BLD-Final | 12/10/2018 | 12/11/2018 | 12/11/2018 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Gus Brandon
|
DOC - Permit Finaled | 12/11/2018 | 12/11/2018 | 12/11/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Framing/Rough-in | 11/9/2018 | 11/9/2018 | 11/9/2018 | P | DONE |
Brandon Shaw
|
|
|
See Documents of Engineering fix for notched beam...
|
BLD-Energy code compliance | 10/3/2018 | 10/3/2018 | 10/3/2018 | A | PEND |
Brandon Shaw
|
|
|
Pending Beam Engineering submital and hold downs being installed- back order on hardware...
|
BLD-Energy code compliance | 10/2/2018 | 10/2/2018 | 10/2/2018 | A | CANC |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by Kyle Seick Inspection cancelled from web by: Kyle Seick
|
BLD-Framing/Rough-in | 9/27/2018 | 9/27/2018 | 9/27/2018 | P | PEND |
Brandon Shaw
|
|
|
Need Engineering detailing beam fix, submitted for review...
OK to insulate
|
BLD-Other | 9/25/2018 | 9/25/2018 | 9/25/2018 | P | PASS |
Brandon Shaw
|
|
|
Soffit Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Framing/Rough-in | 9/25/2018 | 9/25/2018 | 9/25/2018 | P | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### >> Inspection requested via web by Kyle Seick Inspection cancelled from web by: Kyle Seick
|
BLD-Framing/Rough-in | 9/18/2018 | 9/19/2018 | 9/19/2018 | A | NR |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Other | 9/14/2018 | 9/17/2018 | 9/17/2018 | A | CANC |
Brandon Shaw
|
|
|
Soffit Phone #: ###-#### Inspection requested via web by Kyle Seick
|
Plan Modification Accepted | | | 9/6/2018 | | DONE |
|
|
|
New manual j report
|
Routing - MECHANICAL | 9/6/2018 | | 9/6/2018 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 8/8/2018 | 8/9/2018 | 8/9/2018 | A | PART |
Brandon Shaw
|
|
|
Work in progress Hold downs and straps to be installed before framing roungh in
|
BLD-Foundation | 5/23/2018 | 5/23/2018 | 5/23/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 5/23/2018 | 5/23/2018 | 5/23/2018 | A | PASS |
Brandon Shaw
|
|
|
work in progress
|
(F) Reprint permit | | | 5/11/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/11/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 5/9/2018 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 5/9/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/9/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/25/2018 | | 5/9/2018 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/9/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 5/9/2018 | | DONE |
|
|
|
met
|
Plan assigned to (M_H) | 4/16/2018 | | 5/9/2018 | | DONE |
Michael Hanson
|
|
|
04/27 sfd L1 ePlan. 1st review completed - Structural deficiencies. MDH
|
Routing - PLAN CHECK | 4/16/2018 | | 4/25/2018 | | FAIL |
Michael Hanson
|
|
|
Structural deficiencies. MDH
|
Plan Reviewer's activity | | | 4/25/2018 | | DONE |
Michael Hanson
|
|
|
|
1st review completed | | | 4/25/2018 | | FAIL |
Michael Hanson
|
|
|
Structural deficiencies. MDH
|
Route to Impact Fee Review | 4/16/2018 | 4/19/2018 | 4/17/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 4/16/2018 | | 4/17/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 4/16/2018 | | 4/16/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 4/16/2018 | | 4/16/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 4/16/2018 | | 4/16/2018 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/16/2018 | | DONE |
|
|
|
|
Intake Approval | | | 4/16/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/16/2018 | | DONE |
|
|
|
|
Application received | | | 3/21/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 21 2018 2:54PM
|