Permit Information
Permit NumberBLD18-00916
StatusFinaled
Name BENITON CONSTRUCTION
Site Address 400 W FORT ST
Project NameBraves Field Team Room
Customer Number 
ePlanReviewYes
Description
(BRAVES FIELD TEAM ROOM) ""GREEN TAG BOISE SCHOOLS PROJECT"" Permit for the constructio of a new 4,000 Square Foot Team Room for the Braves Field Athletic Complex with work to include general site work and construction of the new building per the approved plans and the attached engineering. This building consists of mens and womens team rooms with restroom facillities, athletic and general equipment storage rooms, public restrooms, concessions and a ticket sales area. This building is not fire sprinklered. Special inspections are required per the attached form 310. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 11/16/201812/6/2018 DONE
This permit finaled on the web by Matt Forrester
First Notice 11/9/201811/6/2018 DONE
mailed 11-12
Permanent Occupancy  10/30/2018 DONE
BLD-Final10/26/201810/29/201810/29/2018APASS
DetailsDave Hannah
Jan Phone #: ###-####
BLD-Final9/26/20189/26/20189/26/2018PPART
DetailsDave Hannah
Jan Phone #: ###-#### ok for tco ok for perm oc after landscaping is finised
FIRE-Final Inspection9/24/20189/25/20189/25/2018APASS
DetailsJim Page
No fire sprinklers, no fire alarms, fire extinguisher is placed with current inspection tag. Final life fire safety inspection for area of work complete.

Jane Phone #: ###-####
BLD-Wall Bracing7/27/20187/30/20187/30/2018APASS
DetailsDave Hannah
Jan Phone #: ###-####
BLD-Energy code compliance6/18/20186/18/20186/18/2018PPASS
DetailsDave Hannah
Jan Phone #: ###-####
BLD-Foundation6/18/20186/18/20186/18/2018PPASS
DetailsDave Hannah
Jan Phone #: ###-####
BLD-Foundation5/15/20185/16/20185/16/2018APASS
DetailsDave Hannah
Jan- foundation rebar-stem wall Phone #: ###-####
BLD-Footing5/10/20185/11/20185/11/2018APASS
DetailsDave Hannah
Jane Phone #: ###-####
Issue PAID IN FULL permit  4/27/2018 DONE
Print Occupancy Form  4/27/2018 DONE
Print Occupancy Form  4/27/2018 DONE
Telephone call  4/25/2018  
customer called, told him what he needs to get the permit issued
Telephone call  4/25/2018 DONE
emailed Matt Forrester the fees due
Routing - FIRE4/21/20184/21/20184/24/2018 PASS
DetailsErika Akin
Attached revised comments to case
Plan assigned to (CDM)3/24/20183/24/20184/24/2018 PASS
DetailsCarl D Madsen
Boise Braves Field House due 4/6
Routing PW Sewer Design4/24/2018 4/24/2018 PASS
DetailsDeAnn Brown
PLANS/APPL TAKEN TO FRONT DESK  4/24/2018 DONE
Permit Ready to Issue  4/24/2018 DONE
all met-NEED
ACHD-met
GC FORM-met
REVISED VALUE-met
Routing - PLAN CHECK4/12/2018 4/21/2018 PASS
DetailsCarl D Madsen
Routing Off Site - STRUCTURAL4/12/2018 4/21/2018 PASS
DetailsCarl D Madsen
Route to Impact Fee Review4/12/20184/15/20184/12/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing PW Flood Plain4/12/2018 4/12/2018 PASS
DetailsJason C. Taylor
Project outside of the SFHA. no floodplain requirements needed. JCT
Routing PW Flood Plain3/26/2018 4/3/2018 FAIL
DetailsJason C. Taylor
Elevation Certificate Needed, elevations need to be placed on site plan, foundation plan, and cross section plans. Jason Taylor ###-####
Routing - FIRE3/24/20183/24/20184/2/2018 FAIL
DetailsScott Arellano
Attached comments to case and emailed architect
1st review completed  4/2/2018 DONE
Routing Off Site - STRUCTURAL3/24/2018 4/1/2018 FAIL
DetailsCarl D Madsen
Routing - PLAN CHECK3/24/2018 4/1/2018 PASS
DetailsCarl D Madsen
Routing - ELECTRICAL3/24/2018 3/29/2018 PASS
DetailsDaryl DeGrange
Routing - Erosion and Sediment3/24/2018 3/28/2018 PASS
DetailsAndy J. Long
VOID, phase 2 of active ESC permit. See ESC17-00513 . No ESC review required.
Routing - PLUMBING3/24/2018 3/27/2018 PASS
DetailsBill VanDegrift
Per plan and ISPC.
Routing - MECHANICAL3/24/2018 3/27/2018 PASS
DetailsTroy James
Routing PW Street Lights3/26/2018 3/27/2018 PASS
DetailsTom Marshall
Routing PW Sewer Design3/26/2018 3/26/2018 FAIL
DetailsDeAnn Brown
Submit site piping/sewer connection plans.
Routing PW Solid Waste3/26/2018 3/26/2018 PASS
DetailsEvan Carpenter
No dumpster locations shown on plans and so none approved.
Routing PW Environmental3/26/2018 3/26/2018 PASS
DetailsTerry Alber
No grease abatement in concessions area, but only single sink, indicating no significant food prep/cleanup. If use changes, retrofit may be required.
Routing PW Drainage3/26/2018 3/26/2018 PASS
DetailsBrian Murphy
APPROVED UNDER PREVIOUS ODI PLAN
Routing - PLANNING3/24/2018 3/26/2018 PASS
DetailsNicolette Womack
Routing - Addressing3/24/2018 3/26/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS3/24/2018 3/26/2018 PASS
DetailsRachael Beierle
Intake Approval  3/24/2018 PASS
CHANGE STATUS TO (PND)  3/20/2018  
wrong permit was routed by mistake
Intake Approval  3/19/2018 FAIL
Application received  3/14/2018 DONE
Application submitted via PDS Online on Mar 14 2018 6:08PM