BLD-Blower Door Test Results | 10/9/2018 | 10/10/2018 | 10/10/2018 | A | PASS |
Tony Young
|
|
|
4.9
|
BLD-Final | 10/8/2018 | 10/9/2018 | 10/9/2018 | A | PASS |
Tony Young
|
|
|
garage code 7665 Phone #: ###-#### Inspection requested via web by Nancy Frost
|
DOC - Permit Finaled | 10/9/2018 | 10/9/2018 | 10/9/2018 | P | PASS |
Tony Young
|
|
|
|
BLD-Framing/Rough-in | 7/20/2018 | 7/20/2018 | 7/20/2018 | P | DONE |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Nancy Frost
|
BLD-Energy code compliance | 6/22/2018 | 6/26/2018 | 6/26/2018 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Nancy Frost
|
BLD-Framing/Rough-in | 6/19/2018 | 6/20/2018 | 6/20/2018 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Nancy Frost,, ok to insulate
|
BLD-Foundation | 4/18/2018 | 4/19/2018 | 4/19/2018 | P | PASS |
Tony Young
|
|
|
Jose Phone #: ###-####
|
BLD-Footing | 4/18/2018 | 4/18/2018 | 4/18/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
Issue PAID IN FULL permit | | | 4/18/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/18/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 4/12/2018 | | |
|
|
|
|
Plan assigned to (RDP) | 4/2/2018 | 4/2/2018 | 4/12/2018 | | DONE |
Rob Patrick
|
|
|
4/13 sfd Level1 ePlan....Failed, Multiple Corrections Req'd
|
Routing - PLAN CHECK | 4/12/2018 | | 4/12/2018 | | PASS |
Rob Patrick
|
|
|
ESC = No: Energy = No
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/12/2018 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 4/12/2018 | | DONE |
|
|
|
Met
|
Routing - PLAN CHECK | 4/9/2018 | | 4/9/2018 | | FAIL |
Rob Patrick
|
|
|
Corrections Required
|
Route to Impact Fee Review | 4/2/2018 | 4/5/2018 | 4/3/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
1st review completed | | | 4/3/2018 | | FAIL |
Rob Patrick
|
|
|
Multiple Corrections Required
|
Routing - PLAN CHECK | 4/2/2018 | | 4/3/2018 | | FAIL |
Rob Patrick
|
|
|
ESC = No; Energy = No
|
Routing - MECHANICAL | 4/2/2018 | | 4/2/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 4/2/2018 | | 4/2/2018 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - Addressing | 4/2/2018 | | 4/2/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 4/2/2018 | | 4/2/2018 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 4/2/2018 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/2/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/2/2018 | | DONE |
|
|
|
|
Intake Approval | | | 3/26/2018 | | FAIL |
|
|
|
Still need to update Energy to 2015 code
|
Intake Approval | | | 3/14/2018 | | FAIL |
|
|
|
need 2015 code changes
|
Application received | | | 3/10/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 10 2018 1:47PM
|