BLD-Final | 3/13/2020 | 3/13/2020 | 3/13/2020 | P | PASS |
Jim Storey
|
|
|
Please call prior to arrival Phone #: ###-#### Inspection requested via web by Jared Patchin
|
DOC - Permit Finaled | 3/13/2020 | 3/13/2020 | 3/13/2020 | P | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 1/17/2020 | 1/17/2020 | 1/17/2020 | | NR |
Jim Storey
|
|
|
|
BLD-Wall cover | 9/4/2019 | 9/5/2019 | 9/5/2019 | A | PASS |
Jim Storey
|
|
|
I would like to schedule my insulation inspection for Thursday AM, 9/5. I will not be home, but will leave my side door unlocked.
Thanks, Jared Patchin Phone #: ###-#### Inspection requested via web by Jared Patchin
|
BLD-Framing/Rough-in | 8/26/2019 | 8/27/2019 | 8/27/2019 | A | PART |
Jim Storey
|
|
|
I would love to have the earliest possible inspection.
Thanks, Jared Phone #: ###-#### Inspection
support rafters to mlb / ok to insulate.
|
BLD-Aging Inspection | 7/4/2019 | 7/4/2019 | 7/5/2019 | | PASS |
Jim Storey
|
|
|
Expires: 08/19/19
|
BLD-Aging Inspection | 7/5/2019 | 7/5/2019 | 7/5/2019 | | PASS |
Jim Storey
|
|
|
Expires: 08/19/19
|
Meeting | | | 6/14/2019 | | DONE |
|
|
|
Spoke with Jared about permit being changed into his name as the parcel owner and how to compelete that process.
|
Telephone call | | | 6/14/2019 | | DONE |
|
|
|
reciefved an email from Jared Patchin (parcel owner)-he let the GC go and is now going to be the GC for his own property-see attached GC and letter
|
BLD-Aging Inspection | 2/19/2019 | 2/19/2019 | 2/20/2019 | | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 2/18/2019 | 2/18/2019 | 2/20/2019 | | PASS |
Jim Storey
|
|
|
|
Issue PAID IN FULL permit | | | 4/5/2018 | | DONE |
|
|
|
emailed permit and inspection card to Derek Hurd
|
Inspection Record Card- Bld | | | 4/5/2018 | | DONE |
|
|
|
|
Plan assigned to (RDP) | 2/27/2018 | 2/27/2018 | 3/29/2018 | | DONE |
Rob Patrick
|
|
|
3/16 sfd L2 ePlan....Failed, Need engineering to show supporting methods.
|
Routing - PLAN CHECK | 3/29/2018 | | 3/29/2018 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/29/2018 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 3/29/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/27/2018 | | 3/21/2018 | | FAIL |
Rob Patrick
|
|
|
as per Rob-no ESC/no energy-Need engineering to show supporting methods.
|
1st review completed | | | 3/21/2018 | | FAIL |
Rob Patrick
|
|
|
|
Application received | | | 2/27/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 27 2018 2:36PM
|
Plans ACCEPTED BY PLAN TECH | | | 2/27/2018 | | |
|
|
|
|
Intake Approval | | | 2/27/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/27/2018 | | DONE |
|
|
|
|
Routing - PLANNING | 2/27/2018 | | 2/27/2018 | | PASS |
Colleen T Carroll
|
|
|
|