Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD18-00353
StatusFinaled
Name STRAIGHT LINE BUILDING SOLUTIONS LL
Site Address 1325 S VISTA AVE
Project NameBoise School District STEP
Customer Number 
ePlanReviewYes
Description
(BOISE SCHOOL DISTRICT STEP) Permit for tenant improvements to an existing building for educational use w/ minor exterior work to add egress doors 7,730 sq. ft. building with work to include the removal and construction of new interior partition walls to create new classrooms, offices, a shower room, kitchen and associated support areas. The plans also indicate the removal and replacement of an interior bearing wall.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 11/24/201811/16/2018 DONE
This permit finaled on the web by Brian McCoy
First Notice11/13/201811/13/201811/16/2018 DONE
DetailsBrandon Shaw
This permit finaled on the web by Brian McCoy
Print Occupancy Form  11/14/2018 DONE
Permanent Occupancy  11/14/2018 DONE
BLD-Final11/13/201811/13/201811/13/2018PPASS
DetailsBrandon Shaw
Please call 30 mins ahead of time so I can meet you there. Phone #: ###-#### Inspection requested via web by Gerome Fries
DOC - Permit Finaled11/13/201811/13/201811/13/2018PPASS
DetailsBrandon Shaw
FIRE-Final Inspection9/4/20189/5/20189/5/2018APASS
DetailsTroy Cobbley
Life safety passed


Please call 30mins ahead of time so I can be there. Phone #: ###-#### Inspection requested via web by Gerome Fries
BLD-Final8/30/20188/31/20188/31/2018PPART
DetailsBrandon Shaw
As per Fire Final;
A temporary for life safety is being given per agreement for a fire watch, during business hours, until the project related fire alarm has been addressed. See email between the fire dept and the contractor.
FIRE-Final Inspection8/30/20188/31/20188/31/2018APART
DetailsTroy Cobbley
A temporary for life safety is being given per agreement for a fire watch, during business hours, until the project related fire alarm has been addressed. See email between the fire dept and the contractor.


Please call Gerome 30 min ahead of time. Phone #: ###-#### Inspection requested via web by Gerome Fries
BLD-Conference8/30/20188/31/20188/31/2018ADONE
DetailsBrandon Shaw
Please call 30 mins ahead of time so I can meet you there. Phone #: ###-#### Inspection requested via web by Gerome Fries
FIRE-Final Inspection8/29/20188/30/20188/29/2018PCANC
DetailsTroy Cobbley
Please call mins ahead of time so I can meet you there. Phone #: ###-#### >> Inspection requested via web by Gerome Fries Inspection cancelled from web by: Gerome Fries
FIRE-Final Inspection8/27/20188/28/20188/28/2018AFAIL
DetailsTroy Cobbley
Need the project related fire alarm permit finaled, need exit signs and emergency lights repaired, need sticker at the main exit.


Please call 30 mins ahead of time so I can meet you there. Phone #: ###-#### Inspection requested via web by Gerome Fries
BLD-Final8/24/20188/28/20188/28/2018ACANC
DetailsDave Hannah
Please call 30 minutes ahead of time so I can’t be there to let you in. Phone #: ###-#### Inspection requested via web by Gerome Fries failed fire
FIRE-Final Inspection8/24/20188/27/20188/27/2018PCANC
DetailsTroy Cobbley
Need the project related fire alrm permit scheduled/passed prior to a fire life safety inspection.

