BLD-Final | 11/6/2018 | 11/7/2018 | 11/8/2018 | P | PASS |
Brandon Shaw
|
|
|
Rollo Phone #: ###-####
|
DOC - Permit Finaled | 11/8/2018 | 11/8/2018 | 11/8/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 11/8/2018 | 11/8/2018 | 11/8/2018 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 4.26 ACH50- 4.26
|
PubWorks Occupancy Approval | 11/8/2018 | 11/8/2018 | 11/8/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Energy code compliance | 7/27/2018 | 7/30/2018 | 7/30/2018 | A | PASS |
Brandon Shaw
|
|
|
Corrections SAT...
|
BLD-Other | 7/26/2018 | 7/26/2018 | 7/26/2018 | P | PASS |
Brandon Shaw
|
|
|
sofit- Rollo Phone #: ###-####
|
BLD-Framing/Rough-in | 7/26/2018 | 7/26/2018 | 7/26/2018 | P | PASS |
Brandon Shaw
|
|
|
OK to insulate
|
BLD-Framing/Rough-in | 7/24/2018 | 7/24/2018 | 7/24/2018 | P | FAIL |
Brandon Shaw
|
|
|
See correction notice and red paint
OK to insulate
|
BLD-Wall Bracing | 7/2/2018 | 7/2/2018 | 7/2/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Foundation | 6/3/2018 | 6/4/2018 | 6/4/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 5/31/2018 | 6/1/2018 | 6/1/2018 | A | PASS |
Brandon Shaw
|
|
|
Work in progress
|
PubWorks Subgrade Approval | 5/25/2018 | 5/25/2018 | 5/25/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
OVERRIDE | | | 5/10/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 4/17/2018 | 4/17/2018 | 5/10/2018 | | DONE |
Brian McGowan
|
|
|
1st review complete - FAIL - 5-4 sfd L2 ePlan
|
Issue PAID IN FULL permit | | | 5/10/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/10/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/10/2018 | | 5/10/2018 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/10/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 5/10/2018 | | DONE |
|
|
|
met
|
Routing - PUBLIC WORKS | 4/17/2018 | | 5/2/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing PW Grading-Hillside | 4/18/2018 | | 5/2/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
|
1st review completed | | | 5/2/2018 | | FAIL |
Brian McGowan
|
|
|
REQUIRED ENGINEERING WAS NOT PROVIDED. Misc structural items
|
Routing - PLAN CHECK | 4/17/2018 | | 5/2/2018 | | FAIL |
Brian McGowan
|
|
|
REQUIRED ENGINEERING WAS NOT PROVIDED. Misc structural items
|
Routing - FIRE | 4/17/2018 | 4/17/2018 | 4/20/2018 | | PASS |
Tim Frost
|
|
|
5/04 house eplan
|
Route to Impact Fee Review | 4/17/2018 | 4/20/2018 | 4/18/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 4/17/2018 | | 4/18/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 4/17/2018 | | 4/17/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 4/17/2018 | | 4/17/2018 | | PASS |
Doug Chausow
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/17/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/17/2018 | | DONE |
|
|
|
|
Intake Approval | | | 4/17/2018 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 4/17/2018 | | 4/17/2018 | | PASS |
Michael Zawacki
|
|
|
Harris North, foothill subdivision. Site prep inspection required.
|
Application received | | | 3/22/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 22 2018 1:53PM
|
Intake Approval | | | 3/22/2018 | | FAIL |
|
|
|
NEED TO FIX DECK PLAN VIEW ON A3.0, Blurry
|