Second Notice | | 6/21/2018 | 7/10/2018 | | DONE |
|
|
|
This permit finaled on the web by Charlene Meadows
|
First Notice | | 5/25/2018 | 6/11/2018 | | DONE |
|
|
|
mailed 6-12
|
Print Occupancy Form | | | 5/15/2018 | | DONE |
|
|
|
|
Permanent Occupancy | | | 5/15/2018 | | DONE |
|
|
|
|
BLD-Final | 5/14/2018 | 5/14/2018 | 5/14/2018 | P | PASS |
Brandon Shaw
|
|
|
dale Phone #: ###-####
|
DOC - Permit Finaled | 5/14/2018 | 5/14/2018 | 5/14/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Final | 5/11/2018 | 5/11/2018 | 5/11/2018 | P | PART |
Jim Sly
|
|
|
Dale Phone #: ###-#### OK for Temp. Occ. OK for Perm Occ. when Electrical signs Perm.
|
Temporary Occupancy | 5/11/2018 | 8/9/2018 | 5/11/2018 | | DONE |
Tiffany Carson-Herker
|
|
|
|
FIRE-Final Inspection | 5/8/2018 | 5/9/2018 | 5/9/2018 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
Dale Phone #: ###-####
|
FIRE-Final Inspection | 5/7/2018 | 5/8/2018 | 5/8/2018 | A | FAIL |
Troy Cobbley
|
|
|
Provide the exit signs as per the city approved plans. Missing four.
Dale EKC call 30 mins before for access Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 4/20/2018 | 4/23/2018 | 4/23/2018 | A | PASS |
Jim Sly
|
|
|
Dale Phone #: ###-####
|
BLD-Framing/Rough-in | 3/22/2018 | 3/23/2018 | 3/23/2018 | A | PASS |
Jim Sly
|
|
|
Dale Phone #: ###-####
|
Issue PAID IN FULL permit | | | 3/2/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/2/2018 | | DONE |
|
|
|
|
Route to Impact Fee Review | 2/17/2018 | 2/20/2018 | 2/20/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Permit Ready to Issue | | | 2/20/2018 | | DONE |
|
|
|
Need
GC Form -met
Revised Cert of Value - met
|
Plan assigned to (JG) | 2/5/2018 | 2/5/2018 | 2/17/2018 | | PASS |
Javier Guzman
|
|
|
2/16 L2 SEL Boise Office Remodel ePlan
|
Routing - PLAN CHECK | 2/5/2018 | | 2/17/2018 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 2/17/2018 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/17/2018 | | DONE |
|
|
|
|
Routing - FIRE | 2/5/2018 | 2/5/2018 | 2/7/2018 | | PASS |
Scott Arellano
|
|
|
Attached comments to case
|
Intake Approval | | | 2/5/2018 | | PASS |
Javier Guzman
|
|
|
|
Routing - Addressing | 2/5/2018 | | 2/5/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 2/5/2018 | | 2/5/2018 | | PASS |
Morgan Webb
|
|
|
|
Application received | | | 1/31/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 31 2018 2:57PM
|