Print Statement | | | 7/19/2019 | | DONE |
|
|
|
|
First Notice | | 6/22/2019 | 7/10/2019 | | DONE |
|
|
|
mailed 7-11
|
PubWorks Occupancy Approval | 6/12/2019 | 6/12/2019 | 6/12/2019 | | DONE |
Tiffany Lowery
|
|
|
|
Permanent Occupancy | | | 6/12/2019 | | DONE |
|
|
|
|
BLD-Final | 6/6/2019 | 6/7/2019 | 6/7/2019 | P | PASS |
Jim Storey
|
|
|
Please call before arriving. Thank you. Phone #: ###-#### Inspection requested via web by Joel Hartman sign offs pw/zone/achd ok for perm no card on site
|
Zoning Approval | 6/7/2019 | 6/7/2019 | 6/7/2019 | | PASS |
Katelyn Menuge
|
|
|
|
BLD-Final | 4/30/2019 | 5/1/2019 | 5/1/2019 | P | PART |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hartman need sign offs pw/zone/achd
|
FIRE-Final Inspection | 4/30/2019 | 5/1/2019 | 5/1/2019 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
Phone #: ###-#### Inspection requested via web by Joel Hartman
|
BLD-Final | 4/30/2019 | 4/30/2019 | 4/30/2019 | P | CANC |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by Joel Hartman Inspection cancelled from web by: Joel Hartman
|
FIRE-Final Inspection | 4/29/2019 | 4/30/2019 | 4/30/2019 | A | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Joel Hartman Inspection cancelled from web by: Joel Hartman
|
BLD-Final | 4/29/2019 | 4/30/2019 | 4/30/2019 | P | CANC |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by Joel Hartman Inspection cancelled from web by: Joel Hartman
|
FIRE-Final Inspection | 4/25/2019 | 4/26/2019 | 4/26/2019 | A | FAIL |
Jim Page
|
|
|
Exit discharge emergency lighting on shop bay exits did not illuminate with power loss, exit discharge landings are required to have emergency egress illumination to be code compliant.
Joel Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 2/5/2019 | 2/5/2019 | 2/5/2019 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hartman
|
BLD-Wall cover | 12/28/2018 | 1/3/2019 | 1/3/2019 | A | PASS |
Jim Storey
|
|
|
Please call when headed to site. Phone #: ###-#### Inspection requested via web by Joel Hartman
|
BLD-Wall cover | 12/28/2018 | 1/2/2019 | 12/28/2018 | A | CANC |
Jim Storey
|
|
|
Please call when heading over to site. Thank you. Phone #: ###-#### >> Inspection requested via web by Joel Hartman Inspection cancelled from web by: Joel Hartman
|
BLD-Wall cover | 12/26/2018 | 12/26/2018 | 12/26/2018 | A | CANC |
Jim Storey
|
|
|
inspect densglass before water proofing membrane. Phone #: ###-#### >> Inspection requested via web by Joel Hartman Inspection cancelled from web by: Joel Hartman
|
BLD-Framing/Rough-in | 12/5/2018 | 12/6/2018 | 12/6/2018 | A | PASS |
Jim Storey
|
|
|
Please call when you get to the site, or headed that way. Thank you, Joel Phone #: ###-#### Inspection requested via web by Joel Hartman framing ok pending trades ok to cover
|
BLD-Other | 9/24/2018 | 9/24/2018 | 9/24/2018 | P | PASS |
Jim Storey
|
|
|
Masonry rebar. Phone #: ###-#### Inspection requested via web by Joel Hartman
|
BLD-Footing | 8/15/2018 | 8/15/2018 | 8/15/2018 | P | PASS |
Jim Storey
|
|
|
Footing inspection at Trash Enclosure. Phone #: ###-#### Inspection requested via web by Joel Hartman
|
BLD-Foundation | 7/26/2018 | 7/27/2018 | 7/27/2018 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hartman
|
