BLD-Final | 5/21/2018 | 5/21/2018 | 5/21/2018 | P | PASS |
Mike Jordan
|
|
|
Chuck Phone #: ###-####. Ok for perm occ.
|
Permanent Occupancy | | | 5/21/2018 | | DONE |
|
|
|
|
BLD-Final | 5/17/2018 | 5/18/2018 | 5/18/2018 | P | PART |
Mike Jordan
|
|
|
Chuck Phone #: ###-####. OK for temp occ. Needs to provide ADA pos.
|
FIRE-Final Inspection | 5/17/2018 | 5/18/2018 | 5/18/2018 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
Chuck Phone #: ###-####
|
BLD-Conference | 5/17/2018 | 5/17/2018 | 5/17/2018 | P | NR |
Mike Jordan
|
|
|
Chuck Phone #: ###-####. fire/life/safeyy final failed.
|
FIRE-Final Inspection | 5/16/2018 | 5/17/2018 | 5/17/2018 | A | FAIL |
Troy Cobbley
|
|
|
Provide address, provide revised floor plan showing the removal of the wall and cooler, repair the non-functional exit signs/emergency lights or remove the non-required/non-functional ones, install ceiling tile, provide automatic flush bolts or get plan review approval to delete in-active leaf of door, mount and tag the fire extinguisher
Chuck Phone #: ###-####
|
BLD-Final | 5/16/2018 | 5/17/2018 | 5/17/2018 | P | CANC |
Mike Jordan
|
|
|
Chuck Phone #: ###-####
|
Print Occupancy Form | | | 5/16/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 3/29/2018 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 3/26/2018 | 3/26/2018 | 3/28/2018 | | DONE |
Julie Romig
|
|
|
03/30 - 528 Boise Nail Supply
|
Routing - PLAN CHECK | | | 3/28/2018 | | PASS |
Julie Romig
|
|
|
|
1st review completed | | | 3/28/2018 | | DONE |
Julie Romig
|
|
|
|
Case Summary (BLD) | | | 3/28/2018 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/28/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/28/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/28/2018 | | DONE |
|
|
|
|
Telephone call | | | 3/28/2018 | | DONE |
|
|
|
informed customer that this permit is ready to be picked up and which ever tech they see will go over the required inspections
|
Plans ACCEPTED BY PLAN TECH | | | 3/26/2018 | | DONE |
|
|
|
|
Intake Approval | | | 3/26/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/26/2018 | | |
|
|
|
|
Application received | | 3/26/2018 | | | |
|
|
|
|