BLD-Final | 11/25/2019 | 11/25/2019 | 11/25/2019 | P | PASS |
Tell Riley
|
|
|
Kevin Phone #: ###-####//final complete//
|
DOC - Permit Finaled | 11/25/2019 | 11/25/2019 | 11/25/2019 | P | PASS |
Tell Riley
|
|
|
|
BLD-Energy code compliance | 2/6/2019 | 2/8/2019 | 2/8/2019 | A | PASS |
Jim Sly
|
|
|
Kevin Phone #: ###-####
|
BLD-Framing/Rough-in | 1/22/2019 | 1/22/2019 | 1/22/2019 | P | PASS |
Jim Sly
|
|
|
Kevin Phone #: ###-####
|
BLD-Framing/Rough-in | 9/17/2018 | 9/18/2018 | 9/18/2018 | A | PART |
Jim Sly
|
|
|
Kevin Phone #: ###-#### Underfloor......OK
|
Routing Walk-In (BLD) | 7/10/2018 | 7/10/2018 | 7/10/2018 | P | PASS |
Josh Bogle
|
|
|
chatted about a possible modification
|
BLD-Conference | 3/27/2018 | 3/27/2018 | 3/27/2018 | P | DONE |
Brandon Shaw
|
|
|
Kevin-questions about window for framing door, and a pad for gun safe Phone #: ###-####
|
Routing Walk-In (BLD) | 3/20/2018 | 3/20/2018 | 3/20/2018 | P | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 3/20/2018 | | 3/20/2018 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 3/20/2018 | | DONE |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 3/20/2018 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 3/20/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/20/2018 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 3/20/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 3/20/2018 | | DONE |
|
|
|
|
Application received | | 3/20/2018 | | | |
|
|
|
|