BLD-Final | 1/22/2019 | 1/23/2019 | 1/23/2019 | P | PASS |
Jim Sly
|
|
|
call 30 mins for access- Brandon Phone #: ###-####
|
DOC - Permit Finaled | 1/23/2019 | 1/23/2019 | 1/23/2019 | P | PASS |
Jim Sly
|
|
|
|
BLD-Energy code compliance | 11/8/2018 | 11/8/2018 | 11/12/2018 | P | PASS |
Jim Sly
|
|
|
Please call ahead for access - Brandon Phone #: ###-####
|
BLD-Framing/Rough-in | 11/6/2018 | 11/7/2018 | 11/8/2018 | P | PASS |
Tony Young
|
|
|
Brandon Phone #: ###-####
|
BLD-Framing/Rough-in | 11/5/2018 | 11/6/2018 | 11/6/2018 | A | NR |
Mike Jordan
|
|
|
Brandon Phone #: ###-####. Fire place rough in inspection has failed. Complte airseal prior to framing inspection.
|
BLD-Framing/Rough-in | 11/2/2018 | 11/2/2018 | 11/2/2018 | P | PART |
Jim Sly
|
|
|
Brandon Phone #: ###-#### Exterior shear nailing.....OK
|
Plan Modification Accepted | | | 10/18/2018 | | DONE |
|
|
|
New manual j report
|
Routing - MECHANICAL | 10/18/2018 | | 10/18/2018 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Footing | 9/13/2018 | 9/13/2018 | 9/13/2018 | P | PASS |
Jim Sly
|
|
|
Brandon Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/12/2018 | | DONE |
|
|
|
|
Extend Review Timeline | | | 8/6/2018 | | DONE |
|
|
|
1st approved 180 day extension per Adele. See documents
|
Meeting | | | 7/26/2018 | | DONE |
|
|
|
sent in extension request 7-25-18
|
Expiration Notice | 7/12/2018 | 8/2/2018 | 7/12/2018 | | DONE |
Brittany Hill
|
|
|
|
OVERRIDE | | | 2/28/2018 | | |
|
|
|
|
Plan assigned to (RDP) | 2/5/2018 | 2/5/2018 | 2/28/2018 | | DONE |
Rob Patrick
|
|
|
2/22 sfd L2 ePlan. Planning Failed due to Set-Backs. Redesign required. Bldr coming with updates.
|
Inspection Record Card- Bld | | | 2/28/2018 | | DONE |
|
|
|
|
Telephone call | | | 2/28/2018 | | DONE |
|
|
|
called Brandon to let know permit is ready and how much is owed-he asked me to email him the fees due-so i did
|
Routing - PLANNING | 2/28/2018 | | 2/28/2018 | | PASS |
Leon Letson
|
|
|
|
Routing - PLAN CHECK | 2/28/2018 | | 2/28/2018 | | PASS |
Rob Patrick
|
|
|
|
Case Summary (BLD) | | | 2/28/2018 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/28/2018 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 2/28/2018 | | DONE |
|
|
|
met
|
Routing - MECHANICAL | | | 2/8/2018 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 2/5/2018 | 2/8/2018 | 2/6/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PUBLIC WORKS | | | 2/6/2018 | | PASS |
|
|
|
|
1st review completed | | | 2/6/2018 | | FAIL |
|
|
|
Planning Failed due to set-backs. Emailed builder to re-submit.
|
Routing - Addressing | 2/5/2018 | | 2/5/2018 | | PASS |
Doug Chausow
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/5/2018 | | DONE |
|
|
|
|
Intake Approval | | | 2/5/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/5/2018 | | DONE |
|
|
|
|
Application received | | 2/5/2018 | | | |
|
|
|
|
Routing - PLANNING | 2/6/2018 | | | | FAIL |
Leon Letson
|
|
|
Project does not meet required 5' front setback for living space, per PUD15-00003.
|
Routing - PLAN CHECK | 2/8/2018 | | | | FAIL |
Rob Patrick
|
|
|
|