Plan Reviewer's activity | | | 6/26/2020 | | DONE |
Joe Bruce
|
|
|
Fire Hydrant distance has been extended per email from Todd Callahan (Asst Fire Marshal). Existing fire hydrant is adequate and new fire hydrant is not required to be installed.
|
BLD-Framing/Rough-in | 5/14/2020 | 5/15/2020 | 5/15/2020 | A | PART |
Mike Jordan
|
|
|
screened // Cory Phone #: ###-####. Framing on pre engineered structure. Needs bolting inspection from 3rd. party. Also noted west set back not per plans. Needs to resubmit updated setbacks for approval. Plans show 15ft set back, addition is currently at 11ft. 1 inch. Should not affect construction of exterior wall. Also needs to send special inspection reports for footing and foundation inspections.
|
BLD-Conference | 10/22/2019 | 10/22/2019 | 10/22/2019 | P | DONE |
Mike Jordan
|
|
|
Please call ahead for inspection/site question - Cory Phone #: ###-####
|
Print Occupancy Form | | | 10/3/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/18/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/18/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 8/20/2019 | | |
|
|
|
|
Plan assigned to (JG) | 2/21/2019 | 2/28/2019 | 8/20/2019 | | PASS |
Javier Guzman
|
|
|
3rd rev, 04/03 (6wks) - 502 LTS Motors Shop Addition ePlan
|
Routing - PLAN CHECK | 8/20/2019 | | 8/20/2019 | | PASS |
Javier Guzman
|
|
|
|
Routing PW Drainage | 8/20/2019 | | 8/20/2019 | | PASS |
Brian Murphy
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/20/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/20/2019 | | DONE |
|
|
|
all met-NEED
RP-met
GC FORM-met
REVISED VALUE-met
still need the RP but emailed Cory Adamson the fees that are due
CAN
|
Routing - FIRE | 7/31/2019 | 7/31/2019 | 8/13/2019 | | PASS |
Mark Scharfen
|
|
|
08/13-LTS Motors resubmittal review completed 08.13.2019. Uploaded rev_fire 08.13.2019.pdf.
|
Routing - PLAN CHECK | 7/31/2019 | | 8/5/2019 | | PASS |
Javier Guzman
|
|
|
|
Routing - FIRE | 7/9/2019 | 7/9/2019 | 7/15/2019 | | FAIL |
Mark Scharfen
|
|
|
07.15.2019-Completed review of resbumittal. Uploaded rev_fire 07.15.2019.pdf and emailed to applicant.
|
Routing - PLAN CHECK | 7/9/2019 | | 7/12/2019 | | PASS |
Javier Guzman
|
|
|
|
Routing - PUBLIC WORKS | 7/12/2019 | | 7/12/2019 | | PASS |
Angela Hardy
|
|
|
revised C1 grading plan sheet
|
Routing - PLUMBING | 7/12/2019 | | 7/12/2019 | | PASS |
Daryl Spivey
|
|
|
revised C1 grading plan sheet
|
Routing - MECHANICAL | 7/9/2019 | | 7/10/2019 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 4/3/2019 | 4/6/2019 | 4/4/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 2/21/2019 | 2/28/2019 | 4/3/2019 | | FAIL |
Mark Scharfen
|
|
|
IFC 1st review 04.03.2019.pdf uploaded and emailed to applicant.
|
Routing Off Site - STRUCTURAL | 2/28/2019 | | 4/3/2019 | | PASS |
Javier Guzman
|
|
|
signed off in ePlan by AHJ Engineers Dave Haugland
|
Routing - PLAN CHECK | 2/28/2019 | | 4/3/2019 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 4/3/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLANNING | 2/28/2019 | | 4/3/2019 | | CANC |
Jeff Lowe
|
|
|
No review required as stated in ePlan by Current Planning Jeff Lowe
|
Routing PW Environmental | 3/1/2019 | | 3/18/2019 | | PASS |
Rick Christenson
|
|
|
Dry shop no drains shown
|
Routing PW Drainage | 3/1/2019 | | 3/13/2019 | | PASS |
Brian Murphy
|
|
|
|
Routing - MECHANICAL | 2/28/2019 | | 3/4/2019 | | FAIL |
Troy James
|
|
|
See Eplan
|
Routing - Erosion and Sediment | 2/28/2019 | | 3/4/2019 | | PASS |
Michael Zawacki
|
|
|
RP needed before work begins. Site prep inspection required.
