BLD-Final | 8/2/2019 | 8/2/2019 | 8/2/2019 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Laz Ponce
|
DOC - Permit Finaled | 8/2/2019 | 8/2/2019 | 8/2/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 8/2/2019 | 8/2/2019 | 8/2/2019 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 4.3
|
BLD-Energy code compliance | 5/24/2019 | 5/28/2019 | 5/28/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by joey benart
|
BLD-Energy code compliance | 5/24/2019 | 5/24/2019 | 5/24/2019 | A | PASS |
Brandon Shaw
|
|
|
|
BLD-Framing/Rough-in | 5/23/2019 | 5/23/2019 | 5/23/2019 | P | PASS |
Brandon Shaw
|
|
|
OK to insulate...
|
BLD-Framing/Rough-in | 5/21/2019 | 5/22/2019 | 5/22/2019 | A | PASS |
Brandon Shaw
|
|
|
OK to insulate...
|
CHANGE STATUS TO (ISS) | | | 5/21/2019 | | DONE |
|
|
|
PLAN MOD
|
Plan assigned to (RDP) | 5/8/2019 | 5/8/2019 | 5/16/2019 | | DONE |
Rob Patrick
|
|
|
05/14 Plan Mod-changing manual J's-assigned to Rob P...05/10 Failed Mechanical Corrections Req'd
|
Routing - MECHANICAL | 5/16/2019 | | 5/16/2019 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - PLAN CHECK | 5/16/2019 | | 5/16/2019 | | PASS |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 5/16/2019 | | DONE |
|
|
|
plan mod so please do not re issue-when the fees for BLD18-00660 are paid-please remember to change status on BLD18-00661, 662 & 663
|
Routing - PLAN CHECK | 5/15/2019 | | 5/15/2019 | | FAIL |
Rob Patrick
|
|
|
Mechanical Corrections Req'd
|
Routing - MECHANICAL | 5/14/2019 | | 5/14/2019 | | FAIL |
Chad Schwendiman
|
|
|
|
Routing - PLAN CHECK | 5/9/2019 | | 5/10/2019 | | FAIL |
Rob Patrick
|
|
|
Mechanical Corrections Req'd
|
Routing - MECHANICAL | 5/9/2019 | | 5/10/2019 | | FAIL |
Chad Schwendiman
|
|
|
Emailed HVAC designer corrections, changemarks in Eplan
|
Plan Modification Accepted | | | 5/8/2019 | | DONE |
|
|
|
plan mod-changing manual J's-assigned to Rob P
|
BLD-Wall Bracing | 5/2/2019 | 5/3/2019 | 5/3/2019 | P | PASS |
Brandon Shaw
|
|
|
Gillemro Phone #: ###-####
|
BLD-Aging Inspection | 1/10/2019 | 1/10/2019 | 1/10/2019 | | CANC |
Brandon Shaw
|
|
|
|
Extend Permit 90/180 days | 1/10/2019 | 1/10/2019 | 1/10/2019 | P | DONE |
Brandon Shaw
|
|
|
|
BLD-Foundation | 8/29/2018 | 8/29/2018 | 8/29/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 8/22/2018 | 8/23/2018 | 8/23/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
Inspection Record Card- Bld | | | 8/1/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/1/2018 | | DONE |
|
|
|
|
Expiration Notice | 7/24/2018 | 8/14/2018 | 7/24/2018 | | DONE |
Brittany Hill
|
|
|
|
OVERRIDE | | | 3/16/2018 | | |
|
|
|
|
Plan assigned to (RDP) | 2/27/2018 | 2/27/2018 | 3/16/2018 | | DONE |
Rob Patrick
|
|
|
3/12 sfd L1 ePlan
|
Routing - PLAN CHECK | 2/27/2018 | | 3/16/2018 | | PASS |
Rob Patrick
|
|
|
|
1st review completed | | | 3/16/2018 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/16/2018 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 3/16/2018 | | DONE |
|
|
|
|
Routing - MECHANICAL | 2/27/2018 | | 3/2/2018 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 2/27/2018 | 3/2/2018 | 2/28/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 2/27/2018 | | 2/28/2018 | | PASS |
Katelyn Menuge
|
|
|
|
Routing - Addressing | 2/27/2018 | | 2/27/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 2/27/2018 | | 2/27/2018 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/27/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/27/2018 | | DONE |
|
|
|
|
Intake Approval | | | 2/27/2018 | | PASS |
|
|
|
|
Application received | | 2/26/2018 | | | |
|
|
|
|
Application received | | 2/26/2018 | | | |
|
|
|
|