Permit Information
Permit NumberBLD18-00494
StatusFinaled
Name REILLY CONSTRUCTION LLC
Site Address 4455 E WARM SPRINGS AVE
Project NameAspen Valley Senior Living
Customer Number 
ePlanReviewYes
Description
(ASPEN VALLEY SENIOR LIVING – ASSISTED LIVING AND MEMORY CARE FACILITIES) (DRH17-00409) (3-4-19 PLAN MODIFICATION TO CONSTRUCT TWO SHADE TRELLIS STRUCTURES WITHIN THE COURTYARDS SERVING AN ASSISTED LIVING AND MEMORY CARE FACILITY. EACH COURTYARD WILL HAVE ONE TRELLIS. WORK INCLUDES CONCRETE FOOTINGS INSTALLED BELOW AN EXISTING CONCRETE SLAB ON GRADE, METAL COLUMNS, METAL BEAMS, METAL JOISTS, AND METAL LATTICE OPEN TO THE SKY. ETC.) (9-27-18 PLAN MODIFICATION TO CLARIFY WHERE CEILING RADIATION DAMPERS, COMBINATION SMOKE AND FIRE DAMPERS, AND FIRE DAMPERS ARE REQUIRED.) The fire sprinkler system is used for building area increase and for occupancy. The footings, foundations, under slab plumbing, and concrete slab on grade were done early start permit BLD18-01504. To construct a 47,379 square foot, one story building (33,224 square feet West “building” and 14,155 square feet East “building” separated by a 2-hr fire wall) to be used as an assisted living facility (50 units) and as a memory care facility (16 units having a total floor area of about 6,853 square feet). Within the assisted living facilities, occupants are expected to be able to respond to an emergency situation without assistance. Within the memory care facility, occupants are expected to need assistance to respond to an emergency situation. In both facilities, the need for bed movement is not expected within or between smoke compartments (i.e. no one is confined to their bed). Work is to include concrete footings, concrete stem walls, concrete pedestals, concrete slab on grade with thickened sections to support interior bearing walls, exterior and interior wood stud walls, exterior and interior wood stud bearing walls with headers at openings, exterior and interior wood stud shear walls with hold downs, wood beams and columns, wood trussed roof system with girder trusses, wood roof sheathing, exterior windows, exterior doors, board and batten siding, lap siding, manufactured stone wainscot, wood trellis accent awnings, metal accent awnings, corrugated metal siding, asphalt shingles, standing seam metal roofing, a 6 foot tall masonry screen wall, a 6 foot tall masonry trash enclosure, and a porte cochere. Special Inspection is required for soils, concrete, shear walls, and roof diaphragms. The design for roof trusses is a deferred submittal item. Other work includes 22 “Unit A” assisted living units each having a toilet/shower room (375 sq. ft. each), 26 “Unit B” assisted living units each having a toilet/shower room (467 sq. feet each), 1 “Unit D” assisted living unit having a toilet/shower room (600 sq. ft.), 1 “Unit E” assisted living unit having a toilet/shower room (467 sq. ft.), and 16 “Unit C” memory care sleeping units each having a toilet room (208 sq. ft. each), a Men’s multi-user toilet room accessible to the disabled, a Women’s multi-user toilet room accessible to the disabled, two single-user toilet rooms accessible to the disabled, a commercial kitchen, a Type I grease hood and duct system, a Type II dishwasher hood and duct system, make-up air, exterior grease trap, a 2-hr fire wall to create separate buildings for building area, 1-hr smoke barrier walls to create smoke compartments, millwork, and interior finishes. At least 2 of the assisted living units are required to comply as “accessible units”. The rest are required to comply as “Type B dwelling units”. All of the memory care units will comply as “accessible units”. A separate permit is required for the future gazebo and trellis. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  10/9/2019 DONE
sent 1st late notice on final fees
First Notice 6/2/20196/10/2019 DONE
mailed 6-11
Permanent Occupancy  5/23/2019 DONE
Permanent Occupancy  5/23/2019 DONE
BLD-Final5/21/20195/21/20195/21/2019PPASS
DetailsBrandon Shaw
DOC - Permit Finaled5/21/20195/21/20195/21/2019PPASS
DetailsBrandon Shaw
BLD-Final5/10/20195/10/20195/10/2019PCANC
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by Scott Simons
BLD-Final5/8/20195/10/20195/10/2019APART
DetailsBrandon Shaw
Temp. C of O is OK'd, see FIR18-00690 notes- Tested system. TCO of 10 days granted to verify 6 corrections. Approved by Ron Johnson

ada room strobes do not turn off until reset.
sounders in rooms 101, 107, 118 sound steady (bad base).

