Permit Information
Permit NumberBLD18-00388
StatusFinaled
Name JH DEVELOPMENT INC
Site Address 1401 S COLOMA PL
Project NameBoulder Heights
Customer Number 
ePlanReviewNo
Description
Permit for the construction of a new 5426 sq. ft., two story (first story 4603 sq. ft., second story 823 sq. ft.) single family dwelling with 6 bedrooms, 6 bathrooms, approximately 850 sq. ft. of covered patio/porch and a 1630 sq. ft. attached garage per the approved plans, plan review report and any notations. Prescriptive Energy Compliance. W.U.I. Foothills Lot, Class "A" Roof required. Structure to be fully sprinklered. Zoning and setbacks per planning.

A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/15/20194/15/20194/15/2019PPASS
DetailsBrandon Shaw
Eric Phone #: ###-####
DOC - Permit Finaled4/15/20194/15/20194/15/2019PPASS
DetailsBrandon Shaw
BLD-Blower Door Test Results4/15/20194/15/20194/15/2019PDONE
DetailsBrandon Shaw
ACH50- 2.8
BLD-Final4/10/20194/10/20194/10/2019PNR
DetailsBrandon Shaw
Need Fire final...
No other issues...
PubWorks Occupancy Approval4/10/20194/10/20194/10/2019 DONE
DetailsMelissa Jannusch
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Melissa Jannusch ###-####.
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
BLD-Aging Inspection2/8/20192/8/20192/8/2019 DEFR
DetailsBrandon Shaw
Work in progress
BLD-Aging Inspection2/7/20192/7/20192/7/2019 DONE
DetailsBrandon Shaw
Work in progress
BLD-Energy code compliance9/26/20189/26/20189/26/2018PPASS
DetailsBrandon Shaw
Eric Phone #: ###-####
BLD-Framing/Rough-in9/26/20189/27/20189/26/2018APASS
DetailsBrandon Shaw
Corrections SAT...
BLD-Framing/Rough-in9/13/20189/13/20189/13/2018PFAIL
DetailsBrandon Shaw
Need Sprinkler rough in...

No Issues with framing...
No cover at this time...
CHANGE STATUS TO (ISS)  9/11/2018 DONE
Inspection Record Card- Bld  9/11/2018 DONE
OVERRIDE  9/10/2018  
Plan assigned to (RDP)8/29/20188/29/20189/10/2018 DONE
DetailsRob Patrick
Routing - PLAN CHECK9/6/2018 9/10/2018 PASS
DetailsRob Patrick
Plan Modification...Delivered Plan sets to Melissa.
Permit Ready to Issue  9/10/2018 DONE
plan mod-pleae do not re issue-as per Rob P no fees due
Telephone call  9/10/2018 DONE
cqalled Jeff-left message on his phone that the plan mod is ready for him to pick up-plans are in the drawers for new SFD under J
Routing PW Grading-Hillside9/6/2018 9/6/2018 PASS
DetailsMelissa Jannusch
PLAN MOD APPROVED


A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.


Routing - PUBLIC WORKS9/6/2018 9/6/2018 PASS
DetailsRachael Beierle
Routing - FIRE8/29/20188/29/20188/30/2018 PASS
DetailsRon Johnson
Defensible space maintained in plan mod
BLD-Wall Bracing8/29/20188/29/20188/29/2018PPASS
DetailsBrandon Shaw
Eric Phone #: ###-####
Routing - PLANNING8/29/2018 8/29/2018 PASS
DetailsNicolette Womack
Send to Ron Johnson for WUI Review.
Plan Modification Accepted  8/29/2018 DONE
Plan Mod submitted2 of each sheet1 of12, 3 of 12 & 1.0 - rotate house-of 2-took to Rob P.-
Routing - MECHANICAL8/27/2018 8/28/2018 PASS
DetailsTroy James
resubmitted manual j report
Plan Modification Accepted  8/27/2018 DONE
New manual j report
BLD-Conference8/17/20188/17/20188/17/2018ADEFR
DetailsBrandon Shaw
Work in progress
BLD-Aging Inspection8/17/20188/17/20188/17/2018 DEFR
DetailsBrandon Shaw
Work in progress
BLD-Foundation4/5/20184/5/20184/5/2018APASS
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by Ben Sears
BLD-Footing4/2/20184/2/20184/2/2018PPEND
DetailsBrandon Shaw
Need revised plot plan submitted to Planning Dept. Foot print of structure has been rotated 90 degrees counter-clockwise from original city approved plans
Proceed at own risk
Footing and rebar- SAT
PubWorks Subgrade Approval3/29/20183/29/20183/29/2018 DONE
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.

