BLD-Final | 4/17/2018 | 4/19/2018 | 4/19/2018 | A | DONE |
Mike Jordan
|
|
|
Install 2 sets of letters reading MOVIES. One on North elevation and 1 on West elevation. Primary power to the West elevation done on permit ElE18-01356. Primary power on North elevation existing no changes. Phone #: ###-#### Inspection requested via web by Ken Olsen
|
DOC - Permit Finaled | 4/19/2018 | 4/19/2018 | 4/19/2018 | P | PASS |
Mike Jordan
|
|
|
|
Permit Ready to Issue | | | 2/28/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/28/2018 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 2/19/2018 | 2/19/2018 | 2/19/2018 | | DONE |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 2/19/2018 | | 2/19/2018 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/19/2018 | | DONE |
|
|
|
|
Intake Approval | | | 2/19/2018 | | PASS |
|
|
|
|
1st review completed | | | 2/19/2018 | | DONE |
|
|
|
|
Application received | | | 2/14/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 14 2018 3:27PM
|
First Notice | 4/19/2018 | 4/19/2018 | | | |
Mike Jordan
|
|
|
|