PubWorks Occupancy Approval | 6/11/2019 | 6/11/2019 | 6/11/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Aging Inspection | 5/3/2019 | 5/3/2019 | 5/6/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 5/2/2019 | 5/2/2019 | 5/6/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Final | 3/12/2019 | 3/13/2019 | 3/13/2019 | A | NR |
Tony Young
|
|
|
Jeff Phone #: ###-####,, needs hillside public works, tempered glass
|
BLD-Wall cover | 12/18/2018 | 12/19/2018 | 12/19/2018 | A | PASS |
Brandon Shaw
|
|
|
Insulation...
|
BLD-Wall cover | 12/4/2018 | 12/5/2018 | 12/5/2018 | A | PASS |
Tony Young
|
|
|
jeff Phone #: ###-####,, soffit ok
|
BLD-Framing/Rough-in | 12/3/2018 | 12/4/2018 | 12/4/2018 | A | PART |
Tony Young
|
|
|
jeff Phone #: ###-####,, corrections painted,, ok to insulate
|
BLD-Footing | 10/1/2018 | 10/2/2018 | 10/2/2018 | A | PART |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Footings for new stairs.
|
BLD-Foundation | 8/29/2018 | 8/29/2018 | 8/29/2018 | P | PASS |
Tony Young
|
|
|
stem wall // Francis Phone #: ###-####
|
BLD-Footing | 8/27/2018 | 8/27/2018 | 8/27/2018 | P | PART |
Tony Young
|
|
|
Mark Phone #: ###-####,, work in progress,, ok
|
PubWorks Subgrade Approval | 8/24/2018 | 8/24/2018 | 8/24/2018 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
BLD-Footing | 8/22/2018 | 8/23/2018 | 8/23/2018 | A | CANC |
Tony Young
|
|
|
Mark Phone #: ###-####,, needs soils
|
Issue PAID IN FULL permit | | | 7/31/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/31/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 7/27/2018 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 6/1/2018 | 6/1/2018 | 7/27/2018 | | PASS |
Josh Bogle
|
|
|
1st done - Hillside addition
|
Routing - PLAN CHECK | 7/27/2018 | | 7/27/2018 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/27/2018 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes
|
Meeting | | | 7/27/2018 | | DONE |
|
|
|
emailed GC/applicant to give him a heads up his RCE number expired. // update is getting it updated
|
Permit Ready to Issue | | | 7/27/2018 | | DONE |
|
|
|
All requirements met
|
Plan Reviewer's activity | | | 7/26/2018 | | DONE |
Josh Bogle
|
|
|
left a msg for applicant (phone) asking about updated footing engineering
|
Routing Walk-In (BLD) | 7/20/2018 | 7/20/2018 | 7/20/2018 | A | FAIL |
Brian McGowan
|
|
|
Requested the ePlan task be sent back so he can upload new documents. Also wanted to know the status of when the permit might be completed. Told him Josh was on vacation and would get back to it asap.
|
Routing - MECHANICAL | 7/13/2018 | | 7/13/2018 | | PASS |
Troy James
|
|
|
|
Plan Reviewer's activity | | | 7/13/2018 | | DONE |
Josh Bogle
|
|
|
cleaned up and correccctly versioned resubmittal - Manual S was new so routed to Mech also JAB
|
Routing - PLAN CHECK | 7/13/2018 | | 7/13/2018 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLANNING | 6/1/2018 | | 7/9/2018 | | PASS |
David Moser
|
|
|
|
Routing - PLAN CHECK | 7/6/2018 | | 7/6/2018 | | FAIL |
Josh Bogle
|
|
|
|
Routing Walk-In (BLD) | 6/26/2018 | 6/26/2018 | 6/26/2018 | P | FAIL |
Josh Bogle
|
|
|
chatted face to face
|
Routing PW Grading-Hillside | 6/7/2018 | | 6/15/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
|
1st review completed | | | 6/8/2018 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 6/1/2018 | | 6/8/2018 | | FAIL |
Josh Bogle
|
|
|
|
Routing PW Grading-Hillside | 6/4/2018 | | 6/5/2018 | | FAIL |
Melissa Jannusch
|
|
|
See changemarks in ePlan
|
Routing - PUBLIC WORKS | 6/1/2018 | | 6/4/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 6/1/2018 | | 6/4/2018 | | PASS |
Michael Zawacki
|
|
|
Addition, no site prep inspection required.
|
Plans ACCEPTED BY PLAN TECH | | | 6/1/2018 | | DONE |
|
|
|
|
Intake Approval | | | 6/1/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/1/2018 | | DONE |
|
|
|
|
Intake Approval | | | 5/21/2018 | | FAIL |
|
|
|
Please wait for the CFH18-00030 appeal period to end on May 31st at 5:00 pm.
|
Intake Approval | | | 3/22/2018 | | FAIL |
|
|
|
Catagory 2 is required, need pre approval from P & Z, wrong app is filled out needs so submit correct app, need grading and drainage
|
Application received | | | 3/21/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 21 2018 7:42PM
|