BLD-Final | 11/29/2018 | 11/30/2018 | 11/30/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
DOC - Permit Finaled | 11/30/2018 | 11/30/2018 | 11/30/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 11/30/2018 | 11/30/2018 | 11/30/2018 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 3.88
|
BLD-Other | 9/28/2018 | 10/1/2018 | 10/1/2018 | A | PASS |
Brandon Shaw
|
|
|
Soffit Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Energy code compliance | 9/27/2018 | 9/28/2018 | 9/28/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Framing/Rough-in | 9/27/2018 | 9/28/2018 | 9/28/2018 | A | PASS |
Brandon Shaw
|
|
|
See attached documents for Engineering fix for F14 (4) trusses... Corrections as per Engineering
|
BLD-Framing/Rough-in | 9/25/2018 | 9/26/2018 | 9/26/2018 | A | FAIL |
Brandon Shaw
|
|
|
Plan note #7 Drag strut not followed... F14 (4) Floor trusses installed wrong, bearing points not in line with interior bearing wall, need Engineering approval/fix...
OK to insulate
|
BLD-Framing/Rough-in | 9/24/2018 | 9/24/2018 | 9/24/2018 | P | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### >> Inspection requested via web by Kyle Seick Inspection cancelled from web by: Kyle Seick
|
BLD-Framing/Rough-in | 9/20/2018 | 9/21/2018 | 9/21/2018 | P | NR |
Brandon Shaw
|
|
|
Need air/foam seal... No Truss Engineering
|
BLD-Framing/Rough-in | 9/20/2018 | 9/21/2018 | 9/20/2018 | A | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### >> Inspection requested via web by Kyle Seick Inspection cancelled from web by: Kyle Seick
|
BLD-Wall Bracing | 8/27/2018 | 8/28/2018 | 8/28/2018 | A | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 7/18/2018 | 7/19/2018 | 7/18/2018 | A | CANC |
Brandon Shaw
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell Inspection cancelled via mobile web on Wednesday, July 18, 2018.
|
BLD-Foundation | 7/13/2018 | 7/13/2018 | 7/13/2018 | A | PASS |
Jim Storey
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
BLD-Footing | 7/11/2018 | 7/11/2018 | 7/11/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Conference | 7/11/2018 | 7/11/2018 | 7/11/2018 | P | CANC |
Brandon Shaw
|
|
|
As early as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell Inspection cancelled via mobile web on Wednesday, July 11, 2018.
|
Issue PAID IN FULL permit | | | 6/22/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/22/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 4/9/2018 | | |
|
|
|
|
Plan assigned to (RDP) | 3/2/2018 | 3/2/2018 | 4/9/2018 | | DONE |
Rob Patrick
|
|
|
3/15 sfd L1 ePlan....Failed, Waiting to receive Declaration of Easement Docs.
|
Routing - PLAN CHECK | 4/9/2018 | | 4/9/2018 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/9/2018 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 4/9/2018 | | DONE |
|
|
|
met
|
1st review completed | | | 3/22/2018 | | FAIL |
Rob Patrick
|
|
|
Waiting for Declaration of Easement for this Lot and Block.
|
Routing - PLAN CHECK | 3/2/2018 | | 3/22/2018 | | FAIL |
Rob Patrick
|
|
|
Waiting for Declaration of Easement for this Lot and Block.
|
Routing - MECHANICAL | 3/2/2018 | | 3/7/2018 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 3/2/2018 | 3/5/2018 | 3/5/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 3/2/2018 | | 3/5/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 3/2/2018 | | 3/5/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 3/2/2018 | | 3/5/2018 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | | 3/2/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 2 2018 3:16PM
|
Plans ACCEPTED BY PLAN TECH | | | 3/2/2018 | | DONE |
|
|
|
|
Intake Approval | | | 3/2/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/2/2018 | | DONE |
|
|
|
|