BLD-Final | 6/9/2018 | 6/11/2018 | 6/11/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Raquel Kenley
|
DOC - Permit Finaled | 6/11/2018 | 6/11/2018 | 6/11/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Other | 3/19/2018 | 3/20/2018 | 3/20/2018 | A | PASS |
Dave Hannah
|
|
|
Rebar inspection Phone #: ###-#### Inspection requested via web by Raquel Kenley
|
Issue PAID IN FULL permit | | | 3/6/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 3/2/2018 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 2/28/2018 | 2/28/2018 | 3/2/2018 | | PASS |
Josh Bogle
|
|
|
due 3/6 - pool/hillside
|
Routing - PLAN CHECK | | | 3/2/2018 | | PASS |
Josh Bogle
|
|
|
|
Telephone call | | | 3/2/2018 | | DONE |
|
|
|
Spoke with James to inform him the permit is ready and what fees are due.
|
Inspection Record Card- Bld | | | 3/2/2018 | | DONE |
|
|
|
|
1st review completed | | | 3/2/2018 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 3/2/2018 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 3/2/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/2/2018 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 3/2/2018 | | DONE |
|
|
|
Met
|
Routing - Erosion and Sediment | 2/28/2018 | | 3/1/2018 | | PASS |
Michael Zawacki
|
|
|
Waiver letter approved. Contractor states all excavated material to be reused on site.
|
Routing Walk-In (Zoning) | 2/28/2018 | 2/28/2018 | 2/28/2018 | A | DONE |
Leon Letson
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/28/2018 | | DONE |
|
|
|
|
Intake Approval | | | 2/28/2018 | | PASS |
|
|
|
couldn't get a hold of PW so just took in
|
Recd Pcfee & Taken To Pln CK | | | 2/28/2018 | | DONE |
|
|
|
no fees taken at intake
|
Routing PW Grading-Hillside | 2/28/2018 | | 2/28/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the pool subgrade is acceptable must be approved by Public Works prior to scheduling inspections. Please allow 24 hours for subgrade approval processing. If you have any questions call Melissa Jannusch ###-####.
|
Routing - PUBLIC WORKS | 2/28/2018 | | 2/28/2018 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | 2/28/2018 | | | |
|
|
|
|