Print Statement | | | 6/24/2019 | | DONE |
|
|
|
|
Meeting | | | 6/24/2019 | | DONE |
|
|
|
emailed court about final value on plumbing
|
Third Notice | | 5/11/2019 | 6/7/2019 | | DONE |
|
|
|
mailed 6-10 with first follow up letter
|
First Follow up | | | 6/7/2019 | | DONE |
|
|
|
|
Third Notice | | 4/13/2019 | 5/6/2019 | | DONE |
|
|
|
mailed 5-10-19
|
Third Notice | | 3/16/2019 | 4/8/2019 | | DONE |
|
|
|
mailed 4/11
|
Second Notice | | 2/17/2019 | 3/11/2019 | | DONE |
|
|
|
mailed 3-12-19
|
Letter of compliance/Occupancy | | | 3/6/2019 | | DONE |
|
|
|
|
Letter of compliance/Occupancy | | | 3/6/2019 | | DONE |
|
|
|
|
First Notice | 1/31/2019 | 1/31/2019 | 2/7/2019 | | DONE |
Jim Storey
|
|
|
mailed 2-11-19
|
FIRE-Final Inspection | 1/30/2019 | 1/31/2019 | 1/31/2019 | P | PASS |
Jim Page
|
|
|
Final life fire safety inspection for core and shell complete.
Michael Phone #: ###-####
|
BLD-Final | 1/30/2019 | 1/31/2019 | 1/31/2019 | P | PASS |
Jim Storey
|
|
|
Michael Phone #: ###-####
|
DOC - Permit Finaled | 1/31/2019 | 1/31/2019 | 1/31/2019 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 1/29/2019 | 1/30/2019 | 1/30/2019 | P | CANC |
Jim Page
|
|
|
Michael Phone #: ###-####-1--30-19 Mike called and cancelled
|
BLD-Conference | 1/23/2019 | 1/24/2019 | 1/24/2019 | A | DONE |
Jim Storey
|
|
|
Courtesy inspection for mezzanine walls // Mike Phone #: ###-####
|
BLD-Framing/Rough-in | 1/22/2019 | 1/23/2019 | 1/23/2019 | A | DEFR |
Jim Storey
|
|
|
Courtesy inspection for mezzanine walls // Mike Phone #: ###-#### out of time
|
BLD-Energy code compliance | 1/22/2019 | 1/22/2019 | 1/22/2019 | P | PASS |
Jim Storey
|
|
|
Mike Phone #: ###-#### ele rm ok to cover
|
BLD-Framing/Rough-in | 1/17/2019 | 1/17/2019 | 1/17/2019 | P | PASS |
Jim Storey
|
|
|
Michael Phone #: ###-#### east end of ele rm ok to cover.
|
BLD-Conference | 1/14/2019 | 1/16/2019 | 1/16/2019 | P | PASS |
Jim Storey
|
|
|
Mike Phone #: ###-####
|
BLD-Grading Inspection | 1/10/2019 | 1/11/2019 | 1/11/2019 | A | NR |
Jim Storey
|
|
|
Michael Pearson On Site Superintendent Phone #: ###-#### Inspection requested via web by Larry Monkarsh
|
BLD-Energy code compliance | 1/10/2019 | 1/11/2019 | 1/11/2019 | A | NR |
Jim Storey
|
|
|
Michael Pearson On Site Superintendent Phone #: ###-#### Inspection requested via web by Larry Monkarsh
|
BLD-Framing/Rough-in | 12/26/2018 | 12/26/2018 | 12/26/2018 | P | PART |
Jim Storey
|
|
|
Mike Phone #: ###-#### need ti number// backing for ada// all trades signed off.
