Information based on query as of Thursday, June 20, 2024.
Permit Information
Permit NumberBLD18-01007
StatusFinaled
Name HHS CONSTRUCTION LLC
Site Address 5525 E HOOTOWL DR
Project NameTablerock - HN 38-1
Customer Number 
ePlanReviewYes
Description
HILLSIDE, WUI FOOTHILLS, ZONE "A" REQUIREMENTS, CLASS "A" ROOF REQUIRED. Permit for the construction of a new 3346 sq. ft., two story (first story 2374 sq. ft., second story 972 sq. ft.) single family dwelling with 4 bedrooms, 3.5 bathrooms, approximately 328 sq. ft. of covered patio/porch and a 1119 sq. ft. attached garage per the approved plans, plan review report and any notations. SP-01 zoning and setbacks per planning. ***BJM***A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.

Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/6/201811/7/201811/8/2018PPASS
DetailsBrandon Shaw
Rollo Phone #: ###-####
DOC - Permit Finaled11/8/201811/8/201811/8/2018PPASS
DetailsBrandon Shaw
BLD-Blower Door Test Results11/8/201811/8/201811/8/2018ADONE
DetailsBrandon Shaw
ACH50- 4.26
ACH50- 4.26
PubWorks Occupancy Approval11/8/201811/8/201811/8/2018 DONE
DetailsMelissa Jannusch
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
BLD-Energy code compliance7/27/20187/30/20187/30/2018APASS
DetailsBrandon Shaw
Corrections SAT...
BLD-Other7/26/20187/26/20187/26/2018PPASS
DetailsBrandon Shaw
sofit- Rollo Phone #: ###-####
BLD-Framing/Rough-in7/26/20187/26/20187/26/2018PPASS
DetailsBrandon Shaw
OK to insulate
BLD-Framing/Rough-in7/24/20187/24/20187/24/2018PFAIL
DetailsBrandon Shaw
See correction notice and red paint

OK to insulate
BLD-Wall Bracing7/2/20187/2/20187/2/2018PPASS
DetailsBrandon Shaw
Work in progress
BLD-Foundation6/3/20186/4/20186/4/2018PPASS
DetailsBrandon Shaw
Work in progress
BLD-Footing5/31/20186/1/20186/1/2018APASS
DetailsBrandon Shaw
Work in progress
PubWorks Subgrade Approval5/25/20185/25/20185/25/2018 DONE
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.

OVERRIDE  5/10/2018  
Plan assigned to (BJM)4/17/20184/17/20185/10/2018 DONE
DetailsBrian McGowan
1st review complete - FAIL - 5-4 sfd L2 ePlan
Issue PAID IN FULL permit  5/10/2018 DONE
Inspection Record Card- Bld  5/10/2018 DONE
Routing - PLAN CHECK5/10/2018 5/10/2018 PASS
DetailsBrian McGowan
PLANS/APPL TAKEN TO FRONT DESK  5/10/2018 DONE
DetailsBrian McGowan
Permit Ready to Issue  5/10/2018 DONE
met
Routing - PUBLIC WORKS4/17/2018 5/2/2018 PASS
DetailsMorgan Webb
Routing PW Grading-Hillside4/18/2018 5/2/2018 PASS
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.

1st review completed  5/2/2018 FAIL
DetailsBrian McGowan
REQUIRED ENGINEERING WAS NOT PROVIDED. Misc structural items
Routing - PLAN CHECK4/17/2018 5/2/2018 FAIL
DetailsBrian McGowan
REQUIRED ENGINEERING WAS NOT PROVIDED. Misc structural items
Routing - FIRE4/17/20184/17/20184/20/2018 PASS
DetailsTim Frost
5/04 house eplan


Route to Impact Fee Review4/17/20184/20/20184/18/2018 PASS
DetailsEric Bilimoria
Initial residential review of new SFD permits requested for now.
Routing - MECHANICAL4/17/2018 4/18/2018 PASS
DetailsTroy James
Routing - PLANNING4/17/2018 4/17/2018 PASS
DetailsSue Cummings
Routing - Addressing4/17/2018 4/17/2018 PASS
DetailsDoug Chausow
Plans ACCEPTED BY PLAN TECH  4/17/2018 DONE
Recd Pcfee & Taken To Pln CK  4/17/2018 DONE
Intake Approval  4/17/2018 PASS
Routing - Erosion and Sediment4/17/2018 4/17/2018 PASS
DetailsMichael Zawacki
Harris North, foothill subdivision. Site prep inspection required.
Application received  3/22/2018 DONE
Application submitted via PDS Online on Mar 22 2018 1:53PM
Intake Approval  3/22/2018 FAIL
NEED TO FIX DECK PLAN VIEW ON A3.0, Blurry