2 smokes in beam pockets to be lowered to bottom of beam (greater than .1 less than .4)
FIRE-Final Inspection5/8/20195/10/20195/10/2019PPASS
DetailsMark Scharfen
Passed fire life safety.n e-lights, exit lights and extinguishers all checked.

Scott Phone #: ###-####
Temporary Occupancy5/10/20198/8/20195/10/2019 DONE
DetailsBrittany Hill
PubWorks Occupancy Approval5/10/20195/10/20195/10/2019 DONE
DetailsMike Sheppard
Completed
PubWorks Occupancy Approval5/10/20195/10/20195/10/2019 DONE
DetailsTiffany Lowery
Zoning Approval5/10/20195/10/20195/10/2019 PASS
DetailsKatelyn Menuge
Zoning Final
BLD-Ceiling Grid Inspection4/1/20194/1/20194/1/2019PPASS
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by Scott Simons
Print Occupancy Form  3/6/2019 DONE
CHANGE STATUS TO (ISS)  3/6/2019 DONE
plan mod
OVERRIDE  3/4/2019  
Plan assigned to (CJW)2/26/20192/26/20193/4/2019 PASS
DetailsCarl Westfall
Plan mod - Aspen Valley (Routed to staff)
Routing - PLAN CHECK3/1/2019 3/4/2019 PASS
DetailsCarl Westfall
IBC plan review approved
Routing - Design Review3/4/2019 3/4/2019 PASS
DetailsKatelyn Menuge
No review required for interior courtyards.
Plan Reviewer's activity  3/4/2019 PASS
Plan mod approved
Permit Ready to Issue  3/4/2019 DONE
plan mod
Routing - PLAN CHECK2/27/2019 3/1/2019 PASS
DetailsCarl Westfall
Plan intake review approved
CHANGE STATUS TO (ISS)  3/1/2019 DONE
Print Occupancy Form  3/1/2019 DONE
Plan Modification Accepted  2/27/2019 DONE
Plan Modification Accepted  2/26/2019 DONE
Addendum to add shade trellis structures to interior courtyards of assisted living favility currently under construction.
BLD-Wall cover1/29/20191/29/20191/29/2019PPASS
DetailsBrandon Shaw
Drywall layering area B...
BLD-Energy code compliance1/18/20191/18/20191/18/2019PPART
DetailsBrandon Shaw
Area B exterior walls, ok to insulate...
BLD-Framing/Rough-in1/15/20191/15/20191/15/2019PPASS
DetailsBrandon Shaw
Front and back patio cover soffits...
BLD-Wall cover1/11/20191/11/20191/11/2019PPASS
DetailsBrandon Shaw
Layering drywall Area C...
BLD-Wall cover1/7/20191/8/20191/8/2019APART
DetailsBrandon Shaw
Ceiling drywall layering inspection, rooms only, BLDG C
BLD-Energy code compliance1/2/20191/3/20191/3/2019APART
DetailsBrandon Shaw
Section C energy code compliance
BLD-Other12/27/201812/27/201812/27/2018PPART
DetailsBrandon Shaw
Drywall layer inspection Area D, East wing...
BLD-Other12/20/201812/21/201812/21/2018APART
DetailsBrandon Shaw
Drywall 2nd layer area D, west wing...
BLD-Other12/17/201812/18/201812/18/2018APART
DetailsBrandon Shaw
Area D west wing rooms,drywall...
BLD-Energy code compliance12/11/201812/12/201812/12/2018APART
DetailsBrandon Shaw
Energy code for area D
BLD-Wall cover12/3/201812/4/201812/4/2018APART
DetailsBrandon Shaw
Layering drywall hallway Area A
BLD-Other11/29/201811/30/201811/30/2018APART
DetailsBrandon Shaw
Drywall layering Area A, resident rooms
BLD-Other11/27/201811/28/201811/28/2018APART
DetailsBrandon Shaw
Drywall ceiling joint overlapping, BLDG A
OK to cover with second layer
BLD-Framing/Rough-in11/19/201811/20/201811/20/2018APART
DetailsBrandon Shaw
Framing Area A Phone #: ###-#### Inspection requested via web by Scott Simons
BLD-Framing/Rough-in11/19/201811/19/201811/19/2018PCANC
DetailsJim Sly
Framing Area A Phone #: ###-#### Inspection requested via web by Scott Simons
BLD-Energy code compliance11/13/201811/14/201811/14/2018PPART
DetailsBrandon Shaw
Tenting and spray foam
OK to insulate exterior...
BLD-Framing/Rough-in11/7/201811/8/201811/8/2018APART
DetailsBrandon Shaw
OK to insulate exterior walls, BLDG A...