|
Routing - Addressing | 2/28/2019 | | 3/1/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 2/28/2019 | | 3/1/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing PW Street Lights | 3/1/2019 | | 3/1/2019 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 3/1/2019 | | 3/1/2019 | | PASS |
DeAnn Brown
|
|
|
|
Routing PW Solid Waste | 3/1/2019 | | 3/1/2019 | | PASS |
Evan Carpenter
|
|
|
|
Routing - Design Review | 2/28/2019 | | 2/28/2019 | | PASS |
Andrea Tuning
|
|
|
|
Intake Approval | | | 2/21/2019 | | PASS |
Joe Bruce
|
|
|
|
Intake Approval | | | 2/19/2019 | | FAIL |
Joe Bruce
|
|
|
1) The metal building drawings (Sheets 1 through 25) do not have the required space reserved for City approval stamps as specified in the Electronic Plans Submittal Standards. Revise sheets with a blank 4” x 2” space located 3” off the right sheet edge to allow for the title block. See our ePlanReview submittal standards: https://pds.cityofboise.org/media/464072/pdox86_electronic_standards_full_050718.pdf
|
Intake Approval | | | 11/30/2018 | | FAIL |
Joe Bruce
|
|
|
1) Plan sheets do not have the required space reserved for City approval stamps as specified in the Electronic Plans Submittal Standards. Revise sheets with a blank 4” x 2” (4"x4" on cover) space located 3” off the right sheet edge to allow for the title block. Verify ALL plan sheets have the required space for city approval stamp. See our ePlanReview submittal standards: https://pds.cityofboise.org/media/464072/pdox86_electronic_standards_full_050718.pdf
2) Steel erection drawings and calculations are required to be stamped and signed by an Idaho Licensed Structural Engineer. Resubmit drawings with required stamp/signature.
3) Form #310 - Statement of Special Inspections is required for the Structural Steel since the seismic resistance coefficient R value is more than (3) three. See 2015 IBC Section 1705.12.1. Fill out the entire form #310 (with engineers stamp/signature) and include any additional sections as required by the special inspections table on page 2 of the form. Sheet "GN" lists additional special inspections in the notes.
4) The drawing index on sheet A0.0 does not list all the plan sheets submitted. List all the sheets (including the metal building drawings & fire extinguishers) in the drawing index.
5) Fire hydrants could not be located on the site plan. Please indicate the page that the fire hydrants are located on.
6) Upload ESC plans in the drawings folder. These could not be located.
7) Provide details of insulation on the building sections as noted in the checklist. The walls sections do not identify the details for insulation or specify the type of insulation to be installed. The building section on sheet A7.1 does reference the ComCheck report, however it does not match the Energy Compliance COMCheck which calls out a continuous insulation R-Value of R-10. Provide details/sections on how the continuous insulation is attached to the roof and walls.
8) Lighting Compliance (COMCheck) could not be located in the drawings or sheet EN0.1 as stated in the checklist. Provide a lighting compliance (COMCheck) certificate for the new light fixtures.
9) Provide a panel load schedule and summary for the new electrical load of the lights, heater, receptacles, and motorized overhead door.
|
Intake Approval | | | 11/14/2018 | | FAIL |
Joe Bruce
|
|
|
1. The "Structural calculations.pdf" and "S1.4 Structural.pdf" are not documents and should not be uploaded in the documents folder. These belong in the drawings folder and need to be individually uploaded.
