Letter of compliance/Occupancy | | | 8/30/2018 | | DONE |
|
|
|
emailed to joel hirtle with cbh homes
|
BLD-Final | 8/8/2018 | 8/14/2018 | 8/14/2018 | P | PASS |
Jim Sly
|
|
|
Door code is 2468 Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
DOC - Permit Finaled | 8/14/2018 | 8/14/2018 | 8/14/2018 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 7/24/2018 | 7/24/2018 | 7/24/2018 | P | NR |
Jim Sly
|
|
|
garage door code is 2468 Phone #: ###-#### Inspection requested via web by Joel Hirtle Need Mech Final
|
BLD-Energy code compliance | 5/7/2018 | 5/7/2018 | 5/7/2018 | P | PASS |
Brandon Shaw
|
|
|
OK to cover
|
BLD-Framing/Rough-in | 5/4/2018 | 5/4/2018 | 5/6/2018 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Framing/Rough-in | 4/30/2018 | 5/2/2018 | 5/2/2018 | P | NR |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle Need plumb approvaL
|
Plan Modification Accepted | | | 4/23/2018 | | DONE |
|
|
|
New manual j report
|
Routing - MECHANICAL | 4/23/2018 | | 4/23/2018 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 4/17/2018 | 4/19/2018 | 4/19/2018 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Footing | 3/27/2018 | 3/28/2018 | 3/28/2018 | P | PASS |
Jim Sly
|
|
|
Dane Phone #: ###-####
|
Issue PAID IN FULL permit | | | 3/20/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/20/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 2/28/2018 | | |
|
|
|
|
Plan assigned to (M_H) | 2/15/2018 | | 2/28/2018 | | DONE |
Michael Hanson
|
|
|
02/26 sfd L1 ePlan - 1st review completed. Structural deficiencies. MDH
|
Routing - PLAN CHECK | 2/21/2018 | | 2/28/2018 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/28/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 2/28/2018 | | DONE |
|
|
|
met
|
Plan Reviewer's activity | | | 2/21/2018 | | DONE |
Michael Hanson
|
|
|
|
1st review completed | | | 2/21/2018 | | FAIL |
Michael Hanson
|
|
|
Structural deficiencies. MDH
|
Routing - PLAN CHECK | 2/13/2018 | | 2/21/2018 | | FAIL |
Michael Hanson
|
|
|
Structural deficiencies. MDH
|
Routing - MECHANICAL | 2/13/2018 | | 2/16/2018 | | PASS |
Troy James
|
|
|
|
Plan assigned to (RDP) | 2/13/2018 | 2/13/2018 | 2/15/2018 | | DEFR |
Rob Patrick
|
|
|
|
Route to Impact Fee Review | 2/13/2018 | 2/16/2018 | 2/14/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Application received | | | 2/13/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 13 2018 8:17AM
|
Plans ACCEPTED BY PLAN TECH | | | 2/13/2018 | | DONE |
|
|
|
|
Intake Approval | | | 2/13/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/13/2018 | | DONE |
|
|
|
|
Routing - PLANNING | 2/13/2018 | | 2/13/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 2/13/2018 | | 2/13/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 2/13/2018 | | 2/13/2018 | | PASS |
Morgan Webb
|
|
|
|