Permanent Occupancy | | | 3/14/2018 | | DONE |
|
|
|
|
BLD-Final | 2/26/2018 | 2/27/2018 | 2/27/2018 | P | PASS |
Jim Sly
|
|
|
Matt Phone #: ###-####
|
FIRE-Final Inspection | 2/26/2018 | 2/27/2018 | 2/27/2018 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Matt is going to remove the two non-functional exit signs prior to a building inspection
Matt Phone #: ###-####
|
Issue PAID IN FULL permit | | | 2/23/2018 | | DONE |
|
|
|
|
Plan assigned to (JG) | 2/14/2018 | 2/14/2018 | 2/16/2018 | | PASS |
Javier Guzman
|
|
|
2/20 L2 Idaho Survey Group Occ Eval
|
Routing - PLAN CHECK | 2/14/2018 | | 2/16/2018 | | PASS |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 2/16/2018 | | DONE |
Javier Guzman
|
|
|
|
1st review completed | | | 2/16/2018 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/16/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/16/2018 | | DONE |
Christina Prado
|
|
|
All met
|
Telephone call | | | 2/16/2018 | | DONE |
Christina Prado
|
|
|
Called Matt to advise permit is ready and gave fee due
|
Print Occupancy Form | | | 2/16/2018 | | DONE |
Christina Prado
|
|
|
|
Routing - FIRE | 2/14/2018 | 2/14/2018 | 2/14/2018 | | PASS |
Scott Arellano
|
|
|
No comments attached. Basic life safety items to be field verified.
|
Plans ACCEPTED BY PLAN TECH | | | 2/14/2018 | | DONE |
|
|
|
|
Intake Approval | | | 2/14/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/14/2018 | | DONE |
|
|
|
|
Routing - Addressing | 2/14/2018 | | 2/14/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 2/14/2018 | | 2/14/2018 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | 2/14/2018 | | | |
|
|
|
|