of o issued
BLD-Blower Door Test Results4/10/20194/10/20194/10/2019PDONE
DetailsTony Young
Scott- please call for access Phone #: ###-####
// 4.5
PubWorks Occupancy Approval4/9/20194/9/20194/9/2019 DONE
DetailsMelissa Jannusch
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Melissa Jannusch ###-####.
BLD-Aging Inspection3/1/20193/1/20193/7/2019 PEND
DetailsTony Young
BLD-Other10/23/201810/24/201810/24/2018APASS
DetailsTony Young
sofit-Scott Phone #: ###-####
BLD-Energy code compliance10/17/201810/18/201810/18/2018PPASS
DetailsTony Young
Scott Phone #: ###-####
BLD-Framing/Rough-in10/17/201810/17/201810/17/2018PPASS
DetailsTony Young
scott johnson Phone #: ###-####
BLD-Framing/Rough-in10/16/201810/17/201810/17/2018APASS
DetailsTony Young
Scott Phone #: ###-####
BLD-Framing/Rough-in10/15/201810/16/201810/16/2018APEND
DetailsTony Young
Scott Phone #: ###-####,, needs fireplace to pass inspection,, failed rough in
BLD-Framing/Rough-in10/15/201810/15/201810/15/2018PNR
DetailsTony Young
Scott Phone #: ###-####,, needs fireplace inspection,,
BLD-Wall Bracing9/24/20189/25/20189/25/2018APASS
DetailsBrandon Shaw
Scott Phone #: ###-####
BLD-Footing8/24/20188/24/20188/24/2018PPART
DetailsTony Young
Pat Phone #: ###-####,, foundation poured,, ok
BLD-Footing8/7/20188/7/20188/7/2018PPART
DetailsTony Young
Pat Phone #: ###-####,, work in progress
PubWorks Subgrade Approval8/7/20188/7/20188/7/2018 DONE
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.

Issue PAID IN FULL permit  7/25/2018 DONE
Inspection Record Card- Bld  7/25/2018 DONE
Meeting  7/24/2018 DONE
sent email to don recommending to send in an extension request (don emailed back stating permit will be picked up tomorrow 7/25)
OVERRIDE  7/23/2018  
Plan assigned to (BJM)3/30/20183/30/20187/23/2018 DONE
DetailsBrian McGowan
1st review complete- 4-18 sfd L2 ePlan
Routing - PLAN CHECK7/23/2018 7/23/2018 PASS
DetailsBrian McGowan
PLANS/APPL TAKEN TO FRONT DESK  7/23/2018 DONE
DetailsBrian McGowan
Permit Ready to Issue  7/23/2018 DONE
Need
RP
Routing PW Grading-Hillside6/5/2018 6/5/2018 PASS
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.

Routing - PLAN CHECK5/18/2018 5/18/2018 FAIL
DetailsBrian McGowan
Did not resolve all corrections
Routing PW Grading-Hillside5/17/2018 5/17/2018 FAIL
DetailsMelissa Jannusch
See changemarks. Need retaining wall calculations
Routing - PLAN CHECK3/30/2018 4/19/2018 FAIL
DetailsBrian McGowan
1st review completed  4/18/2018 FAIL
DetailsBrian McGowan
Engineering for retaining wall and foundation
Routing - FIRE3/30/20183/30/20184/11/2018 PASS
DetailsErika Akin
Plans were reviewed for FD access, availability of hydrants and defensible space.
Routing PW Grading-Hillside3/30/2018 4/4/2018 FAIL
DetailsMelissa Jannusch
See changemarks in ePlan
Route to Impact Fee Review3/30/20184/2/20184/2/2018 PASS
DetailsEric Bilimoria
Initial residential review of new SFD permits requested for now.
Routing - Erosion and Sediment3/30/2018 4/2/2018 PASS
DetailsMichael Zawacki
Hillside lot. Site prep inspection required.
Routing - MECHANICAL3/30/2018 4/2/2018 PASS
DetailsTroy James
Routing - PLANNING3/30/2018 3/30/2018 PASS
DetailsSue Cummings
Routing - Addressing3/30/2018 3/30/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS3/30/2018 3/30/2018 PASS
DetailsRachael Beierle
Intake Approval  3/30/2018 FAIL
3/30-Please provide most updated grading and drainage plans that were approved under the CFH review process. The driveway configuration had been altered and the wall in the front setback reduced. --MMJ ###-#### (everything else ok)
Plans ACCEPTED BY PLAN TECH  3/30/2018 DONE
Intake Approval  3/30/2018 PASS
Recd Pcfee & Taken To Pln CK  3/30/2018 DONE
Telephone call  3/22/2018 DONE
plans were given to me to submit for a resubmittal but they were done online so Don will need to come get these and submit threw e plan. Called him and left a message on his cell phone
Intake Approval  2/12/2018 FAIL
still need the 2012 IRC letter and approval letter from P & Z. I don't show one has been started
Intake Approval  2/7/2018 FAIL
Project will require a CAT II Hillside application prior to acceptance of the building permit application. Application #114 will need to be filled out and turned in to the Planning & Zoning counter at city hall with the application fee. Once the application has been approved by P&Z please upload the approval letter and then this building permit case can be routed for approval.
Intake Approval  1/30/2018 FAIL
Has not applied for CFH case yet
Intake Approval  1/26/2018 FAIL
CAT II per Melissa
Missing letter to review under 2012
Plans need to be separated
Application received  1/23/2018 DONE
Application submitted via PDS Online on Jan 23 2018 10:43AM