BLD-Energy code compliance | 7/20/2018 | 7/20/2018 | 7/20/2018 | P | PASS |
Dave Hannah
|
|
|
Kent Phone #: ###-####
|
BLD-Framing/Rough-in | 7/18/2018 | 7/19/2018 | 7/19/2018 | A | PART |
Dave Hannah
|
|
|
Kent Phone #: ###-#### ok to insulate needs to strape plates and beams needs fire place r/i and fire block top of fireplace
|
BLD-Wall Bracing | 7/13/2018 | 7/16/2018 | 7/16/2018 | A | PASS |
Dave Hannah
|
|
|
Brett Phone #: ###-####
|
BLD-Wall Bracing | 7/2/2018 | 7/2/2018 | 7/2/2018 | P | NR |
Dave Hannah
|
|
|
Brett Phone #: ###-#### needs to finish corner
|
BLD-Footing | 5/16/2018 | 5/17/2018 | 5/17/2018 | P | PASS |
Brandon Shaw
|
|
|
Tucker Phone #: ###-####
|
OVERRIDE | | | 5/11/2018 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 5/11/2018 | 5/11/2018 | 5/11/2018 | | PASS |
Josh Bogle
|
|
|
|
Routing Walk-In (BLD) | 5/11/2018 | 5/11/2018 | 5/11/2018 | P | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 5/11/2018 | | 5/11/2018 | | PASS |
Josh Bogle
|
|
|
|
CHANGE STATUS TO (ISS) | | | 5/11/2018 | | DONE |
|
|
|
Plan Mod Approved
|
Permit Ready to Issue | | | 5/11/2018 | | DONE |
|
|
|
Plan Mod Approved
|
CHANGE STATUS TO (ISS) | | | 5/11/2018 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 5/11/2018 | | DONE |
|
|
|
new structural details and cals
|
BLD-Wall Bracing | 3/22/2018 | 3/23/2018 | 3/23/2018 | A | PASS |
Dave Hannah
|
|
|
Brandon Phone #: ###-#### wants both footing and wall inspections at same time
|
BLD-Footing | 3/22/2018 | 3/23/2018 | 3/23/2018 | A | PASS |
Dave Hannah
|
|
|
Brandon Phone #: ###-####
|
PubWorks Subgrade Approval | 3/23/2018 | 3/23/2018 | 3/23/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
OVERRIDE | | | 3/13/2018 | | |
|
|
|
|
Routing Walk-In (BLD) | 3/13/2018 | 3/13/2018 | 3/13/2018 | P | DONE |
Josh Bogle
|
|
|
|
Plan assigned to (JAB) Josh | 3/1/2018 | 3/1/2018 | 3/13/2018 | | PASS |
Josh Bogle
|
|
|
1st done - lacks structural details
|
Routing - PLAN CHECK | 3/13/2018 | | 3/13/2018 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 3/13/2018 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 3/13/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/13/2018 | | DONE |
Josh Bogle
|
|
|
|
Issue PAID IN FULL permit | | | 3/13/2018 | | DONE |
|
|
|
|
Plan resubmittals received | | | 3/13/2018 | | DONE |
|
|
|
resubmittals brought in-received 1 set of sheets A2.3, A2.2, existing floor plan and a cover sheet-took to JAB
|
Permit Ready to Issue | | | 3/13/2018 | | DONE |
|
|
|
|
Routing Walk-In (BLD) | 3/12/2018 | 3/12/2018 | 3/12/2018 | A | FAIL |
Josh Bogle
|
|
|
resubmittals for hillside addition
|
1st review completed | | | 3/7/2018 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | | | 3/7/2018 | | FAIL |
Josh Bogle
|
|
|
|
Routing - Erosion and Sediment | 3/5/2018 | | 3/6/2018 | | PASS |
Andy J. Long
|
|
|
|
Routing Walk-In (Zoning) | 3/1/2018 | 3/1/2018 | 3/1/2018 | P | PASS |
Colleen T Carroll
|
|
|
|
Routing Walk-In (PW Hillside) | 3/1/2018 | 3/1/2018 | 3/1/2018 | P | PASS |
Melissa Jannusch
|
|
|
|
Application received | | 3/1/2018 | | | |
|
|
|
|