Print Statement | | | 6/18/2019 | | DONE |
|
|
|
sent 2nd statement
|
PubWorks Occupancy Approval | 5/15/2019 | 5/15/2019 | 5/15/2019 | | DONE |
Tiffany Lowery
|
|
|
|
Print Statement | | | 4/19/2019 | | DONE |
|
|
|
ent 1st late notice
|
Print Statement | | | 1/18/2019 | | DONE |
|
|
|
|
Print Statement | | | 1/7/2019 | | DONE |
|
|
|
|
Second Notice | | 11/23/2018 | 12/13/2018 | | DONE |
|
|
|
mailed 12-14
|
First Notice | | 10/29/2018 | 11/13/2018 | | DONE |
|
|
|
mailed 11-14
|
BLD-Final | 10/18/2018 | 10/19/2018 | 10/19/2018 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by KJ Savaria
|
Zoning Approval | 10/19/2018 | 10/19/2018 | 10/19/2018 | | PASS |
Katelyn Menuge
|
|
|
|
PubWorks Occupancy Approval | 10/19/2018 | 10/19/2018 | 10/19/2018 | | DONE |
Tiffany Lowery
|
|
|
|
Permanent Occupancy | | | 10/19/2018 | | DONE |
|
|
|
|
FIRE-Final Inspection | 10/17/2018 | 10/18/2018 | 10/18/2018 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. The Opticon was tested by Station 14. Plan review is ok with the 4'-9" access to man gates.
Phone #: ###-#### Inspection requested via web by KJ Savaria
|
BLD-Footing | 8/30/2018 | 8/30/2018 | 8/30/2018 | A | DEFR |
Brandon Shaw
|
|
|
Special inspection required
|
BLD-Footing | 8/30/2018 | 8/30/2018 | 8/30/2018 | P | CANC |
Mike Jordan
|
|
|
Concrete pour is scheduled for 2 pm. Phone #: ###-#### >> Inspection requested via web by KJ Savaria Inspection cancelled from web by: KJ Savaria
|
BLD-Footing | 8/22/2018 | 8/22/2018 | 8/22/2018 | A | DEFR |
Mike Jordan
|
|
|
Pour is at 12 pm. Phone #: ###-#### Inspection requested via web by KJ Savaria. Pending special inspection.
|
Issue PAID IN FULL permit | | | 5/21/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/21/2018 | | DONE |
|
|
|
|
Route to Impact Fee Review | 5/16/2018 | 5/21/2018 | 5/16/2018 | | PASS |
Eric Bilimoria
|
|
|
|
Plan assigned to (JG) | 3/15/2018 | 3/15/2018 | 5/16/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 4/11 Five Mile Storage (bldg L)
|
Permit Ready to Issue | | | 5/16/2018 | | DONE |
|
|
|
Need
RP
ACHD
GC Form
Revised Cert of Value
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/16/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/15/2018 | | 5/16/2018 | | PASS |
Javier Guzman
|
|
|
|
Routing - FIRE | 5/15/2018 | 5/15/2018 | 5/15/2018 | | PASS |
Erika Akin
|
|
|
Attached review comments to case BLD18-00685
|
Routing Off Site - STRUCTURAL | 4/28/2018 | | 5/9/2018 | | PASS |
Javier Guzman
|
|
|
signed off in ePlan by AHJ Engineers Ena Beganovic
|
Routing - PLAN CHECK | 4/28/2018 | | 5/3/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - FIRE | 4/28/2018 | 4/28/2018 | 5/2/2018 | | FAIL |
Erika Akin
|
|
|
Comments attached to BLD18-00685
|
Routing - PLAN CHECK | 3/15/2018 | | 4/18/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLANNING | 3/15/2018 | | 4/18/2018 | | PASS |
Todd Tucker
|
|
|
Signed of in ePlan under BLD18-00685 by Current Planning Todd Tucker
|
Routing Off Site - STRUCTURAL | 3/15/2018 | | 4/18/2018 | | FAIL |
Javier Guzman
|
|
|
Failed in ePlan under BLD18-00685 by AHJ Engineers Ena Beganovic
|
Routing PW Solid Waste | 3/19/2018 | | 4/18/2018 | | PASS |
|
|
|
Signed of in ePlan under BLD18-00685 by PW Solid Waste Evan Carpenter
|
Routing PW Drainage | 3/19/2018 | | 4/18/2018 | | PASS |
Brian Murphy
|
|
|
Signed of in ePlan under BLD18-00685 by PW Drainage Brian Murphy
|
1st review completed | | | 4/18/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - FIRE | 3/15/2018 | 3/15/2018 | 3/26/2018 | | FAIL |
Scott Arellano
|
|
|
Comments attached to BLD18-00685
|
Routing PW Street Lights | 3/19/2018 | | 3/26/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 3/19/2018 | | 3/22/2018 | | PASS |
DeAnn Brown
|
|
|
|
Routing - Erosion and Sediment | 3/15/2018 | | 3/21/2018 | | PASS |
Michael Zawacki
|
|
|
See ESC18-00313
|
Routing - PUBLIC WORKS | 3/15/2018 | | 3/19/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing PW Environmental | 3/19/2018 | | 3/19/2018 | | PASS |
Rick Christenson
|
|
|
|
Routing - Design Review | 3/15/2018 | | 3/16/2018 | | PASS |
Katelyn Menuge
|
|
|
DRH18-00013
|
Intake Approval | | | 3/15/2018 | | PASS |
|
|
|
|
Routing - Addressing | 3/15/2018 | | 3/15/2018 | | PASS |
Doug Chausow
|
|
|
|
Application received | | 3/7/2018 | | | |
|
|
|
|