|
BLD-Wall Bracing | 12/3/2018 | 12/3/2018 | 12/3/2018 | P | PASS |
Jim Storey
|
|
|
Bryce Phone #: ###-####
|
BLD-Framing/Rough-in | 11/27/2018 | 11/27/2018 | 11/27/2018 | P | PASS |
Jim Storey
|
|
|
Bruce Phone #: ###-#### ele room ok/ east demizing wall ok
|
BLD-Framing/Rough-in | 11/14/2018 | 11/15/2018 | 11/15/2018 | A | PASS |
Jim Storey
|
|
|
Brice Phone #: ###-#### exterior roofs at vestables ok to cover
|
BLD-Other | 10/18/2018 | 10/18/2018 | 10/23/2018 | P | PASS |
Jim Storey
|
|
|
Bryce-roof deck-2nd half Phone #: ###-#### si
|
BLD-Framing/Rough-in | 10/12/2018 | 10/15/2018 | 10/15/2018 | A | PASS |
Jim Storey
|
|
|
Bryce-decking on a reroof Phone #: ###-#### si passed for decking/ need verifacation of 2 inch poly iso to meet 11.6 r
|
BLD-Other | 8/22/2018 | 8/27/2018 | 8/27/2018 | P | PART |
Jim Storey
|
|
|
rebar insp // Bryce Phone #: ###-#### placed w s/i
|
BLD-Other | 8/22/2018 | 8/24/2018 | 8/24/2018 | P | PASS |
Jim Storey
|
|
|
rebar insp // Bryce Phone #: ###-#### si on site
|
BLD-Foundation | 8/14/2018 | 8/15/2018 | 8/15/2018 | P | PASS |
Jim Storey
|
|
|
rebar // Bryce Phone #: ###-#### rebar ok pending si reports
|
BLD-Concrete | 8/6/2018 | 8/8/2018 | 8/8/2018 | P | PASS |
Jim Storey
|
|
|
please call ahead // Bryce Phone #: ###-#### pending si report
|
BLD-Foundation | 7/26/2018 | 7/31/2018 | 8/1/2018 | P | PART |
Jim Storey
|
|
|
Bryce-rebar Phone #: ###-#### pending si report
|
BLD-Concrete | 7/23/2018 | 7/25/2018 | 7/25/2018 | P | PART |
Jim Storey
|
|
|
rebar- Bryce Phone #: ###-#### wip ok pending si report
|
BLD-Concrete | 7/23/2018 | 7/23/2018 | 7/23/2018 | A | PASS |
Jim Storey
|
|
|
si pannels as noted on site
|
BLD-Footing | 7/13/2018 | 7/16/2018 | 7/16/2018 | P | PASS |
Jim Storey
|
|
|
Carl Phone #: ###-#### north east ft ok ufer ground in place ok/ pannels wip
|
BLD-Other | 6/8/2018 | 6/11/2018 | 6/11/2018 | P | PASS |
Jim Storey
|
|
|
vipor bearer- Carl Phone #: ###-#### south end slab on grade ok to cover
|
BLD-Foundation | 5/29/2018 | 5/30/2018 | 5/30/2018 | P | PASS |
Jim Storey
|
|
|
rebar // Carl Phone #: ###-#### north slab ok
|
BLD-Other | 5/23/2018 | 5/24/2018 | 5/24/2018 | A | DEFR |
Jim Storey
|
|
|
Carl -for conduits underneath the footing Phone #: ###-#### need ele permit and ele insp.
