BLD-Final | 8/17/2018 | 8/20/2018 | 8/20/2018 | P | PASS |
Tony Young
|
|
|
Garage code is 1280 Phone #: ###-#### Inspection requested via web by Evan Waters
|
DOC - Permit Finaled | 8/20/2018 | 8/20/2018 | 8/20/2018 | P | PASS |
Tony Young
|
|
|
|
BLD-Framing/Rough-in | 6/13/2018 | 6/14/2018 | 6/14/2018 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Evan Waters
|
BLD-Energy code compliance | 6/8/2018 | 6/8/2018 | 6/8/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Evan Waters
|
BLD-Framing/Rough-in | 6/6/2018 | 6/6/2018 | 6/6/2018 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Evan Waters,, need 2 truss fixes ,, strap top plates/beams,, ok to insulate
|
BLD-Wall Bracing | 5/14/2018 | 5/14/2018 | 5/14/2018 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Evan Waters
|
BLD-Wall Bracing | 5/11/2018 | 5/14/2018 | 5/14/2018 | A | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Evan Waters
|
BLD-Foundation | 4/25/2018 | 4/26/2018 | 4/26/2018 | A | PART |
Tony Young
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo,, work in progress
|
BLD-Footing | 4/24/2018 | 4/25/2018 | 4/26/2018 | P | PART |
Tony Young
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo
|
BLD-Footing | 4/22/2018 | 4/23/2018 | 4/23/2018 | P | NR |
Tony Young
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo
|
Issue PAID IN FULL permit | | | 4/11/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 4/5/2018 | | |
|
|
|
|
Telephone call | | | 4/5/2018 | | DONE |
|
|
|
Left a message for Lisa informing her this permit is ready, the fee amount due and that another RP will be needed (see andy's not in esc)
|
Inspection Record Card- Bld | | | 4/5/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/5/2018 | | DONE |
|
|
|
met
|
Plan assigned to (BJM) | 3/22/2018 | 3/22/2018 | 4/4/2018 | | DONE |
Brian McGowan
|
|
|
1st review complete - FAIL- Must provide RP to ESC-4-4 sfd L1 paper
|
Routing - PLAN CHECK | 3/27/2018 | | 4/4/2018 | | PASS |
Brian McGowan
|
|
|
Must provide RP to ESC before issuing permit.
|
1st review completed | | | 4/4/2018 | | DONE |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 4/4/2018 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/4/2018 | | DONE |
Brian McGowan
|
|
|
|
Routing - Erosion and Sediment | 3/29/2018 | | 3/29/2018 | | PASS |
Andy J. Long
|
|
|
Asbury Construction needs to list their own RP. Wood Bros. not doing RP work for entire project. Asbury to get Interim RP or complete RP class.
|
Routing - MECHANICAL | 3/23/2018 | | 3/27/2018 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 3/23/2018 | 3/26/2018 | 3/26/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 3/23/2018 | | 3/23/2018 | | PASS |
Colleen T Carroll
|
|
|
The site plan does not scale but setbacks are correct as written.
|
Routing - Addressing | 3/23/2018 | | 3/23/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | | | 3/23/2018 | | PASS |
|
|
|
|
Intake Approval | | | 3/22/2018 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/22/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/22/2018 | | DONE |
|
|
|
|
Application received | | 3/22/2018 | | | |
|
|
|
|