Print Statement | | | 10/1/2018 | | DONE |
|
|
|
|
First Notice | | 8/13/2018 | 9/6/2018 | | DONE |
|
|
|
mailed 9-10-18
|
Permanent Occupancy | | | 8/3/2018 | | DONE |
|
|
|
|
BLD-Final | 8/2/2018 | 8/3/2018 | 8/2/2018 | A | PASS |
Jim Sly
|
|
|
Tucker Phone #: ###-#### OK for Perm Occ.
|
BLD-Final | 7/30/2018 | 7/31/2018 | 7/31/2018 | A | PART |
Jim Sly
|
|
|
Requesting partial for TCO. Phone #: ###-#### Inspection requested via web by Tucker Robb OK for Temp Occ. OK for Perm Occ. when Plumbing final is Perm.
|
BLD-Final | 7/30/2018 | 7/30/2018 | 7/30/2018 | P | NR |
Jim Sly
|
|
|
Please call Tucker Robb when on the way. Phone #: ###-#### Inspection requested via web by Tucker Robb Need Plumbing final.
|
FIRE-Final Inspection | 7/30/2018 | 7/30/2018 | 7/30/2018 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 7/27/2018 | 7/30/2018 | 7/30/2018 | A | CANC |
Jim Sly
|
|
|
Final inspection for occupancy. Please call ahead. Phone #: ###-#### >> Inspection requested via web by Tucker Robb Inspection cancelled from web by: Tucker Robb
|
FIRE-Final Inspection | 7/25/2018 | 7/27/2018 | 7/27/2018 | P | FAIL |
Troy Cobbley
|
|
|
Need the project related fire alarm permit finaled then life safety can be passed
Fire/Life safety. Please call Tucker when on the way. Phone #: ###-#### Inspection requested via web by Tucker Robb
|
FIRE-Conference | 7/10/2018 | 7/10/2018 | 7/10/2018 | P | DONE |
Troy Cobbley
|
|
|
The project superintendant and I discussed the requirement for a fire alarm permit for the work being performed and also the need for a racking permit for the existing storage racks that exceed 8'
|
BLD-Conference | 6/12/2018 | 6/13/2018 | 6/13/2018 | A | DONE |
Jim Sly
|
|
|
Requesting a a conference to discuss existing exit lights. The plan reviewer noted that exit lights shall be provided at all exits in the building. Existing exits already have exit lights and I want to make sure the inspector is ok with those and that the note in my drawings does not require replacement of existing.
Please call ahead. Phone #: ###-#### Inspection requested via web by Tucker Robb
|
BLD-Energy code compliance | 5/25/2018 | 5/29/2018 | 5/29/2018 | P | PASS |
Jim Sly
|
|
|
Requesting insulation and wall cover inspection. Please call Tucker when on the way. Phone #: ###-#### Inspection requested via web by Tucker Robb
|
BLD-Wall cover | 5/25/2018 | 5/25/2018 | 5/25/2018 | A | CANC |
Jim Sly
|
|
|
Exterior wall insulation inspection for cover. Please call Tucker when on the way. Phone #: ###-#### >> Inspection requested via web by Tucker Robb Inspection cancelled from web by: Tucker Robb
|
BLD-Framing/Rough-in | 5/11/2018 | 5/14/2018 | 5/14/2018 | A | PART |
Jim Storey
|
|
|
Please call Tucker Robb when inspector is in route. Phone #: ###-#### Inspection requested via web by Tucker Robb// framing ok pending ele aproval/ need ec insp.
|
Plan assigned to (CDM) | 3/24/2018 | 3/24/2018 | 4/11/2018 | | PASS |
Carl D Madsen
|
|
|
Restoration services L-3 1st comp.
|
Routing - PLAN CHECK | 3/30/2018 | | 4/11/2018 | | PASS |
Carl D Madsen
|
|
|
|
Routing - Design Review | 4/10/2018 | | 4/11/2018 | | PASS |
Katelyn Menuge
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/11/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/11/2018 | | DONE |
|
|
|
Need:
Revised cert of value from GC
|
Issue PAID IN FULL permit | | | 4/11/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/11/2018 | | DONE |
|
|
|
|
Routing - FIRE | 4/9/2018 | 4/9/2018 | 4/9/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - Design Review | 3/30/2018 | | 4/2/2018 | | FAIL |
Sarah Schafer
|
|
|
Gates do not meet minimum allowed distance from street.
|
Route to Impact Fee Review | 3/24/2018 | 3/27/2018 | 3/26/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Plan assigned to (JG) | 2/26/2018 | 2/26/2018 | 3/24/2018 | | DEFR |
Javier Guzman
|
|
|
3/16 L3 Complete restoration services ePlan
|
Routing - PLAN CHECK | 2/26/2018 | | 3/24/2018 | | FAIL |
Carl D Madsen
|
|
|
Plan review repot in the agency comments folder
|
1st review completed | | | 3/24/2018 | | DONE |
|
|
|
|
Routing - MECHANICAL | 2/26/2018 | | 3/7/2018 | | PASS |
Troy James
|
|
|
|
Routing PW Environmental | 2/27/2018 | | 3/5/2018 | | PASS |
Rick Christenson
|
|
|
|
Routing - FIRE | 2/26/2018 | 2/26/2018 | 3/2/2018 | | FAIL |
Scott Arellano
|
|
|
Attached comments to case and emailed architect
|
Routing - PLANNING | 2/26/2018 | | 2/28/2018 | | PASS |
Susan Riggs
|
|
|
|
Routing - Addressing | 2/26/2018 | | 2/27/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 2/26/2018 | | 2/27/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLUMBING | 2/26/2018 | | 2/27/2018 | | PASS |
Bill VanDegrift
|
|
|
1) additional cross connection protection may be required.
2) verify venting cross sectional requirements.
3) verify premise protection.
4) provide asse 1070 mixing valves at the public lavs.
|
Routing - Design Review | 2/26/2018 | | 2/27/2018 | | FAIL |
Sarah Schafer
|
|
|
A zoning certificate is required for the exterior modifications.
|
Intake Approval | | | 2/26/2018 | | PASS |
|
|
|
|
Intake Approval | | | 2/23/2018 | | FAIL |
|
|
|
|
Intake Approval | | | 2/20/2018 | | FAIL |
|
|
|
|
Intake Approval | | | 2/19/2018 | | FAIL |
|
|
|
|
Application received | | | 2/16/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 16 2018 3:31PM
|