BLD-Final | 10/26/2018 | 10/26/2018 | 10/26/2018 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
DOC - Permit Finaled | 10/26/2018 | 10/26/2018 | 10/26/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 10/26/2018 | 10/26/2018 | 10/26/2018 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 3.99
|
BLD-Final | 10/8/2018 | 10/9/2018 | 10/9/2018 | A | FAIL |
Brandon Shaw
|
|
|
R-3 insulation needed at hot side of suppy, from water heater to house... Caulking needed at water heater vent penetration... Blower door test results to be posted... Egerss window, bedroom 3, to be no more than 44" from finished floor...
|
BLD-Energy code compliance | 8/13/2018 | 8/14/2018 | 8/13/2018 | A | PASS |
Brandon Shaw
|
|
|
Gus Phone #: ###-####
|
BLD-Energy code compliance | 8/9/2018 | 8/10/2018 | 8/9/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Other | 8/8/2018 | 8/10/2018 | 8/9/2018 | A | PASS |
Brandon Shaw
|
|
|
Soffit Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Framing/Rough-in | 8/7/2018 | 8/8/2018 | 8/8/2018 | A | PASS |
Brandon Shaw
|
|
|
Corrections SAT...
OK to insulate
|
BLD-Framing/Rough-in | 8/6/2018 | 8/6/2018 | 8/6/2018 | P | FAIL |
Brandon Shaw
|
|
|
See correction notice
OK to insulate
|
BLD-Wall Bracing | 7/23/2018 | 7/23/2018 | 7/23/2018 | P | PEND |
Brandon Shaw
|
|
|
Interior shear, hold downs and anchor bolts to be tightened down
|
BLD-Wall Bracing | 7/16/2018 | 7/16/2018 | 7/16/2018 | A | FAIL |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick covered with out insp.
|
BLD-Foundation | 6/5/2018 | 6/6/2018 | 6/7/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 6/5/2018 | 6/5/2018 | 6/5/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
Issue PAID IN FULL permit | | | 5/24/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/24/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 4/20/2018 | | |
|
|
|
|
Plan assigned to (RDP) | 4/5/2018 | 4/5/2018 | 4/20/2018 | | DONE |
Rob Patrick
|
|
|
4/18 sfd L1 ePlan....4/16 Failed: Manual "J" doesn't match Prescriptive.
|
Routing - PLAN CHECK | 4/20/2018 | | 4/20/2018 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/20/2018 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 4/20/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/5/2018 | | 4/16/2018 | | FAIL |
Rob Patrick
|
|
|
|
1st review completed | | | 4/16/2018 | | FAIL |
Rob Patrick
|
|
|
4/16...Fail: Manual J doesn't match Prescriptive
|
Routing - MECHANICAL | 4/5/2018 | | 4/9/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Route to Impact Fee Review | 4/5/2018 | 4/8/2018 | 4/6/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 4/5/2018 | | 4/6/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 4/5/2018 | | 4/6/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 4/5/2018 | | 4/6/2018 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/5/2018 | | DONE |
|
|
|
|
Intake Approval | | | 4/5/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/5/2018 | | DONE |
|
|
|
|
Application received | | | 3/20/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 20 2018 4:30PM
|