Permit Information
Permit NumberBLD18-00685
StatusFinaled
Name WRIGHT BROTHERS THE BLDG CO EAGLE
Site Address 1100 S FIVE MILE RD
Project NameFive Mile Storage - Building A
Customer NumberBLD18-00795-00800, BLD18-00919-0021
ePlanReviewYes
Description
(FIVE MILE STORAGE – BUILDING #A) (10 PERMITS FILED UNDER BLD18-00685 IN EPLAN REVIEW THESE BLD’S ARE BLD18-00795-00800, and BLD18-00919-00921) Permit to construct a new 5,736 sq. ft. storage building (21 storage units) and related site improvements. Scope of work includes: construction of a slab on grade concrete, concrete foundation, construction of steel stud framed exterior walls with metal siding, metal roof purlins with a metal roof, metal storage unit partition panels, installation of new overhead doors, new electrical and site work. The building is not fire sprinklered. Note: Special Inspections Required see form 310. **JG**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  6/18/2019 DONE
sent 2nd late notice
Print Statement  4/19/2019 DONE
sent 1st late notice
Print Statement  1/7/2019 DONE
Second Notice 11/23/201812/13/2018 DONE
mailed 12-14
First Notice 10/29/201811/13/2018 DONE
mailed 11-14
BLD-Final10/18/201810/19/201810/19/2018PPASS
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by KJ Savaria
Zoning Approval10/19/201810/19/201810/19/2018 PASS
DetailsKatelyn Menuge
PubWorks Occupancy Approval10/19/201810/19/201810/19/2018 DONE
DetailsTiffany Lowery
Permanent Occupancy  10/19/2018 DONE
FIRE-Final Inspection10/17/201810/18/201810/18/2018PPASS
DetailsTroy Cobbley
Life safety passed. The Opticon was tested by Station 14. Plan review is ok with the 4'-9" access to man gates.

Phone #: ###-#### Inspection requested via web by KJ Savaria
Routing PW Drainage10/15/2018 10/15/2018 PASS
DetailsBrian Murphy
BLD-Footing6/21/20186/22/20186/22/2018ADEFR
DetailsMike Jordan
KJ Phone #: ###-####. Ok to place concrete pending special ispection.
Issue PAID IN FULL permit  5/21/2018 DONE
Print Occupancy Form  5/21/2018 DONE
OVERRIDE  5/16/2018  
Route to Impact Fee Review5/16/20185/21/20185/16/2018 PASS
DetailsEric Bilimoria
Plan assigned to (JG)3/15/20183/15/20185/16/2018 PASS
DetailsJavier Guzman
1st rev comp, 4/11 Five Mile Storage (bldg A) ePlan***
Permit Ready to Issue  5/16/2018 DONE
Need
RP
ACHD
GC Form
Revised Cert of Value
CHANGE STATUS TO (REV)  5/16/2018 DONE
Did not mean to make ready yet, missing activity
Routing - PLAN CHECK5/15/2018 5/16/2018 PASS
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  5/16/2018 DONE
Permit Ready to Issue  5/16/2018 DONE
Need
RP
ACHD
GC Form
Revised Cert of Value
Routing - FIRE5/15/20185/15/20185/15/2018 PASS
DetailsErika Akin
Attached revised comments to case
Routing Off Site - STRUCTURAL4/28/2018 5/9/2018 PASS
DetailsJavier Guzman
signed off in ePlan by AHJ Engineers Ena Beganovic
Routing - PLAN CHECK4/28/2018 5/3/2018 FAIL
DetailsJavier Guzman
Routing - FIRE4/28/20184/28/20185/2/2018 FAIL
DetailsErika Akin
Comments attached to BLD18-00685
1st review completed  4/18/2018 FAIL
DetailsJavier Guzman
Routing - PLAN CHECK3/15/2018 4/18/2018 FAIL
DetailsJavier Guzman
Routing Off Site - STRUCTURAL3/15/2018 4/4/2018 FAIL
DetailsJavier Guzman
Failed in ePlan by AHJ Engineers Ena Beganovic
Routing PW Drainage3/19/2018 4/4/2018 PASS
DetailsBrian Murphy
Signed off in ePlan b PW Brian Murphy
Routing - FIRE3/15/20183/15/20183/26/2018 FAIL
DetailsScott Arellano
Attached comments to case and emailed architect
Routing PW Street Lights3/19/2018 3/26/2018 PASS
DetailsTom Marshall
Routing - PLANNING3/15/2018 3/23/2018 PASS
DetailsTodd Tucker
Routing PW Sewer Design3/19/2018 3/22/2018 PASS
DetailsDeAnn Brown
Routing - Erosion and Sediment3/15/2018 3/21/2018 PASS
DetailsMichael Zawacki
SWPPP approved. Site prep inspection required.
Routing - PUBLIC WORKS3/15/2018 3/19/2018 PASS
DetailsRachael Beierle
Routing PW Solid Waste3/19/2018 3/19/2018 PASS
DetailsEvan Carpenter
Approved for commercial cart solid waste service.
Routing PW Environmental3/19/2018 3/19/2018 PASS
DetailsRick Christenson
Routing - MECHANICAL3/19/2018 3/19/2018 PASS
DetailsTroy James
Routing - Design Review3/15/2018 3/16/2018 PASS
DetailsKatelyn Menuge
DRH18-00013
Routing - Addressing3/15/2018 3/15/2018 PASS
DetailsDoug Chausow
Intake Approval  3/15/2018 PASS
Routing - PLUMBING3/15/2018 3/15/2018 PASS
DetailsDaryl Spivey
Per plan and ISPC
Intake Approval  3/8/2018 FAIL
Intake Approval  3/5/2018 FAIL
Application received  2/27/2018 DONE
Application submitted via PDS Online on Feb 27 2018 1:58PM