BLD-Foundation | 7/25/2018 | 7/26/2018 | 7/26/2018 | P | CANC |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by Joel Hartman Inspection cancelled from web by: Joel Hartman
|
BLD-Footing | 7/19/2018 | 7/20/2018 | 7/20/2018 | A | PASS |
Jim Storey
|
|
|
Early AM please, trying to place concrete at 11:00 AM. Phone #: ###-#### Inspection requested via web by Joel Hartman si on site
|
Issue PAID IN FULL permit | | | 7/6/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/6/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 5/21/2018 | | |
|
|
|
|
Plan assigned to (JG) | 3/30/2018 | 3/30/2018 | 5/21/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 4/26 Donahue McNamara Steel New building ePlan--
|
Routing PW Drainage | 5/21/2018 | | 5/21/2018 | | PASS |
Brian Murphy
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/21/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/21/2018 | | DONE |
Christina Prado
|
|
|
Need:
ACHD - met, need receipt or payment 6/29/18
RP - N/A see GRD18-00075, attached ESC voided
GC - met
Revised Certificate of Value - met
|
Routing - PLAN CHECK | 5/15/2018 | | 5/19/2018 | | PASS |
Javier Guzman
|
|
|
|
Routing Off Site - STRUCTURAL | 5/15/2018 | | 5/19/2018 | | PASS |
Javier Guzman
|
|
|
signed off in ePlan by AHJ Engineers Chris Holladay
|
Routing PW Sewer Design | 5/15/2018 | | 5/18/2018 | | PASS |
DeAnn Brown
|
|
|
|
Route to Impact Fee Review | 5/1/2018 | 5/4/2018 | 5/3/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 3/30/2018 | | 5/1/2018 | | FAIL |
Javier Guzman
|
|
|
|
1st review completed | | | 5/1/2018 | | DONE |
Javier Guzman
|
|
|
|
Routing Off Site - STRUCTURAL | 3/30/2018 | | 4/30/2018 | | FAIL |
Javier Guzman
|
|
|
Failed in ePlan by AHJ Engineers Chris Holladay
|
Routing - FIRE | 3/30/2018 | 3/30/2018 | 4/25/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing PW Sewer Design | 4/2/2018 | | 4/6/2018 | | FAIL |
DeAnn Brown
|
|
|
Please make corrections specified in changemarks on utility plan sheet C05 in eplanreview.
|
Routing PW Environmental | 4/2/2018 | | 4/5/2018 | | PASS |
Rick Christenson
|
|
|
Exterior Interceptor will need to be rated for Flammable Liquids and vented properly if vehicle maintenance is being done in the shop area.
|
Routing - MECHANICAL | 3/30/2018 | | 4/4/2018 | | PASS |
Troy James
|
|
|
Asked applicant to provide letter from owner stating what type of work is being performed in the shop. Letter attached to documents
|
Routing - PLANNING | 3/30/2018 | | 4/2/2018 | | PASS |
David Moser
|
|
|
See DRH17-00443
|
Routing - Addressing | 3/30/2018 | | 4/2/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 3/30/2018 | | 4/2/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing PW Solid Waste | 4/2/2018 | | 4/2/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Drainage | 4/2/2018 | | 4/2/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Street Lights | 4/2/2018 | | 4/2/2018 | | PASS |
Tom Marshall
|
|
|
|
Intake Approval | | | 3/30/2018 | | PASS |
|
|
|
|
Routing - PLUMBING | 3/30/2018 | | 3/30/2018 | | PASS |
Bill VanDegrift
|
|
|
See redline notes, and install per ISPC.
|
Routing - Design Review | 3/30/2018 | | 3/30/2018 | | PASS |
Katelyn Menuge
|
|
|
DRH17-00443
|
Intake Approval | | | 3/26/2018 | | FAIL |
Julie Romig
|
|
|
|
Application received | | | 3/22/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 22 2018 8:40AM
|