Print Statement | | | 11/1/2018 | | DONE |
|
|
|
|
First Notice | | 9/24/2018 | 10/12/2018 | | DONE |
|
|
|
mailed 10-15-18
|
Zoning Approval | 9/13/2018 | 9/13/2018 | 9/14/2018 | | PASS |
KayCee Babb
|
|
|
per CZC18-00073
|
Permanent Occupancy | | | 9/14/2018 | | DONE |
|
|
|
|
BLD-Final | 9/13/2018 | 9/14/2018 | 9/13/2018 | A | PASS |
Mike Jordan
|
|
|
Chuck Phone #: ###-####. Ok for perm oc.
|
FIRE-Final Inspection | 9/13/2018 | 9/13/2018 | 9/13/2018 | P | PASS |
Mike Jordan
|
|
|
Chuck Phone #: ###-####. Fire/life/safety was passed on 8-20-18 by Jim Page.
|
BLD-Final | 8/29/2018 | 8/29/2018 | 8/29/2018 | P | PEND |
Mike Jordan
|
|
|
Byron Phone #: ###-####. Pending plumbing final.
|
FIRE-Final Inspection | 8/28/2018 | 8/29/2018 | 8/29/2018 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed on 8/20/18
Byron Phone #: ###-####
|
FIRE-Final Inspection | 8/17/2018 | 8/20/2018 | 8/20/2018 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, no fire alarm modifications, fire extinguishers will be placed in discussed locations. Final life fire safety inspection for area of work complete.
Dustin Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 8/10/2018 | 8/10/2018 | 8/10/2018 | P | PASS |
Mike Jordan
|
|
|
Byron Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 8/3/2018 | 8/3/2018 | 8/3/2018 | P | NR |
Mike Jordan
|
|
|
Byron Phone #: ###-####. Needs mech and fire sprinkler rough in inspections. Also needs to install perimeter clips.
|
BLD-Framing/Rough-in | 7/5/2018 | 7/6/2018 | 7/6/2018 | A | PART |
Jim Sly
|
|
|
Brian Phone #: ###-#### East/ West full height wall....approx 35 feet from South end of building.....OK
|
FIRE-Conference | 6/26/2018 | 6/26/2018 | 6/26/2018 | P | DONE |
Troy Cobbley
|
|
|
I spoke with the project superintendant about the drawing sheet E4 that shows a fire alarm notification device and a manual pull station.
|
Meeting | | | 6/5/2018 | | DONE |
|
|
|
Received letter from tenant and new GC form to change GC from Chamisa Building to Precision Environments. See attached documents. Transfer fee paid.
|
Print Occupancy Form | | | 6/5/2018 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 5/31/2018 | 6/1/2018 | 6/1/2018 | A | PASS |
Mike Jordan
|
|
|
Byron Phone #: 208-###-####. Interior steel stud framed wall, north side only.
|
BLD-Other | 5/21/2018 | 5/21/2018 | 5/21/2018 | P | PASS |
Mike Jordan
|
|
|
Allen- structural steel bolt connection Phone #: ###-####
|
Fees Due Hold | 5/10/2018 | 5/10/2018 | 5/21/2018 | | DONE |
Rita DeYoung
|
|
|
Fees paid
|
BLD-Footing | 5/4/2018 | 5/7/2018 | 5/7/2018 | A | PEND |
Mike Jordan
|
|
|
Byron Phone #: ###-####. INterior column pad footings. Noted city approved plans have been redlined to show (4) #4 rebar at 10 in. oc. each way. In place work has #5 bar, 3 each way per the orginal schedule. Contractor to replace as per city approved plan, or engineer of record to provide new calcs and letter showing existing work is ok.
|
Issue PAID IN FULL permit | | | 5/4/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/2/2018 | | DONE |
|
|
|
|
Routing - FIRE | 4/26/2018 | 4/26/2018 | 5/1/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Plan assigned to (JG) | 3/28/2018 | 3/28/2018 | 5/1/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 4/20 L3 NxEdge Cleanroom ePlan, pend fire
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/1/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/1/2018 | | DONE |
|
|
|
NEED
GC FORM
REVISED VALUE - met
|
Routing - PLAN CHECK | 4/26/2018 | | 4/30/2018 | | PASS |
Javier Guzman
|
|
|
|
Routing - Design Review | 4/26/2018 | | 4/27/2018 | | PASS |
KayCee Babb
|
|
|
|
Route to Impact Fee Review | 4/20/2018 | 4/23/2018 | 4/23/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 3/28/2018 | 3/28/2018 | 4/20/2018 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and emailed architect
|
Routing - PLAN CHECK | 3/28/2018 | | 4/20/2018 | | FAIL |
Javier Guzman
|
|
|
|
1st review completed | | | 4/20/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing PW Environmental | 3/28/2018 | | 4/2/2018 | | PASS |
Rick Christenson
|
|
|
|
Routing - Design Review | 3/28/2018 | | 4/2/2018 | | FAIL |
Sarah Schafer
|
|
|
Zoning Certificate needed for the roof top mechanical equipment and screening.
|
Routing - PLUMBING | 3/28/2018 | | 3/29/2018 | | PASS |
Bill VanDegrift
|
|
|
per plan and ISPC.
|
Routing - PLANNING | 3/28/2018 | | 3/28/2018 | | PASS |
Celine Acord
|
|
|
No current planning review required.
|
Routing - Addressing | 3/28/2018 | | 3/28/2018 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 3/28/2018 | | 3/28/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Erosion and Sediment | 3/28/2018 | | 3/28/2018 | | PASS |
Michael Zawacki
|
|
|
TI. No outside excavation scheduled to occur.
|
Routing - MECHANICAL | 3/28/2018 | | 3/28/2018 | | PASS |
Troy James
|
|
|
|
Intake Approval | | | 3/26/2018 | | PASS |
|
|
|
|
Intake Approval | | | 3/23/2018 | | FAIL |
|
|
|
(3-13-18) Please refer to the circled item in the plan intake checklist. Please resolve that item as directed. CJW
|
Application received | | | 3/19/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 19 2018 9:17AM
|