BLD-Final | 10/1/2018 | 10/2/2018 | 10/2/2018 | A | PASS |
Jim Sly
|
|
|
Please call ahead for access instructions - Vinnie Phone #: ###-#### Blower door...3.9
|
DOC - Permit Finaled | 10/2/2018 | 10/2/2018 | 10/2/2018 | P | PASS |
Jim Sly
|
|
|
|
BLD-Energy code compliance | 7/26/2018 | 7/27/2018 | 7/30/2018 | P | PASS |
Jim Sly
|
|
|
As late as possible, please call ahead // Kerry Phone #: ###-####
|
BLD-Framing/Rough-in | 7/26/2018 | 7/26/2018 | 7/26/2018 | P | PASS |
Jim Sly
|
|
|
Kerry Phone #: ###-####
|
BLD-Conference | 7/26/2018 | 7/27/2018 | 7/26/2018 | P | CANC |
Jim Sly
|
|
|
As late as posiblble // Kerry Phone #: ###-#### Inspection cancelled from web by: Keeley Wilson
|
Plan Modification Accepted | | | 7/26/2018 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 7/26/2018 | | 7/26/2018 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Framing/Rough-in | 7/25/2018 | 7/25/2018 | 7/25/2018 | P | NR |
Jim Sly
|
|
|
Kerry Phone #: ###-#### Mechanical Red Tag still in window...3PM
|
BLD-Framing/Rough-in | 7/23/2018 | 7/24/2018 | 7/24/2018 | P | NR |
Jim Sly
|
|
|
Kerry Phone #: ###-#### Need Mech rough in approval.
|
BLD-Framing/Rough-in | 7/20/2018 | 7/23/2018 | 7/23/2018 | P | NR |
Jim Sly
|
|
|
late late pm- Kerry Phone #: ###-#### Need Mech rough-in approval.
|
BLD-Wall Bracing | 7/18/2018 | 7/18/2018 | 7/18/2018 | P | PASS |
Jim Sly
|
|
|
said he talked to you and set up for this AM // Carey Phone #: ###-####
|
BLD-Wall Bracing | 7/9/2018 | 7/9/2018 | 7/9/2018 | P | FAIL |
Jim Sly
|
|
|
Kerry Phone #: ###-#### C/N posted
|
BLD-Wall Bracing | 5/25/2018 | 5/30/2018 | 5/30/2018 | A | PART |
Jim Sly
|
|
|
Jose Phone #: ###-#### Should be FOUNDATION WALL...........OK.
|
BLD-Footing | 5/24/2018 | 5/25/2018 | 5/25/2018 | P | PART |
Jim Sly
|
|
|
Jose Phone #: ###-#### No forms or string lines pulled. Met with Jose. We found 3 pins and a witness stake (front East) Pour at own risk.
|
OVERRIDE | | | 5/17/2018 | | |
|
|
|
|
Plan assigned to (RDP) | 3/6/2018 | 3/6/2018 | 5/17/2018 | | DONE |
Rob Patrick
|
|
|
3/19 sfd L1 ePlan....5/10 Failed: Corrections Required.
|
Routing - PLAN CHECK | 5/17/2018 | | 5/17/2018 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/17/2018 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 5/17/2018 | | DONE |
|
|
|
verify who the RP is-thee are 4 names of the same name in the RP's
|
Inspection Record Card- Bld | | | 5/17/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/17/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/10/2018 | | 5/10/2018 | | FAIL |
Rob Patrick
|
|
|
Requires corrections not addressed in last version.
|
Routing - PLANNING | 5/1/2018 | | 5/4/2018 | | PASS |
Katelyn Menuge
|
|
|
Redlined the remaining changes needed for Design Review.
|
Routing - PLAN CHECK | 4/18/2018 | | 4/18/2018 | | FAIL |
Rob Patrick
|
|
|
Corrections Required
|
Routing - PLANNING | 4/17/2018 | | 4/17/2018 | | FAIL |
Katelyn Menuge
|
|
|
Corrections required to meet conditions of DRH17-00237.
|
1st review completed | | | 3/22/2018 | | FAIL |
Rob Patrick
|
|
|
Waiting for new Design Review Application to be filed.
|
Route to Impact Fee Review | 3/6/2018 | 3/9/2018 | 3/7/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 3/6/2018 | | 3/7/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 3/6/2018 | | 3/7/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing - MECHANICAL | 3/6/2018 | | 3/7/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 3/6/2018 | | 3/6/2018 | | FAIL |
Katelyn Menuge
|
|
|
Drawings do not match Design Review Approval. Need to submit new Design Review application for this new design.
|
Plans ACCEPTED BY PLAN TECH | | | 3/6/2018 | | DONE |
|
|
|
|
Intake Approval | | | 3/6/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/6/2018 | | DONE |
|
|
|
|
Intake Approval | | | 3/1/2018 | | FAIL |
|
|
|
need to rotate plans, name plans correctly and use 2015 code
|
Application received | | | 2/23/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 23 2018 11:33AM
|
Routing - PLAN CHECK | 3/6/2018 | | | | FAIL |
Rob Patrick
|
|
|
Waiting for new Design Review Application to be filed.
|