BLD-Final | 7/30/2018 | 7/31/2018 | 7/31/2018 | P | PASS |
Jim Sly
|
|
|
call for access-Brandon Phone #: ###-####
|
DOC - Permit Finaled | 7/31/2018 | 7/31/2018 | 7/31/2018 | P | PASS |
Jim Sly
|
|
|
|
BLD-Energy code compliance | 4/25/2018 | 4/26/2018 | 4/26/2018 | A | PASS |
Tony Young
|
|
|
Brandon- call for access Phone #: ###-####
|
BLD-Energy code compliance | 4/24/2018 | 4/25/2018 | 4/26/2018 | P | NR |
Tony Young
|
|
|
Brandon- call for access Phone #: ###-####
|
BLD-Framing/Rough-in | 4/24/2018 | 4/25/2018 | 4/25/2018 | A | PASS |
Tony Young
|
|
|
Brandon -please call 30 min ahead- Phone #: ###-####
|
BLD-Framing/Rough-in | 4/23/2018 | 4/24/2018 | 4/24/2018 | P | FAIL |
Tony Young
|
|
|
Brandon please call 30 min prior Phone #: ###-####,, need plans and truss engineering
|
BLD-Framing/Rough-in | 4/16/2018 | 4/16/2018 | 4/16/2018 | P | NR |
Jim Sly
|
|
|
Disregard Pass on previous inspection. Mistake.
|
BLD-Framing/Rough-in | 4/13/2018 | 4/16/2018 | 4/16/2018 | A | PASS |
Jim Sly
|
|
|
Bradon Phone #: ###-####
|
Plan Modification Accepted | | | 4/9/2018 | | DONE |
|
|
|
revised acca report
|
Routing - MECHANICAL | 4/9/2018 | | 4/9/2018 | | PASS |
Chad Schwendiman
|
|
|
revised acca report
|
BLD-Wall Bracing | 3/30/2018 | 4/2/2018 | 4/2/2018 | P | PART |
Tony Young
|
|
|
Brandon Phone #: ###-####, exterior ok
|
BLD-Foundation | 3/6/2018 | 3/7/2018 | 3/7/2018 | A | PART |
Tony Young
|
|
|
work in progress,, ok
|
BLD-Footing | 3/1/2018 | 3/5/2018 | 3/5/2018 | A | PASS |
Tony Young
|
|
|
pour around 10:30-Brandon Phone #: ###-####
|
Issue PAID IN FULL permit | | | 2/26/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 2/14/2018 | | |
|
|
|
|
Telephone call | | | 2/14/2018 | | DONE |
|
|
|
Called Brandon to advise permit is ready pending RP and gave fees due
|
Routing - MECHANICAL | | | 2/14/2018 | | PASS |
Troy James
|
|
|
|
Plan assigned to (M_H) | 1/31/2018 | | 2/14/2018 | | DONE |
Michael Hanson
|
|
|
02/09 Townhome L2 Paper - 1st review completed. Wall bracing and structural deficiencies. MDH Emailed applicant for resubmittals. 01/31 MDH
|
Case Summary (BLD) | | | 2/14/2018 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/14/2018 | | DONE |
Michael Hanson
|
|
|
|
Inspection Record Card- Bld | | | 2/14/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/14/2018 | | DONE |
Christina Prado
|
|
|
Need:
RP
|
Routing - PLAN CHECK | 1/31/2018 | | 2/7/2018 | | PASS |
Michael Hanson
|
|
|
|
Plan resubmittals received | | | 2/5/2018 | | DONE |
|
|
|
resubmittlas received 2 sheets of 2 of 7 and 3 of 7-took to Mikael Hansen
|
Plan assigned to (RDP) | 1/23/2018 | 1/23/2018 | 1/31/2018 | | DEFR |
Rob Patrick
|
|
|
2/5 sfd L1 ePlan
|
Routing - PLAN CHECK | | | 1/31/2018 | | FAIL |
Michael Hanson
|
|
|
Wall bracing and structural deficiencies. MDH
|
Plan Reviewer's activity | | | 1/31/2018 | | FAIL |
Michael Hanson
|
|
|
Wall bracing and structural deficiencies. MDH
|
1st review completed | | | 1/31/2018 | | FAIL |
Michael Hanson
|
|
|
Wall bracing and structural deficiencies. MDH
|
Route to Impact Fee Review | 1/24/2018 | 1/27/2018 | 1/25/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 1/24/2018 | | 1/24/2018 | | PASS |
Leon Letson
|
|
|
|
Routing - Addressing | 1/24/2018 | | 1/24/2018 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | | | 1/24/2018 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/23/2018 | | DONE |
|
|
|
|
Intake Approval | | | 1/23/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/23/2018 | | DONE |
|
|
|
|
Application received | | 1/23/2018 | | | |
|
|
|
|