Third Notice | | 7/15/2018 | 8/7/2018 | | DONE |
|
|
|
mailed 8-10-18
|
Second Notice | | 6/21/2018 | 7/10/2018 | | DONE |
|
|
|
|
First Notice | | 6/4/2018 | 6/11/2018 | | DONE |
|
|
|
mailed 6-12
|
Print Occupancy Form | | | 5/25/2018 | | DONE |
|
|
|
|
Permanent Occupancy | | | 5/25/2018 | | DONE |
|
|
|
per Carl Madsen, this should have been permit for CO.
|
Letter of compliance/Occupancy | | | 5/24/2018 | | DONE |
|
|
|
|
BLD-Final | 5/21/2018 | 5/22/2018 | 5/22/2018 | A | PASS |
Dave Hannah
|
|
|
Mike -need both fire final and bld final in am Phone #: ###-####
|
FIRE-Final Inspection | 5/21/2018 | 5/22/2018 | 5/22/2018 | A | PASS |
Jim Page
|
|
|
No fire sprinkler modifications, no fire alarm modifications, fire extinguishers are in place with current inspection tags, emergency egress light will be installed in discussed locations in west corridor. Final life fire safety inspection for area of work complete.
Mike Phone #: ###-####- wants both fire final and bld final inspections done in am, due to parking problems
|
FIRE-Final Inspection | 5/17/2018 | 5/18/2018 | 5/18/2018 | A | CANC |
Jim Page
|
|
|
Mike Phone #: ###-####
|
BLD-Final | 5/17/2018 | 5/18/2018 | 5/18/2018 | A | CANC |
Jim Storey
|
|
|
Mike-wants both inspections at same time Phone #: ###-####
|
BLD-Framing/Rough-in | 4/27/2018 | 5/1/2018 | 5/1/2018 | A | PASS |
Dave Hannah
|
|
|
Mike Phone #: ###-####
|
BLD-Conference | 4/25/2018 | 4/26/2018 | 4/26/2018 | A | PASS |
Jim Storey
|
|
|
Mike Phone #: ###-#### door frame in ok to cover
|
Issue PAID IN FULL permit | | | 4/9/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/9/2018 | | DONE |
|
|
|
|
Route to Impact Fee Review | 3/19/2018 | 3/22/2018 | 3/20/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Plan assigned to (RMH) | 3/16/2018 | 3/16/2018 | 3/20/2018 | | DONE |
Ron Hill
|
|
|
3/27 L2 FACES Expansion and Remodel ePlan*
|
Routing - PLAN CHECK | 3/14/2018 | | 3/20/2018 | | PASS |
Ron Hill
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/20/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/20/2018 | | DONE |
|
|
|
MET
Need
GC Form
Revised Cert of Value
|
1st review completed | | | 3/19/2018 | | FAIL |
|
|
|
|
Plan assigned to (JG) | 3/14/2018 | 3/14/2018 | 3/16/2018 | | DEFR |
Javier Guzman
|
|
|
3/27 L2 FACES Expansion and Remodel ePlan*
|
Routing - FIRE | 3/14/2018 | 3/14/2018 | 3/16/2018 | | PASS |
Scott Arellano
|
|
|
Attached comments to case
|
Routing - Addressing | 3/14/2018 | | 3/14/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 3/14/2018 | | 3/14/2018 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 3/14/2018 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 3/9/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 9 2018 11:31AM
|