Issue PAID IN FULL permit  3/16/2018 DONE
OVERRIDE  3/5/2018  
Plan assigned to (RDP)3/5/20183/5/20183/5/2018 DONE
DetailsRob Patrick
Routing - FIRE3/5/20183/5/20183/5/2018 PASS
DetailsErika Akin
Residence to be Fire Sprinklered. Attached comments to case
Plan assigned to (RDP)2/5/20182/5/20183/5/2018 DONE
DetailsRob Patrick
2/22 sfd L2 paper...Failed for no secondary drainage from roof.
Case Summary (BLD)  3/5/2018 DONE
DetailsRob Patrick
PLANS/APPL TAKEN TO FRONT DESK  3/5/2018 DONE
DetailsRob Patrick
PLANS/APPL TAKEN TO FRONT DESK  3/5/2018 DONE
DetailsRob Patrick
Inspection Record Card- Bld  3/5/2018 DONE
Routing - PLAN CHECK3/5/2018 3/5/2018 PASS
DetailsRob Patrick
Telephone call  3/5/2018 DONE
DetailsChristina Prado
Called Eric to give permit fees due and advised about double fee on retaining portion
Permit Ready to Issue  3/5/2018 DONE
DetailsChristina Prado
All requirements met
Plan resubmittals received  3/2/2018 DONE
Two sheets of page 1, 3 and 5. taken to rob
Routing - FIRE2/22/20182/22/20182/22/2018 FAIL
DetailsScott Arellano
Attached comments and emailed applicant
1st review completed  2/22/2018 FAIL
DetailsRob Patrick
Failed for no secondary drainage from roof.
Routing - PLAN CHECK2/21/2018 2/22/2018 FAIL
DetailsRob Patrick
No secondary drainage from roof.
Plan Reviewer's activity  2/21/2018  
Plan was held in PW for 10 days. Plan was received for Plan Check on 2-21-18.
Routing - Erosion and Sediment2/20/2018 2/20/2018 PASS
DetailsAndy J. Long
ESC permit already issued for project, see ESC17-01749
Routing - MECHANICAL  2/20/2018 PASS
DetailsTroy James
Routing - PLANNING2/16/2018 2/20/2018 PASS
DetailsNicolette Womack
Eaves shall not exceed more than 2' into the setback.
Routing - PUBLIC WORKS2/5/2018 2/16/2018 PASS
DetailsMorgan Webb
Routing PW Grading-Hillside2/6/2018 2/16/2018 PASS
DetailsMelissa Jannusch


A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
Meeting  2/14/2018 DONE
DetailsChristina Prado
Per MIS18-00051 - Stop work for construction of retaining wall without permits. Double fee on permit once obtained per JCB & PW. GRD specifically states no retaining wall
Retaining wall value $16,000, valuation & investigation fee added as directed above
Route to Impact Fee Review2/5/20182/8/20182/6/2018 PASS
DetailsEric Bilimoria
Initial residential review of new SFD permits requested for now.
Routing PW Sewer Rating2/6/2018 2/6/2018 PASS
DetailsRachael Beierle
Routing - Addressing2/5/2018 2/6/2018 PASS
DetailsDoug Chausow
Plans ACCEPTED BY PLAN TECH  2/5/2018 DONE
Intake Approval  2/5/2018 PASS
Recd Pcfee & Taken To Pln CK  2/5/2018 DONE
Application received 2/5/2018   
Routing - PUBLIC WORKS GRADING8/29/2018    
DetailsMelissa Jannusch