BLD-Final | 11/9/2018 | 11/9/2018 | 11/9/2018 | P | PASS |
Brandon Shaw
|
|
|
Kyle-as per Kyle plumbing signed off on a final tag that''s in the garage so i also assigned a plumbing plumbing Phone #: ###-####
|
DOC - Permit Finaled | 11/9/2018 | 11/9/2018 | 11/9/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 11/9/2018 | 11/9/2018 | 11/9/2018 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 3.25
|
(F) Reprint permit | | | 11/9/2018 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 11/9/2018 | | DONE |
|
|
|
plan mod
|
OVERRIDE | | | 9/19/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 9/18/2018 | 9/18/2018 | 9/19/2018 | | DONE |
Brian McGowan
|
|
|
09/18 Plan Mod - Corrections required.
|
Routing - PLAN CHECK | 9/19/2018 | | 9/19/2018 | | PASS |
Brian McGowan
|
|
|
|
Plan Reviewer's activity | | | 9/19/2018 | | DONE |
Brian McGowan
|
|
|
Please add 1/2 hour of Plan Review Fee.
|
Permit Ready to Issue | | | 9/19/2018 | | DONE |
|
|
|
Plan Mod Approved
DO NOT REISSUE (plan mod fees due)
|
Routing - PLAN CHECK | 9/5/2018 | | 9/18/2018 | | FAIL |
Brian McGowan
|
|
|
|
Telephone call | | | 9/17/2018 | | DONE |
|
|
|
Chelsea called, plan mod submitted on 9-5-18-left note on BJM's monitor asking him if he can do the plan review
|
BLD-Other | 9/13/2018 | 9/13/2018 | 9/13/2018 | A | PASS |
Brandon Shaw
|
|
|
Soffit
|
BLD-Energy code compliance | 9/12/2018 | 9/13/2018 | 9/13/2018 | A | PASS |
Brandon Shaw
|
|
|
Kyle-Kyle said plan mod that''s in for review has nothing to do with the inspections. so approved pans are not on the job site for some of the project Phone #: ###-####
|
BLD-Framing/Rough-in | 9/4/2018 | 9/4/2018 | 9/5/2018 | P | PASS |
Brandon Shaw
|
|
|
OK to insulate
|
Plan assigned to (BJM) | 9/5/2018 | 9/5/2018 | 9/5/2018 | | DONE |
Brian McGowan
|
|
|
|
CHANGE STATUS TO (REV) | | | 9/5/2018 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 9/5/2018 | | DONE |
|
|
|
Replacing beams with box girders
|
BLD-Framing/Rough-in | 8/31/2018 | 8/31/2018 | 8/31/2018 | P | PASS |
Brandon Shaw
|
|
|
Corrections SAT... OK to insulate
|
BLD-Wall Bracing | 7/3/2018 | 7/3/2018 | 7/3/2018 | P | PART |
Brandon Shaw
|
|
|
Exterior only- Work in progress
Provide floor truss engineering for missing beam and hold downs
|
BLD-Foundation | 5/3/2018 | 5/4/2018 | 5/4/2018 | A | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 5/1/2018 | 5/2/2018 | 5/2/2018 | A | PASS |
Brandon Shaw
|
|
|
As early as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion
|
Issue PAID IN FULL permit | | | 4/19/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/19/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 4/5/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 2/20/2018 | 2/20/2018 | 4/5/2018 | | DONE |
Brian McGowan
|
|
|
Resubmittals received-1st review complete - FAIL- 3-5 sfd L1 ePlan
|
Routing - PLAN CHECK | 4/5/2018 | | 4/5/2018 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/5/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 4/5/2018 | | DONE |
|
|
|
Met
|
Plan Reviewer's activity | | | 3/5/2018 | | DONE |
Brian McGowan
|
|
|
Requested by Chelsea to resolve 18-00566 issues before working on this permit since they are the same plan.
|
Routing - PLAN CHECK | 2/20/2018 | | 3/2/2018 | | FAIL |
Brian McGowan
|
|
|
Need to verify several beams and headers.
|
1st review completed | | | 3/2/2018 | | FAIL |
Brian McGowan
|
|
|
Need to verify several beams and headers.
|
Routing - MECHANICAL | 2/20/2018 | | 2/27/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Route to Impact Fee Review | 2/20/2018 | 2/23/2018 | 2/21/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 2/20/2018 | | 2/20/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 2/20/2018 | | 2/20/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 2/20/2018 | | 2/20/2018 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/20/2018 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 2/20/2018 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/20/2018 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 2/16/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 16 2018 4:24PM
|