Permit Information
Permit NumberBLD18-00280
StatusFinaled
Name ST LUKES HEALTH SYSTEM LTD
Site Address 190 E BANNOCK ST
Project NameSurgery Locker Rooms
Customer Number 
ePlanReviewYes
Description
(ST. LUKE’S – SURGERY LOCKER ROOMS – GROUND STORY [BELOW 1ST STORY] – NEAR CENTER OF BUILDING) The fire sprinkler system is used for high rise and for occupancy. To convert a conference room into a 569 square foot Men’s locker room and to convert a waiting room into a 1,085 square foot Women’s locker room. Work is to include interior nonbearing walls, about 58 square feet of concrete filler floor slab over an existing ramp to create a level floor, suspended acoustical ceilings, lockers, benches, and finishes. All 2-hr shaft enclosures for stairways, 2-hr mechanical shafts, 1-hr smoke barriers creating smoke compartments, smoke partitions creating I-2 rated corridors, and smoke partitions creating care suites are required to be maintained. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 (including quick-response heads installed within the remodeled areas) and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 10/17/201810/31/2018 DONE
This permit finaled on the web by Curtis Weedop
Third Notice 9/15/201810/12/2018 DONE
mailed 10-15-18
First Follow up  10/12/2018 DONE
Third Notice 9/12/20189/10/2018 DONE
mailed 9-11-18
Third Notice 8/12/20189/7/2018 DONE
maild 9-10-18
Second Notice 7/20/20188/7/2018 DONE
mailed 8-10-18
First Notice 6/14/20187/10/2018 DONE
mailed 7-11-18
Permanent Occupancy  6/4/2018 DONE
BLD-Final5/30/20185/31/20185/31/2018APASS
DetailsDave Hannah
Darly Phone #: ###-####
FIRE-Final Inspection5/29/20185/30/20185/30/2018APASS
DetailsJim Page
Fire sprinkler inspection complete, fire alarm insepction complete, fire extinguishers are in common areas with current inspection tags. Final life fire safety inspection for area of work complete.

Daryl Phone #: ###-####
BLD-Ceiling Grid Inspection5/10/20185/11/20185/11/2018APASS
DetailsDave Hannah
Daryl Phone #: ###-####
BLD-Ceiling Grid Inspection4/30/20185/1/20185/1/2018APASS
DetailsDave Hannah
Daryl Phone #: ###-####
Issue PAID IN FULL permit  4/3/2018 DONE
Print Occupancy Form  4/3/2018 DONE
Plan assigned to (CJW)1/26/20181/26/20183/13/2018 PASS
DetailsCarl Westfall
(1st done) (Feb 15 - 15 days) (21 sheets) St Lukes locker rooms
Routing - PLAN CHECK1/26/2018 3/13/2018 FAIL
DetailsCarl Westfall
Revised drawings required
1st review completed  3/13/2018 DONE
Plan resubmittals requested  3/13/2018 DONE
Plan resubmittals received  3/13/2018 DONE
Plan resubmittals received  3/13/2018 DONE
Routing - PLAN CHECK3/13/2018 3/13/2018 PASS
DetailsCarl Westfall
2nd IBC plan review approved
PLANS/APPL TAKEN TO FRONT DESK  3/13/2018 DONE
Permit Ready to Issue  3/13/2018 DONE
DetailsChristina Prado
Need
GC Form - met
Revised Cert of Value - met
Routing - FIRE1/26/20181/26/20181/31/2018 PASS
DetailsErika Akin
Attached comments to case
Routing - MECHANICAL1/26/2018 1/29/2018 PASS
DetailsTroy James
Routing - PLUMBING1/26/2018 1/26/2018 PASS
DetailsBill VanDegrift
no plumbing
Routing - Addressing1/26/2018 1/26/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS1/26/2018 1/26/2018 PASS
DetailsRachael Beierle
Intake Approval  1/26/2018 PASS
DetailsAdele J Schaffeld-Griffin
Michael accepted pre screen and notified occupant of Major TI routing for this change of use
Application received  1/25/2018 DONE
Application submitted via PDS Online on Jan 25 2018 3:48PM
Telephone call  1/25/2018 DONE
Alejandro from ZGA Arch. called. wanted him added to applicant group to upload plans. Wanted to Keep Brenda Brosa in applicant group also.