BLD-Other11/6/201811/6/201811/6/2018PDONE
DetailsBrandon Shaw
Smoke dampers, access panels, and fire wall penetrations...
CHANGE STATUS TO (ISS)  10/31/2018 DONE
per Brandon-was finaled by mistake
BLD-Conference10/30/201810/30/201810/30/2018PDONE
DetailsBrandon Shaw
Finaled by mistake, per Brandon Shaw 30OCT2018
DOC - Permit Finaled10/30/201810/30/201810/30/2018PPASS
DetailsBrandon Shaw
BLD-Conference10/24/201810/26/201810/26/2018ACANC
DetailsBrandon Shaw
Conference on area B fire rated partitions and ceiling height changes Phone #: ###-#### Inspection requested via web by Scott Simons
BLD-Other10/23/201810/23/201810/23/2018PDONE
DetailsBrandon Shaw
Fire wall final layer inspection and also final shear wall inspection Phone #: ###-#### Inspection requested via web by Scott Simons
BLD-Wall Bracing10/23/201810/23/201810/23/2018PPART
DetailsBrandon Shaw
Exterior shear done...
BLD-Other10/23/201810/23/201810/23/2018PPART
DetailsBrandon Shaw
Fire Walls, BLDG's C & D
BLD-Conference10/17/201810/17/201810/17/2018PDONE
DetailsBrandon Shaw
Clarifications on firewall and fire chase requirements

Smoke partition, BLDG's C/D...
Exhaust and Make-up air, O2 room, BLDG A...
BLD-Wall cover10/10/201810/10/201810/10/2018PPART
DetailsBrandon Shaw
Firewall - Second layer, South side, BLD C
First layer, North side, BLD C...
OVERRIDE  9/27/2018  
Plan assigned to (CJW)9/18/20189/18/20189/27/2018 PASS
DetailsCarl Westfall
Plan Mod - Aspen Valley (routed back to applicant)
CHANGE STATUS TO (ISS)  9/27/2018 DONE
Inspection Record Card- Bld  9/27/2018 DONE
(F) Reprint permit  9/27/2018 DONE
Routing - PLAN CHECK9/26/2018 9/27/2018 PASS
DetailsCarl Westfall
Plan Reviewer's activity  9/27/2018 PASS
Plan mod approved
Permit Ready to Issue  9/27/2018 DONE
Plan mod - PLEASE do no re issue-no cert of val attached for plan mod so please have them fill one out
BLD-Other9/25/20189/26/20189/26/2018APART
DetailsBrandon Shaw
Fire wall, first layer
BLD-Wall Bracing9/25/20189/26/20189/26/2018APART
DetailsBrandon Shaw
BLDG C
Plan resubmittals received  9/26/2018 DONE
Plan Modification Accepted  9/20/2018 DONE
Workflow in ePlanReview received
Routing - PLAN CHECK9/20/2018 9/20/2018 FAIL
DetailsCarl Westfall
The 1st plan mod - 1st review did not pass. Revisions were required. Workflow sent back to the applicant.
Plan resubmittals requested  9/20/2018 DONE
Plan Modification Accepted  9/18/2018 DONE
Mechanical Modifications removing fire dampers, smoke dampers and economzers on select furnaces per architectural info. safety review and metting with mechical constractor
BLD-Concrete9/12/20189/13/20189/13/2018PPASS
DetailsBrandon Shaw
Finish slab footings and floor for Area B Phone #: ###-#### Inspection requested via web by Scott Simons
BLD-Energy code compliance9/10/20189/11/20189/11/2018PPART
DetailsBrandon Shaw
Exterior gypsum inspection area d and area A
BLD-Framing/Rough-in8/26/20188/27/20188/27/2018APART
DetailsBrandon Shaw
Shear wall inspection for west wing area
BLD-Foundation8/24/20188/24/20188/24/2018PPASS
DetailsBrandon Shaw
Trash enclosure and screen wall
BLD-Wall Bracing8/23/20188/23/20188/23/2018PPART
DetailsBrandon Shaw
Memory care side- work in progress
BLD-Footing8/22/20188/23/20188/23/2018PPASS
DetailsBrandon Shaw
Trash encloser // Dane Phone #: ###-####
Issue PAID IN FULL permit  7/3/2018 DONE
Print Occupancy Form  7/3/2018 DONE
OVERRIDE  7/2/2018  
Plan assigned to (CJW)3/6/20183/6/20187/2/2018 PASS
DetailsCarl Westfall
* (3rd done) (Apr 9 - 25 days) (Mar 6 PI) (90 sheets) Aspen Valley Senior Living
Routing - FIRE6/27/2018 7/2/2018 PASS
DetailsErika Akin
Attached comments to case
PLANS/APPL TAKEN TO FRONT DESK  7/2/2018 DONE
Permit Ready to Issue  7/2/2018 DONE
NEED
GC FORM
REVISED VALUE
Routing PW Street Lights6/27/2018 6/28/2018 PASS
DetailsTom Marshall
Plan resubmittals received  6/27/2018 DONE
Routing - PLAN CHECK6/27/2018 6/27/2018 PASS
DetailsCarl Westfall
3rd review
Routing - FIRE6/13/20186/20/20186/20/2018 FAIL
DetailsErika Akin
Attached comments to case and emailed architect
Plan resubmittals requested  6/20/2018 DONE
Routing - MECHANICAL6/13/2018 6/19/2018 PASS
DetailsTroy James
Routing Off Site - STRUCTURAL6/13/2018 6/18/2018 PASS
DetailsCarl Westfall
Jordan Terry (KPFF)
Routing - PUBLIC WORKS6/13/2018 6/13/2018 PASS
DetailsRachael Beierle
Some sinks removed
Routing PW Sewer Rating6/13/2018 6/13/2018 PASS
DetailsRachael Beierle
some sinks removed. no change in rating. rated per room and not per fixture.
