Second Notice | | 8/18/2018 | 8/20/2018 | | DONE |
|
|
|
This permit finaled on the web by Charlene Meadows
|
First Notice | | 7/21/2018 | 8/8/2018 | | DONE |
|
|
|
mailed 8-10-18
|
BLD-Final | 7/10/2018 | 7/11/2018 | 7/11/2018 | A | PASS |
Dave Hannah
|
|
|
Tim Phone #: ###-####
|
Permanent Occupancy | | | 7/11/2018 | | DONE |
|
|
|
|
FIRE-Final Inspection | 7/5/2018 | 7/5/2018 | 7/5/2018 | P | PASS |
Jim Page
|
|
|
No fire sprinkler modifications, no fire alarm modifications, fire extinguisher will be mounted in discussed location. Final life fire safety inspection for area of work complete.
Tim-please call 20 minutes prior Phone #: ###-####
|
BLD-Wall cover | 4/30/2018 | 5/1/2018 | 5/1/2018 | A | PASS |
Dave Hannah
|
|
|
Tim Phone #: ###-####
|
Issue PAID IN FULL permit | | | 4/23/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/23/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/2/2018 | | DONE |
|
|
|
email permit to Tim Hendrix at tim@firstcallboise.com
Need:
GC form-met
Revised value from GC-met
|
Plan assigned to (AJS) | 3/6/2018 | 3/6/2018 | 3/31/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
self serve growler filling
|
Plan Reviewer's activity | | | 3/31/2018 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
The certificate of occupany issued for Jumba Juice incorrectly identifed the occupantcy as an A2. The occupancy has always been less than 49 occupants. I am correcting it on the certificate of occupancy to a B as it should have been. As this building is built to High rise standarda with core restrooms there are not code issued that change between these 2 occupancy groups.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/31/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/29/2018 | | 3/31/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - MECHANICAL | 3/30/2018 | | 3/30/2018 | | PASS |
Troy James
|
|
|
Additional cooling added for pizza oven. Ventless pizza oven just needs to be in a well ventilated space.
|
Route to Impact Fee Review | 3/16/2018 | 3/19/2018 | 3/16/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 3/16/2018 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - MECHANICAL | 3/6/2018 | | 3/16/2018 | | FAIL |
Troy James
|
|
|
Talked with applicant and owner. Received data for pizza oven. Owner does not want to comply with manufacturer ventilation requirements.
|
Routing - FIRE | 3/6/2018 | 3/6/2018 | 3/9/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - PLUMBING | 3/6/2018 | | 3/7/2018 | | PASS |
Bill VanDegrift
|
|
|
new equipment connecting to existing plumbing installed under BLD11-01128
|
Intake Approval | | | 3/6/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Javier accepted pre screen, CDH approval stamped on cover sheet
|
Routing - PLAN CHECK | 3/6/2018 | | 3/6/2018 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - Addressing | 3/6/2018 | | 3/6/2018 | | PASS |
Doug Chausow
|
|
|
Corrected address 132 N 8th St
|
Routing - PUBLIC WORKS | 3/6/2018 | | 3/6/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing PW Environmental | 3/6/2018 | | 3/6/2018 | | PASS |
Rick Christenson
|
|
|
Grease Trap Shown- connection to 3-Comp sink. Grease Trap not to be connected to dishwasher.
|
Application received | | | 3/2/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 2 2018 10:33AM
|