Print Statement | | | 11/14/2019 | | DONE |
|
|
|
|
Print Statement | | | 10/9/2019 | | DONE |
|
|
|
called and emailed accounting@datumcnsgtruction.com about the past due amount that's over 90 days
|
Telephone call | | | 10/9/2019 | | DONE |
|
|
|
called-talked to John about the late fee amount that's past 90 days old-he asked me to email him at accounting@datumconstgruction.com and he'd get to the bottom of why they're not paid
|
Print Statement | | | 8/21/2019 | | DONE |
|
|
|
sent 3rd late notice
|
Print Statement | | | 7/25/2019 | | DONE |
|
|
|
sent 2nd late notice
|
Print Statement | | | 6/18/2019 | | DONE |
|
|
|
sent 1st late notice
|
Print Statement | | | 5/1/2019 | | DONE |
|
|
|
|
Print Statement | | | 2/22/2019 | | DONE |
|
|
|
|
Third Notice | | 1/12/2019 | 2/7/2019 | | DONE |
|
|
|
mailed 2-11-19
|
Second Notice | | 12/31/2018 | 1/7/2019 | | DONE |
|
|
|
mailed 1-11-19
|
First Notice | | 11/16/2018 | 12/13/2018 | | DONE |
|
|
|
mailed 12-14
|
BLD-Final | 11/5/2018 | 11/6/2018 | 11/6/2018 | P | PASS |
Mike Jordan
|
|
|
Cody Phone #: ###-####. Ok for perm occ. Exit sign in warehouse has been installed.
|
FIRE-Final Inspection | 11/5/2018 | 11/6/2018 | 11/6/2018 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Exit sign to be installed in warehouse prior to the building inspection as discussed.
Cody Phone #: ###-####
|
Permanent Occupancy | | | 11/6/2018 | | DONE |
|
|
|
|
Temporary Occupancy | 10/30/2018 | 1/28/2019 | 10/30/2018 | | DONE |
Brittany Hill
|
|
|
|
BLD-Final | 10/29/2018 | 10/29/2018 | 10/29/2018 | A | PART |
Mike Jordan
|
|
|
Verified work from pictures over weekend. Fire should be finaled by today. Contractor has a few transitions from handrails to clean up and will call for final whwn completed. Temp occ still ok.
|
BLD-Final | 10/26/2018 | 10/27/2018 | 10/27/2018 | A | PART |
Mike Jordan
|
|
|
Ok for temp occ. Gurad rail issues and floor transitions have issues have been resolved.
|
BLD-Final | 10/25/2018 | 10/26/2018 | 10/26/2018 | P | NR |
Mike Jordan
|
|
|
Cody Phone #: ###-####. Needs to install all transitions from ramps to concrete floor and from 2 inch foam on elevated walkways to carpeted areas on ramps and stairs. Also noted that guardrails are only 40 inches from walking surface, Due to 2 inch foam being placed on plywood deck.
|
FIRE-Final Inspection | 10/25/2018 | 10/26/2018 | 10/26/2018 | A | PART |
Troy Cobbley
|
|
|
A temporary for life safety is being given with the fire code and building code officials permission until the project related fire alarm permit is passed, the missing exit sign is provided in the warehouse and the racks are removed as discussed.
Cody Phone #: ###-####
|
FIRE-Conference | 10/25/2018 | 10/25/2018 | 10/25/2018 | P | DONE |
Troy Cobbley
|
|
|
Provide exit signs, exit discharge and emergency lights as per the approved plans, repair the existing emergency lights, provide occupant load sign, provide panic hardware where required, provide racking permit or remove racks, provide building address, remove all old fire alarm equipment and provide adequate strobe coverage with new equipment.
|
BLD-Conference | 10/23/2018 | 10/24/2018 | 10/24/2018 | A | DONE |
Mike Jordan
|
|
|
Cody Phone #: ###-####
|
BLD-Framing/Rough-in | 10/9/2018 | 10/10/2018 | 10/10/2018 | A | PASS |
Mike Jordan
|
|
|
Ben-plat form Phone #: ###-####. Remainder of interior steel stud framed walls and cross members for elevated platforms ok to cover. Contractor also geting close to job completion. reviewed several items for final. Noted issue is the main enterance wich are power operated sliding doors. Due to Occupancy type and load, panic hardware will be required.
|
BLD-Framing/Rough-in | 10/2/2018 | 10/3/2018 | 10/3/2018 | A | PART |
Brandon Shaw
|
|
|
High platform and access ramp farming... Center air bag and blocking for guard rail, at later date...
