Permit Information
Permit NumberBLD18-00400
StatusFinaled
Name KURKOV CONSTRUCTION LLC
Site Address 255 N WHITEWATER PARK BLVD
Project NameWhitewater Apartments
Customer Number 
ePlanReviewYes
Description
(WHITEWATER PARK APARTMENTS – UNITS #107, #108, #207, #208, #307 and #308 – FIRE DAMAGE REPAIR PERMIT) ""PREINSPECTION IS REQUIRED PRIOR TO THE START OF ANY WORK"" Permit for repairs to six (6) units within an existing apartment building resulting from fire/water damage. Note: This building was built in 1994 using the 1991 UBC, plans on file under micro fiche #97113. This is a scope of work permit only; A Letter of Completion is to be issued when done. Approval is contingent upon adhering to the approved plans on file. Work to include: remove and replace select pre-engineered structural roof trusses, remove and replace select roof assembly, remove and replace select wall finishes, remove and replace select floor and ceiling finishes, select cabinetry replacement, select exterior finishes, select new fireplace, electrical work, plumbing work, mechanical work and interior finishes in compliance with Ch. 8 of the 2015 IBC. This building is Not Fire Sprinklered. **JG**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final9/19/20189/19/20189/20/2018PDONE
DetailsDave Hannah
Fedor Phone #: ###-####
BLD-Final9/19/20189/20/20189/20/2018APASS
DetailsDave Hannah
Fedor Phone #: ###-####
DOC - Permit Finaled9/20/20189/20/20189/20/2018PPASS
DetailsDave Hannah
FIRE-Final Inspection9/19/20189/19/20189/19/2018PPASS
DetailsMike Jordan
Fedor Phone #: ###-####. Life/safety final ok.
BLD-Final9/18/20189/19/20189/19/2018ACANC
DetailsDave Hannah
Fedor Phone #: ###-####
BLD-Framing/Rough-in7/18/20187/19/20187/19/2018APASS
DetailsDave Hannah
Fedor--lock box in unit 307, code 9325 Phone #: ###-####
BLD-Energy code compliance6/29/20187/2/20187/2/2018PPASS
DetailsDave Hannah
Call for access // Fudor Phone #: ###-####
BLD-Framing/Rough-in6/27/20186/29/20186/29/2018APASS
DetailsDave Hannah
Fedor Phone #: ###-####
BLD-Framing/Rough-in6/14/20186/18/20186/18/2018PPART
DetailsDave Hannah
Pedor Phone #: ###-#### trusses ok
BLD-Conference4/5/20184/9/20184/9/2018ADONE
DetailsDave Hannah
Sedor- call 30 mins ahead, he will be there after 9am, flying in from washington Phone #: ###-####
Issue PAID IN FULL permit  4/5/2018 DONE
Inspection Record Card- Bld  4/5/2018 DONE
Plan assigned to (JG)2/15/20182/15/20182/15/2018 PASS
DetailsJavier Guzman
Whitewater Apartments
Plan assigned to (JG)2/8/20182/8/20182/15/2018 PASS
DetailsJavier Guzman
Whitewater Apartments Repair L2
Routing - PLAN CHECK2/12/2018 2/15/2018 PASS
DetailsJavier Guzman
Intake Approval  2/15/2018 PASS
DetailsJavier Guzman
1st review completed  2/15/2018 DONE
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  2/15/2018 DONE
Permit Ready to Issue  2/15/2018 DONE
MET
NEED
GC
Rev Cert of Val
Application received  2/6/2018 DONE
Application submitted via PDS Online on Feb 6 2018 11:16AM
First Notice9/20/20189/20/2018   
DetailsDave Hannah