lease call 30 minutes ahead of time so I can’t be there to let you in. Phone #: ###-#### Inspection requested via web by Gerome Fries
BLD-Other7/24/20187/24/20187/24/2018PPASS
DetailsJim Storey
Inspection for the plumbing penetrations in the fire walls. Please call 30 minuets ahead of time so I can meet you there. Phone #: ###-#### Inspection requested via web by Gerome Fries
BLD-Framing/Rough-in7/23/20187/23/20187/23/2018PPASS
DetailsJim Storey
Cover inspection on phase 2. Phone #: ###-#### Inspection requested via web by Gerome Fries
BLD-Other7/17/20187/17/20187/17/2018PPASS
DetailsJim Storey
Please call 30 minutes ahead of time, so I can meet you there. Phone #: ###-#### Inspection requested via web by Gerome Fries
BLD-Framing/Rough-in6/21/20186/21/20186/21/2018PPART
DetailsJim Storey
Please call 30 mins ahead of time so I can meet you there. ###-#### Phone #: ###-#### Inspection requested via web by Gerome Fries cmu foward to vista st ok to rock walls/ pending core board ceilling and firestopping.
BLD-Conference5/30/20185/30/20185/31/2018PDEFR
DetailsJim Storey
Conference to discuss 1 hour corridor envelope system. Phone #: ###-#### Inspection requested via web by Gerome Fries //to planreview
BLD-Conference5/29/20185/29/20185/30/2018PCANC
DetailsJim Sly
Conference for one hour corridor assembly. Phone #: ###-#### Inspection requested via web by Gerome Fries
BLD-Conference5/25/20185/29/20185/29/2018ADONE
DetailsJim Sly
Call 30 mins ahead of time please. Phone #: ###-#### Inspection requested via web by Gerome Fries
Issue PAID IN FULL permit  4/23/2018 DONE
Print Occupancy Form  4/23/2018 DONE
Meeting  4/20/2018 DONE
after talking to Christina-no eraly start was started so removed the fees and voided BLD18-01005
Routing - PLAN CHECK4/10/2018 4/11/2018 PASS
DetailsCarl D Madsen
PLANS/APPL TAKEN TO FRONT DESK  4/11/2018 DONE
Permit Ready to Issue  4/11/2018 DONE
ALL Met-Need GC form for early start Bld18-01005 and need to pay fee (close out early start when main TI is issued)

Met-Need GC form and Revised value from GC
Routing PW Solid Waste4/10/2018 4/10/2018 PASS
DetailsEvan Carpenter
Routing - PUBLIC WORKS4/10/2018 4/10/2018 PASS
DetailsRachael Beierle
Routing - Design Review4/9/2018 4/9/2018 PASS
DetailsKatelyn Menuge
Routing PW Solid Waste4/9/2018 4/9/2018 FAIL
DetailsEvan Carpenter
The solid waste enclosure must have a straight-line approach of at least 50 feet in front of the enclosure gates.

Additionally, the enclosure must have a depth of at least 8 feet.
Routing - PLAN CHECK4/4/2018 4/6/2018 PASS
DetailsCarl D Madsen
Plan assigned to (CDM)2/9/20182/9/20183/22/2018 PASS
DetailsCarl D Madsen
1st comp Boise School District STEP
Route to Impact Fee Review2/18/20182/21/20182/20/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
1st review completed  2/18/2018 FAIL
Routing - PLAN CHECK2/9/2018 2/18/2018 FAIL
DetailsCarl D Madsen
Routing - FIRE2/9/20182/9/20182/15/2018 PASS
DetailsScott Arellano
Attached comments to case
Routing PW Environmental2/9/2018 2/15/2018 PASS
DetailsRick Christenson
Routing - MECHANICAL2/9/2018 2/12/2018 PASS
DetailsTroy James
Plan assigned to (CJW)2/9/20182/9/20182/9/2018 DEFR
DetailsCarl D Madsen
Boise School District STEP
Routing - Design Review2/9/2018 2/9/2018 FAIL
DetailsKatelyn Menuge
Relocate bike rack to be outside of clear vision triangle.
Intake Approval  2/9/2018 PASS
Routing - PLUMBING2/9/2018 2/9/2018 PASS
DetailsBill VanDegrift
Per plan and ISPC.
Routing - PLANNING2/9/2018 2/9/2018 PASS
DetailsCeline Acord
per CUP17-00059
Routing - Addressing2/9/2018 2/9/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS2/9/2018 2/9/2018 PASS
DetailsRachael Beierle
Application received  2/1/2018 DONE
Application submitted via PDS Online on Feb 1 2018 1:59PM