BLD-Final | 10/1/2018 | 10/1/2018 | 10/1/2018 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
DOC - Permit Finaled | 10/1/2018 | 10/1/2018 | 10/1/2018 | P | PASS |
Brandon Shaw
|
|
|
|
CHANGE STATUS TO (ISS) | | | 10/1/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/1/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 9/28/2018 | | |
|
|
|
|
Plan assigned to (RDP) | 9/20/2018 | 9/20/2018 | 9/28/2018 | | DONE |
Rob Patrick
|
|
|
Plan Mod; recevied 9/20
|
Routing - PLAN CHECK | 9/28/2018 | | 9/28/2018 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/28/2018 | | DONE |
Rob Patrick
|
|
|
Please add 1 hour Plan Mod Fee.
|
Permit Ready to Issue | | | 9/28/2018 | | DONE |
|
|
|
PLAN MOD
|
Plan Modification Accepted | | | 9/19/2018 | | DONE |
|
|
|
as per Chelsea-plan mod in e plan-revising framing at the front wall
|
BLD-Final | 9/4/2018 | 9/4/2018 | 9/5/2018 | P | FAIL |
Brandon Shaw
|
|
|
Need revised plans and Engineering submitted, as previously noted...
|
BLD-Energy code compliance | 7/2/2018 | 7/3/2018 | 7/3/2018 | A | PASS |
Brandon Shaw
|
|
|
Corrections SAT...
|
BLD-Framing/Rough-in | 6/22/2018 | 6/25/2018 | 6/25/2018 | A | FAIL |
Brandon Shaw
|
|
|
Need revised plans and Engineering See correction notice
Ok to insulate
|
BLD-Framing/Rough-in | 6/12/2018 | 6/12/2018 | 6/12/2018 | P | NR |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Other | 6/11/2018 | 6/12/2018 | 6/12/2018 | A | PASS |
Brandon Shaw
|
|
|
Soffit Inspection Phone #: ###-#### Inspection requested via web by Kyle Seick
|
Plan Modification Accepted | | | 5/30/2018 | | DONE |
|
|
|
resubmitted manual j report
|
Routing - MECHANICAL | 5/30/2018 | | 5/30/2018 | | PASS |
Troy James
|
|
|
New manual j report
|
BLD-Wall Bracing | 5/22/2018 | 5/22/2018 | 5/22/2018 | A | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Foundation | 4/4/2018 | 4/4/2018 | 4/4/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Conference | 4/4/2018 | 4/4/2018 | 4/4/2018 | P | CANC |
Brandon Shaw
|
|
|
As early as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion
|
BLD-Footing | 4/3/2018 | 4/3/2018 | 4/3/2018 | P | PASS |
Brandon Shaw
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion
|
BLD-Foundation | 3/28/2018 | 3/28/2018 | 3/29/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 3/23/2018 | 3/26/2018 | 3/26/2018 | A | PASS |
Brandon Shaw
|
|
|
Work in progress
|
OVERRIDE | | | 3/12/2018 | | |
|
|
|
|
Plan assigned to (RDP) | 2/16/2018 | 2/16/2018 | 3/12/2018 | | DONE |
Rob Patrick
|
|
|
3/1 sfd L1 ePlan. Failed, need more details.
|
Issue PAID IN FULL permit | | | 3/12/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/12/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/12/2018 | | 3/12/2018 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/12/2018 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 3/12/2018 | | DONE |
|
|
|
Met
|
1st review completed | | | 3/1/2018 | | FAIL |
Rob Patrick
|
|
|
|
Routing - MECHANICAL | 2/16/2018 | | 2/26/2018 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 2/16/2018 | 2/19/2018 | 2/20/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 2/16/2018 | | 2/16/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 2/16/2018 | | 2/16/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 2/16/2018 | | 2/16/2018 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/16/2018 | | DONE |
|
|
|
|
Intake Approval | | | 2/16/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/16/2018 | | DONE |
|
|
|
|
Application received | | | 2/15/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 15 2018 12:25PM
|
Routing - PLAN CHECK | 2/16/2018 | | | | FAIL |
Rob Patrick
|
|
|
|