BLD-Final | 5/4/2018 | 5/7/2018 | 5/7/2018 | A | PASS |
Mike Jordan
|
|
|
Adam Phone #: ###-####
|
DOC - Permit Finaled | 5/7/2018 | 5/7/2018 | 5/7/2018 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Conference | 5/2/2018 | 5/2/2018 | 5/2/2018 | P | DEFR |
Dave Hannah
|
|
|
As late as possible Phone #: 2089820822 >> Inspection requested via mobile web by Adam Junior
|
BLD-Final | 4/10/2018 | 4/11/2018 | 4/11/2018 | A | NR |
Mike Jordan
|
|
|
after 10:30, please - Adam Phone #: ###-####. Contacted engineer to discuss east end portion of roof. No call back. Contacted Adam to let him know. He noted he would contact engineer and resolve any issues if needed.
|
BLD-Final | 4/4/2018 | 4/5/2018 | 4/5/2018 | P | NR |
Mike Jordan
|
|
|
Adam Phone #: ###-####. Will need to reschedule for access to attic to verify additional work to strengthen roof.
|
Plan assigned to (JAB) Josh | 3/9/2018 | 3/9/2018 | 3/15/2018 | | PASS |
Josh Bogle
|
|
|
1st done - roof-mount PV - need optimizer specs
|
Routing - PLAN CHECK | 3/15/2018 | | 3/15/2018 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/15/2018 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Permit Ready to Issue | | | 3/15/2018 | | DONE |
|
|
|
Met
|
Issue PAID IN FULL permit | | | 3/15/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/9/2018 | | 3/13/2018 | | FAIL |
Josh Bogle
|
|
|
|
1st review completed | | | 3/13/2018 | | FAIL |
Josh Bogle
|
|
|
|
Application received | | | 3/9/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 9 2018 2:05PM
|
Plans ACCEPTED BY PLAN TECH | | | 3/9/2018 | | DONE |
|
|
|
|
Intake Approval | | | 3/9/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/9/2018 | | DONE |
|
|
|
|
Routing - PLANNING | 3/9/2018 | | 3/9/2018 | | PASS |
Sue Cummings
|
|
|
|
BLD-Conference | 5/2/2018 | 5/3/2018 | | P | |
Mike Jordan
|
|
|
call adam before going out would like to meet you on siteAs late as possible Phone #: 2089820822 >> Inspection requested via mobile web by Adam Junior
|