BLD-Final | 5/16/2019 | 5/20/2019 | 5/20/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
DOC - Permit Finaled | 5/20/2019 | 5/20/2019 | 5/20/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 5/14/2019 | 5/16/2019 | 5/16/2019 | A | DONE |
Brandon Shaw
|
|
|
ACH50-4.3
|
BLD-Final | 5/14/2019 | 5/16/2019 | 5/14/2019 | A | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall Inspection cancelled from web by: Clint Wall
|
BLD-Energy code compliance | 3/11/2019 | 3/13/2019 | 3/13/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Framing/Rough-in | 3/5/2019 | 3/11/2019 | 3/11/2019 | A | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall. Nail offf all simpson hangars. Complte fire blocking on mech. enclosure upstairs. ok to insulate. Corrections were noted to the onsite framer.
|
BLD-Wall Bracing | 2/25/2019 | 2/25/2019 | 2/25/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Aging Inspection | 11/14/2018 | 11/14/2018 | 11/14/2018 | | CANC |
Brandon Shaw
|
|
|
|
BLD-Aging Inspection | 11/13/2018 | 11/13/2018 | 11/13/2018 | | CANC |
Brandon Shaw
|
|
|
|
BLD-Foundation | 7/2/2018 | 7/2/2018 | 7/2/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 6/28/2018 | 6/29/2018 | 6/29/2018 | P | PASS |
Brandon Shaw
|
|
|
Phone #: 2088708888 >> Inspection requested via mobile web by Wes
|
Issue PAID IN FULL permit | | | 6/14/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/14/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 3/16/2018 | | |
|
|
|
|
Plan assigned to (RDP) | 2/27/2018 | 2/27/2018 | 3/16/2018 | | DEFR |
Rob Patrick
|
|
|
3/12 sfd L1 ePlan
|
Routing - PLAN CHECK | 2/27/2018 | | 3/16/2018 | | PASS |
Michael Hanson
|
|
|
|
Plan assigned to (M_H) | 3/16/2018 | | 3/16/2018 | | DONE |
Michael Hanson
|
|
|
3/12 sfd L1 ePlan
|
Plan Reviewer's activity | | | 3/16/2018 | | DONE |
Michael Hanson
|
|
|
|
1st review completed | | | 3/16/2018 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/16/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 3/16/2018 | | DONE |
|
|
|
met
|
Routing - MECHANICAL | 2/27/2018 | | 3/1/2018 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 2/27/2018 | 3/2/2018 | 2/28/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 2/27/2018 | | 2/27/2018 | | PASS |
Jeff Lowe
|
|
|
|
Routing - Addressing | 2/27/2018 | | 2/27/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 2/27/2018 | | 2/27/2018 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/27/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/27/2018 | | DONE |
|
|
|
|
Intake Approval | | | 2/27/2018 | | PASS |
|
|
|
|
Application received | | | 2/22/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 22 2018 8:09AM
|