Letter of compliance/Occupancy | | | 8/2/2019 | | DONE |
|
|
|
|
BLD-Final | 6/10/2019 | 6/10/2019 | 6/10/2019 | P | PASS |
Tony Young
|
|
|
###-####
|
DOC - Permit Finaled | 6/10/2019 | 6/10/2019 | 6/10/2019 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 5/22/2019 | 5/22/2019 | 5/23/2019 | P | NR |
Tony Young
|
|
|
Jim- Phone #: ###-####,, needs historical pass,, needs handrails, steps out of window wells
|
Zoning Approval | 5/23/2019 | 5/23/2019 | 5/23/2019 | | DONE |
Ted Vanegas
|
|
|
|
BLD-Energy code compliance | 3/4/2019 | 3/5/2019 | 3/5/2019 | A | PASS |
Brandon Shaw
|
|
|
Jim Phone #: ###-####
|
BLD-Framing/Rough-in | 2/19/2019 | 2/20/2019 | 2/20/2019 | P | PASS |
Tony Young
|
|
|
Mike Phone #: ###-####
|
BLD-Conference | 2/5/2019 | 2/6/2019 | 2/6/2019 | A | PART |
Tony Young
|
|
|
Mike Phone #: ###-####,, ok to insulate floor/ ceiling area in basement
|
BLD-Wall cover | 1/24/2019 | 1/25/2019 | 1/25/2019 | A | DONE |
Jim Storey
|
|
|
Mike Phone #: ###-####
|
BLD-Wall Bracing | 1/25/2019 | 1/25/2019 | 1/25/2019 | A | PASS |
Jim Storey
|
|
|
Mike Phone #: ###-####
|
BLD-Concrete | 10/26/2018 | 10/29/2018 | 10/29/2018 | A | PASS |
Dave Hannah
|
|
|
rebar-Jeff Phone #: ###-#### baseme walls ok
|
BLD-Footing | 10/3/2018 | 10/4/2018 | 10/4/2018 | A | PASS |
Tony Young
|
|
|
Waylin Phone #: ###-####,, basement footing ok
|
BLD-Footing | 8/24/2018 | 8/27/2018 | 8/27/2018 | A | PART |
Dave Hannah
|
|
|
Waylon Phone #: ###-#### 6 2x2 ftgs ok
|
BLD-Other | 8/9/2018 | 8/9/2018 | 8/9/2018 | P | PART |
Brandon Shaw
|
|
|
West end of North wall
|
BLD-Footing | 8/3/2018 | 8/3/2018 | 8/3/2018 | P | PART |
Tony Young
|
|
|
Waylon Phone #: ###-####,, west footings,, north and south
|
BLD-Foundation | 7/10/2018 | 7/11/2018 | 7/11/2018 | A | PART |
Tony Young
|
|
|
Waylon Phone #: ###-####,, east and east side of the north wall ok to shoot
|
BLD-Foundation | 7/10/2018 | 7/10/2018 | 7/10/2018 | P | NR |
Tony Young
|
|
|
Waylon Phone #: ###-####
|
BLD-Footing | 7/6/2018 | 7/9/2018 | 7/9/2018 | P | PART |
Tony Young
|
|
|
James Phone #: ###-####,, remainder of south and east footing,, and east portion of north footing,, ok
|
BLD-Foundation | 6/26/2018 | 6/27/2018 | 6/27/2018 | A | PART |
Jim Sly
|
|
|
Waylan Phone #: ###-#### 30 feet of South Wall. 6 mil Viqueen in place for waterproofing.
|
BLD-Footing | 6/19/2018 | 6/20/2018 | 6/20/2018 | A | PART |
Jim Sly
|
|
|
Waylon Phone #: ###-#### Approx 15 to 20 feet of South Wall.
|
Issue PAID IN FULL permit | | | 3/19/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 3/16/2018 | | |
|
|
|
|
Permit Ready to Issue | | | 3/16/2018 | | DONE |
|
|
|
called Jim to let know permit
|
Plan assigned to (JAB) Josh | 2/12/2018 | 2/12/2018 | 3/15/2018 | | PASS |
Josh Bogle
|
|
|
1st done - missing footing, egress, energy details
|
Routing - PLAN CHECK | 2/22/2018 | | 3/15/2018 | | PASS |
Josh Bogle
|
|
|
copy fees - 26@.05/ea=1.30 4@.75ea=$3 $4.30 total
|
Inspection Record Card- Bld | | | 3/15/2018 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 3/15/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/15/2018 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes - $4.30 copy fees
|
Routing - MECHANICAL | 2/22/2018 | | 2/22/2018 | | PASS |
Troy James
|
|
|
|
1st review completed | | | 2/20/2018 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 2/16/2018 | | 2/20/2018 | | FAIL |
Josh Bogle
|
|
|
|
Routing - MECHANICAL | 2/12/2018 | | 2/16/2018 | | FAIL |
Troy James
|
|
|
Emailed corrections to western heating
|
Routing Walk-In (Zoning) | 2/12/2018 | 2/12/2018 | 2/12/2018 | P | PASS |
Brent Moore
|
|
|
|
Routing Walk-In (BLD) | 2/12/2018 | 2/12/2018 | 2/12/2018 | P | PASS |
Josh Bogle
|
|
|
took in as level 2, routed to Mech - JAB
|
Application received | | 2/12/2018 | | | |
|
|
|
|