Second Notice | | 6/21/2018 | 6/15/2018 | | DONE |
|
|
|
This permit finaled on the web by Brian McCoy
|
First Notice | 6/1/2018 | 6/1/2018 | 6/11/2018 | | DONE |
Mike Jordan
|
|
|
mailed 6-12
|
Letter of compliance/Occupancy | | | 6/4/2018 | | DONE |
|
|
|
|
BLD-Final | 5/31/2018 | 6/1/2018 | 6/1/2018 | A | PASS |
Mike Jordan
|
|
|
Call for access code to building. Phone #: ###-#### Inspection requested via web by Gerome Fries
|
DOC - Permit Finaled | 6/1/2018 | 6/1/2018 | 6/1/2018 | P | PASS |
Mike Jordan
|
|
|
Vanilla shell only. A seperate permit is required for occupancy.
|
FIRE-Final Inspection | 5/31/2018 | 5/31/2018 | 5/31/2018 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
Call for access code to building. Phone #: ###-#### Inspection requested via web by Gerome Fries
|
BLD-Ceiling Grid Inspection | 5/18/2018 | 5/18/2018 | 5/18/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Gerome Fries
|
BLD-Framing/Rough-in | 4/19/2018 | 4/20/2018 | 4/20/2018 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Gerome Fries. Interior steel stud framed walls ok. no grid at this time.
|
Plan assigned to (JG) | 3/14/2018 | 3/14/2018 | 4/5/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 3/27 L2 Vanilla Space 1st time T.I. ePlan
|
Routing - PLAN CHECK | 4/5/2018 | | 4/5/2018 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/5/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/5/2018 | | DONE |
|
|
|
Need
GC Form
Revised Cert of Value
|
Inspection Record Card- Bld | | | 4/5/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/5/2018 | | DONE |
|
|
|
|
Route to Impact Fee Review | 4/4/2018 | 4/7/2018 | 4/4/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 4/4/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 3/14/2018 | | 4/4/2018 | | FAIL |
Javier Guzman
|
|
|
|
Meeting | | | 4/3/2018 | | DONE |
|
|
|
GC form didn't scan and i thought it did so there is no GC form for Straight line
|
Routing - FIRE | 3/14/2018 | 3/14/2018 | 3/19/2018 | | PASS |
Scott Arellano
|
|
|
Attached comments to case
|
Routing - MECHANICAL | 3/14/2018 | | 3/19/2018 | | PASS |
Troy James
|
|
|
bath fan to restroom
|
Routing - PLUMBING | 3/14/2018 | | 3/15/2018 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing - Addressing | 3/14/2018 | | 3/15/2018 | | PASS |
Doug Chausow
|
|
|
Vanilla Ste #110
|
Routing - PUBLIC WORKS | 3/14/2018 | | 3/15/2018 | | PASS |
Rachael Beierle
|
|
|
CONTACT WEST BOISE SEWER FOR PERMIT.
|
Routing - Erosion and Sediment | 3/14/2018 | | 3/15/2018 | | PASS |
Michael Zawacki
|
|
|
Internal work only. No exterior or ground disturbance shown on plan sheets.
|
Intake Approval | | | 3/14/2018 | | PASS |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 3/12/2018 | | DONE |
|
|
|
|
Application received | | | 3/11/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 11 2018 2:15PM
|