2. Fire extinguisher locations is uploaded sideway. - Upload in the correct direction. Sheet has been deleted from the folder.
3. The complete set of drawings has not been uploaded individually. A majority of the drawings are missing. All sheets need to be individually uploaded and follow the electronic plan submittal standards with naming convention. "Complete Set (1).pdf" needs to have each sheet individually uploaded with a file name that lists the sheet number and sheet title. Refer to this document link: https://pds.cityofboise.org/media/464072/pdox86_electronic_standards_full_050718.pdf
4. Building Calculations Page (1) (2).pdf is upload sideways. Revise and upload the correct direction.
5. Plan sheets do not have the required space reserved for City approval stamps as specified in the Electronic Plans Submittal Standards. Revise sheets with a blank 4” x 2” (4"x4" on cover) space located 3” off the right sheet edge to allow for the title block. Verify ALL plan sheets have the required space for city approval stamp.
6. Documents shall be multiple pages as noted in our electronic plan submittal standards. Please upload the checklist as a multiple page PDF.
|
Intake Approval | | | 10/23/2018 | | FAIL |
Joe Bruce
|
|
|
Pre-screen #3 - Joe Bruce - ###-####
1. Fill out and upload checklist #502 into the documents folder. The form must be filled out completely. The items that do not apply to your project need to have the "N/A" boxed checked. Locations of all items must be noted with the location of the plans sheets. This is mandatory and must be uploaded. I could not locate the checklist in the documents folder.
2. All documents need to be uploaded in the correct direction. All documents that were uploaded upside down have been deleted. Please upload these documents in the correct direction.
3. The "Structural calculations.pdf" and "S1.4 Structural.pdf" are not documents and should not be uploaded in the documents folder. These belong in the drawings folder and need to be individually uploaded.
4. All plan sheets are required to be individually uploaded with a minimum sheet size of 18 x 24. These steel building structural drawings do not meet our minimum requirement. Revised and upload.
5. The verification of legal lot form is missing the signature from a subdivision planner. Please contact: Sue Cummings ###-#### for information on how to obtain this signature. This form was also uploaded individually and upside down. Upload the entire document as a single PDF in the documents folder. - I am deleting the individual/upside down sheets from the case.
6. Fire extinguisher locations is uploaded sideway. - Upload in the correct direction. Sheet has been deleted from the folder.
7. All sheets need to be individually uploaded and follow the electronic plan submittal standards with naming convention. "Complete Set (1).pdf" needs to have each sheet individually uploaded with a file name that lists the sheet number and sheet title. Refer to this document link: https://pds.cityofboise.org/media/464072/pdox86_electronic_standards_full_050718.pdf
|
Intake Approval | | | 8/24/2018 | | FAIL |
Joe Bruce
|
|
|
This prescreen has failed due to the following:
1.Fill out and upload form #520 into the documents folder.
2.Structural calculations need to be stamped and signed by an Idaho licensed engineer.
3.All “A-sheets” need to be individually uploaded and follow the electronic plan submittal standards with naming convention.
4.Provide verification of Legal Lot or Parcel form signed and approved by PDS Subdivision Staff.
5.Provide site specific fire flow at hydrants letter from Suez Water or other public water provider.
6.Provide and ESC Plan designed for the specific project, and be prepared and signed by a plan designer certified by Boise City.
7.Provide foundation plan & details stamped and signed by an Idaho licensed engineer.
8.Provide electrical plans stamped and signed by and Idaho licensed engineer with required items on checklist.
|
Intake Approval | | | 8/23/2018 | | FAIL |
|
|
|
|
Application received | | | 2/7/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 7 2018 11:27AM
|
Routing PW Drainage | 7/12/2019 | | | | FAIL |
Brian Murphy
|
|
|
revised C1 grading plan sheet/ keynote 2 is wrong
|
Routing PW Drainage | 7/31/2019 | | | | FAIL |
Brian Murphy
|
|
|
OLD PLAN NOTE 2
|