Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD18-00890
StatusFinaled
Name BLUE RAVEN SOLAR LLC
Site Address 2188 S WHITE PINE PL
Project NameTodd & Erin Katzner
Customer Number 
ePlanReviewYes
Description
MODIFICATION - 25 PANELS IN 2 ARRAYS **jab** Permit for 472sq' of roof-mounted, grid-tied Photo-voltaic panels with optimizers; 27 panels in 4 arrays. No work needed to the existing roof structure per engineer’s roof evaluation. All work per plans, engineering, manufacturer’s specs, & local code. Separate electrical permit required. **JAB**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/29/20185/31/20186/1/2018APASS
DetailsJim Sly
Trent, tech: ###-#### Phone #: ###-#### Inspection requested via web by BRS Permitting
DOC - Permit Finaled6/1/20186/1/20186/1/2018PPASS
DetailsJim Sly
BLD-Final5/22/20185/23/20185/22/2018PCANC
DetailsJim Storey
Phone #: ###-#### >> Inspection requested via web by BRS Permitting Inspection cancelled from web by: BRS Permitting
CHANGE STATUS TO (ISS)  5/17/2018 DONE
Plan assigned to (JAB) Josh5/7/20185/7/20185/14/2018 PASS
DetailsJosh Bogle
plan mod - PV
Routing - PLAN CHECK5/7/2018 5/14/2018 PASS
DetailsJosh Bogle
Permit Ready to Issue  5/14/2018 DONE
Plan Mod Approved
DO NOT REISSUE
Routing - PLANNING5/7/2018 5/7/2018 PASS
DetailsSue Cummings
Plan Modification Accepted  5/7/2018 DONE
plan mod-had to changed the layout of the solar panels due to the roofs layout-assigned to JAB
BLD-Final4/25/20184/27/20184/25/2018PCANC
DetailsJim Storey
Homeowner may not be there. No locked gates or pets. Phone #: ###-#### >> Inspection requested via web by BRS Permitting Inspection cancelled from web by: BRS Permitting
BLD-Framing/Rough-in4/19/20184/20/20184/20/2018ADEFR
DetailsJim Storey
Kyle and crew will be there in the morning. Phone #: ###-#### Inspection requested via web by BRS Permitting No work needed to the existing roof structure per engineer’s roof evaluation
(F) Reprint permit  3/28/2018 DONE
Plan assigned to (JAB) Josh3/14/20183/14/20183/19/2018 PASS
DetailsJosh Bogle
due 3/20 - PV
Routing - PLAN CHECK3/14/2018 3/19/2018 PASS
DetailsJosh Bogle
1st review completed  3/19/2018 DONE
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  3/19/2018 DONE
DetailsJosh Bogle
ESC no - Energy no
Permit Ready to Issue  3/19/2018 DONE
Met
Issue PAID IN FULL permit  3/19/2018 DONE
Inspection Record Card- Bld  3/19/2018 DONE
Application received  3/14/2018 DONE
Application submitted via PDS Online on Mar 14 2018 8:45AM
Intake Approval  3/14/2018 FAIL
upload plans to the drawings folder and plans must be uploaded as individual sheets.
Plans ACCEPTED BY PLAN TECH  3/14/2018 DONE
Recd Pcfee & Taken To Pln CK  3/14/2018 DONE
Intake Approval  3/14/2018 PASS
Routing - PLANNING3/14/2018 3/14/2018 PASS
DetailsColleen T Carroll