|
BLD-Framing/Rough-in | 9/13/2018 | 9/14/2018 | 9/14/2018 | A | PASS |
Mike Jordan
|
|
|
partial framing for platforms prior to sheathing // Ben Phone #: ###-####. Interior steel stud framing for platforms at kids corner area.
|
BLD-Conference | 8/23/2018 | 8/24/2018 | 8/24/2018 | A | DONE |
Mike Jordan
|
|
|
Ben Phone #: ###-####
|
Issue PAID IN FULL permit | | | 6/21/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/21/2018 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 3/26/2018 | 3/26/2018 | 6/18/2018 | | PASS |
Carl Westfall
|
|
|
* (2nd done) (Apr 13 - 15 days) (29 sheets) Altitude Trampoline Park L-3
|
Routing Off Site - STRUCTURAL | 6/12/2018 | | 6/18/2018 | | PASS |
Carl Westfall
|
|
|
Chris Merrill (Stapley)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/18/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/18/2018 | | DONE |
|
|
|
NEED
ACHD-met (see documents)
GC FORM - met
REVISED VALUE - met
E-mail permits Olivia (Datum Const.) - olivia@datumconstruction.com
|
Routing - PLAN CHECK | 6/11/2018 | | 6/12/2018 | | PASS |
Carl Westfall
|
|
|
Pending Structural (upload new plan review report)
|
Plan resubmittals received | | | 6/11/2018 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 6/8/2018 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 5/31/2018 | | 6/8/2018 | | FAIL |
Carl Westfall
|
|
|
Jan Welch (Stapley)
|
Routing - FIRE | 5/31/2018 | | 6/4/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Plan Reviewer's activity | | | 6/4/2018 | | DONE |
|
|
|
Uploaded stamped sheets
|
Routing - PLAN CHECK | 5/30/2018 | | 5/31/2018 | | PASS |
Carl Westfall
|
|
|
Passed pending approval by Structural
|
Routing - PLUMBING | 5/31/2018 | | 5/31/2018 | | PASS |
Daryl Spivey
|
|
|
Routed so that you can move your red line. Per plan and ISPC.
|
Plan resubmittals received | | | 5/30/2018 | | DONE |
|
|
|
|
Route to Impact Fee Review | 4/25/2018 | 4/28/2018 | 4/26/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 3/26/2018 | | 4/25/2018 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
1st review completed | | | 4/25/2018 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 4/25/2018 | | DONE |
|
|
|
|
Routing - FIRE | 3/26/2018 | 3/26/2018 | 4/20/2018 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and emailed architect
|
Routing Off Site - STRUCTURAL | 3/26/2018 | | 4/10/2018 | | FAIL |
Carl Westfall
|
|
|
Jan Welch (Stapley)
|
Routing Off Site - C.D.H | 3/26/2018 | | 4/5/2018 | | PASS |
Carl Westfall
|
|
|
Natasha Ferney
|
Routing - PLUMBING | 3/26/2018 | | 3/29/2018 | | PASS |
Daryl Spivey
|
|
|
See redline notes and per ISPC
|
Routing - MECHANICAL | 3/26/2018 | | 3/28/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - Design Review | 3/26/2018 | | 3/27/2018 | | PASS |
Sarah Schafer
|
|
|
Use is allowed in the zone and there are no exterior changes. Parking is adequate for the use.
|
Routing - Addressing | 3/26/2018 | | 3/27/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 3/26/2018 | | 3/27/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 3/26/2018 | | 3/27/2018 | | PASS |
Michael Zawacki
|
|
|
Interior work. No ESCP needed based on provided plan sheets.
|
Plan Reviewer's activity | | | 3/26/2018 | | DONE |
|
|
|
Adele instructed the applicant to contact ACHD
|
Intake Approval | | | 3/26/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
James,
Your project has been routed through plan review.
Please make sure that you reach out to ACHD for review on this change of use/occupancy. If additional fees are due they will need to be paid or paid when the permit is issued. If no fees are do please submit the documentation from ACDH as such.
Thank you
Adele Schaffeld-Griffin
Assistant Building Official
Planning and Development Services
Office: ###-####
aschaffeldgriffin@cityofboise.org
Making Boise the most livable city in the country.
|
Intake Approval | | | 3/26/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Intake Approval | | | 3/21/2018 | | FAIL |
|
|
|
|
Application received | | | 3/20/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 20 2018 11:28AM
|