Routing PW Drainage6/13/2018 6/13/2018 PASS
DetailsBrian Murphy
Brian needs to move approval stamp to the most recent version
Routing - PLAN CHECK6/11/2018 6/13/2018 PASS
DetailsCarl Westfall
Pending approval by structural
Routing PW Street Lights6/13/2018 6/13/2018 FAIL
DetailsTom Marshall
Routing PW Sewer Design6/13/2018 6/13/2018 PASS
DetailsDeAnn Brown
Sewer review and work completed under GRD17-00069.
Plan resubmittals received  6/11/2018 DONE
Route to Impact Fee Review4/17/20184/20/20184/23/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Plan Reviewer's activity  4/20/2018 DONE
The Architect uploaded revised structural sheets. The Consultant Structural Engineer was asked if he could start his 2nd review while the Architect continues to resolve items and upload drawings. The Architect is seeking a footing, foundation, underslabing plumbing, and concrete slab on grade permit. The consultant does not have a task in ePlanReview.
Routing - PLAN CHECK3/6/2018 4/17/2018 FAIL
DetailsCarl Westfall
Revised drawings required
1st review completed  4/17/2018 DONE
Plan resubmittals requested  4/17/2018 DONE
Routing - FIRE3/6/20183/6/20183/20/2018 FAIL
DetailsScott Arellano
Comments attached in BLD18-00774
Routing Off Site - STRUCTURAL3/6/2018 3/20/2018 FAIL
DetailsCarl Westfall
Jordan Terry (KPFF)
Routing - MECHANICAL3/6/2018 3/13/2018 FAIL
DetailsTroy James
Routing PW Sewer Design3/7/2018 3/12/2018 FAIL
DetailsDeAnn Brown
See notes in eplanreview
Routing PW Solid Waste3/7/2018 3/8/2018 PASS
DetailsEvan Carpenter
Routing PW Environmental3/7/2018 3/8/2018 PASS
DetailsRick Christenson
Exterior Grease Interceptor 1500 Gallon shown
Routing PW Street Lights3/7/2018 3/8/2018 FAIL
DetailsTom Marshall
Routing - PLUMBING3/6/2018 3/8/2018 PASS
DetailsBill VanDegrift
Per plan and ISPC.
Routing - PLANNING3/6/2018 3/8/2018 PASS
DetailsKatelyn Menuge
DRH17-00409
Routing - Design Review3/6/2018 3/8/2018 PASS
DetailsKatelyn Menuge
DRH17-00409
Routing - Addressing3/6/2018 3/7/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS3/6/2018 3/7/2018 PASS
DetailsRachael Beierle
Routing - Erosion and Sediment3/6/2018 3/7/2018 PASS
DetailsMichael Zawacki
Refer to ESC17-01389
Routing PW Drainage3/7/2018 3/7/2018 PASS
DetailsBrian Murphy
Intake Approval  3/6/2018 PASS
Intake Approval  2/14/2018 FAIL
DetailsJulie Romig
Need: 1. Verification of Legal Lot or Parcel Form signed by PDS Subdivision Staff. Please contact Todd Tucker at TTucker@cityofboise.org.
2. Completed form #310 with Design Professional's information, Owner's information and owner's signature.
3. The City of Boise adopted the 2015 codes on Jan. 1, 2018. Drawings state the 2012 codes as the applicable codes. Please submit a letter requesting to have the application reviewed under the 2012 codes.
Application received  2/13/2018 DONE
Application submitted via PDS Online on Feb 13 2018 1:20PM