|
BLD-Footing | 5/22/2018 | 5/23/2018 | 5/23/2018 | A | PASS |
Jim Storey
|
|
|
Carl Phone #: ###-#### interior ft and rebar ok area a pending si reports
|
Issue PAID IN FULL permit | | | 5/11/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/11/2018 | | DONE |
|
|
|
|
(F) Reprint permit | | | 5/11/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/11/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 5/8/2018 | | |
|
|
|
|
Permit Ready to Issue | | | 5/8/2018 | | DONE |
|
|
|
ALL MET
Need:
GC form
Revised cert of value from GC
RP
|
Plan assigned to (JAR) | 3/1/2018 | 3/1/2018 | 5/7/2018 | | DONE |
Julie Romig
|
|
|
**1st Rev Comp - 3rd Rec'd 05/03 - 502 Federal Way Industrial Bldg
|
Routing - PLAN CHECK | 5/3/2018 | | 5/7/2018 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/7/2018 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 4/24/2018 | | 5/1/2018 | | PASS |
Julie Romig
|
|
|
2nd Review
|
Routing - FIRE | 4/24/2018 | 4/24/2018 | 4/30/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
revised plans addressed comments resubmittal eplan
|
Routing PW Solid Waste | 4/24/2018 | | 4/25/2018 | | PASS |
Evan Carpenter
|
|
|
|
Application received | | 4/24/2018 | 4/24/2018 | | DONE |
|
|
|
|
Routing PW Drainage | 4/24/2018 | | 4/24/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Sewer Design | 4/24/2018 | | 4/24/2018 | | PASS |
DeAnn Brown
|
|
|
|
Routing - PLAN CHECK | 4/24/2018 | | 4/24/2018 | | FAIL |
Julie Romig
|
|
|
2nd Review - report emailed to architect.
|
Routing PW Street Lights | 4/24/2018 | | 4/24/2018 | | PASS |
Tom Marshall
|
|
|
|
Route to Impact Fee Review | 4/17/2018 | 4/20/2018 | 4/18/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 4/17/2018 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 3/1/2018 | | 4/17/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - FIRE | 3/1/2018 | 3/1/2018 | 3/13/2018 | | FAIL |
Scott Arellano
|
|
|
Attached comments and emailed architect
|
Routing Off Site - STRUCTURAL | 3/1/2018 | | 3/13/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - MECHANICAL | 3/1/2018 | | 3/8/2018 | | PASS |
Troy James
|
|
|
|
Routing PW Solid Waste | 3/1/2018 | | 3/7/2018 | | FAIL |
Evan Carpenter
|
|
|
Submitted site plans do not match in terms of solid waste enclosure locations. Sheet A-101 needs to match C1.0; the enclosures in A-101 are inaccessible to collection vehicles.
|
Routing - Erosion and Sediment | 3/1/2018 | | 3/5/2018 | | PASS |
Michael Zawacki
|
|
|
RP Needed prior to permit issue. Site inspection required.
|
Routing PW Street Lights | 3/1/2018 | | 3/2/2018 | | FAIL |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 3/1/2018 | | 3/1/2018 | | FAIL |
Mike Sheppard
|
|
|
Sewer revision required
|
Routing PW Environmental | 3/1/2018 | | 3/1/2018 | | PASS |
Terry Alber
|
|
|
|
Intake Approval | | | 3/1/2018 | | PASS |
|
|
|
|
Routing PW Drainage | 3/1/2018 | | 3/1/2018 | | FAIL |
Brian Murphy
|
|
|
NO SEEPAGE BED
|
Routing - PLUMBING | 3/1/2018 | | 3/1/2018 | | PASS |
Bill VanDegrift
|
|
|
Per plans and ISPC.
|
Routing - PLANNING | 3/1/2018 | | 3/1/2018 | | PASS |
David Moser
|
|
|
See DRH17-00143 - Current Planning review not required, allowed use in M-1D zone
|
Routing - Addressing | 3/1/2018 | | 3/1/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 3/1/2018 | | 3/1/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Design Review | 3/1/2018 | | 3/1/2018 | | PASS |
Katelyn Menuge
|
|
|
DRH17-00143
|
Intake Approval | | | 2/26/2018 | | FAIL |
Julie Romig
|
|
|
1. Structural Calculations - indicated on checklist but not found in documents.
2. G-001 States applicable codes as the 2012 codes. The 2015 codes were adopted on Jan. 1, 2018. Update codes to 2018 codes or submit letter by February 28th requesting review under the previous codes.
3. Structural sheets - are stamped but not signed - upload signed sheets.
|
Application received | | | 2/21/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 21 2018 9:12AM
|