BLD-Final | 11/9/2018 | 11/9/2018 | 11/9/2018 | P | PASS |
Brandon Shaw
|
|
|
|
DOC - Permit Finaled | 11/9/2018 | 11/9/2018 | 11/9/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 11/9/2018 | 11/9/2018 | 11/9/2018 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 3.88
Disregard previous enrty, not applicable to this permit...
|
BLD-Final | 11/9/2018 | 11/9/2018 | 11/9/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress... Interior OSB shear and missing anchor bolts to be installed before framing rough-in...
|
PubWorks Occupancy Approval | 11/2/2018 | 11/2/2018 | 11/2/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Energy code compliance | 8/15/2018 | 8/16/2018 | 8/16/2018 | A | PASS |
Brandon Shaw
|
|
|
Les Phone #: ###-####
|
BLD-Other | 8/15/2018 | 8/15/2018 | 8/15/2018 | P | PASS |
Brandon Shaw
|
|
|
Les- sofit Phone #: ###-####
|
BLD-Framing/Rough-in | 8/10/2018 | 8/13/2018 | 8/13/2018 | A | PASS |
Brandon Shaw
|
|
|
All corrections SAT... Tenting for sprinklers installed OK to insulate
|
BLD-Framing/Rough-in | 8/8/2018 | 8/8/2018 | 8/8/2018 | P | PART |
Brandon Shaw
|
|
|
Floor to floor straps to be insalled, as per plans, at Energy inspection
|
BLD-Wall Bracing | 7/23/2018 | 7/24/2018 | 7/24/2018 | A | PART |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Foundation | 6/5/2018 | 6/6/2018 | 6/7/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 6/5/2018 | 6/5/2018 | 6/5/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
Issue PAID IN FULL permit | | | 5/17/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/17/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 5/16/2018 | | |
|
|
|
|
OVERRIDE | | | 5/16/2018 | | |
|
|
|
|
Plan assigned to (RDP) | 4/2/2018 | 4/2/2018 | 5/16/2018 | | DONE |
Rob Patrick
|
|
|
4/19 sfd L2 ePlan...5/2: Failed: Need to address Grading-Hillside coments
|
Routing PW Grading-Hillside | 5/16/2018 | | 5/16/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
|
Routing - PLAN CHECK | 5/16/2018 | | 5/16/2018 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/16/2018 | | DONE |
Rob Patrick
|
|
|
|
Override - Parcel Holds | | | 5/16/2018 | | |
|
|
|
|
Permit Ready to Issue | | | 5/16/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/15/2018 | | 5/15/2018 | | FAIL |
Rob Patrick
|
|
|
Hillside needs to review.
|
Routing PW Grading-Hillside | 5/7/2018 | | 5/7/2018 | | FAIL |
Melissa Jannusch
|
|
|
See changemarks from 1st review
|
Routing - PLAN CHECK | 5/2/2018 | | 5/2/2018 | | FAIL |
Rob Patrick
|
|
|
Needs to resolve Grading-Hillside comments
|
Routing PW Grading-Hillside | 4/18/2018 | | 4/19/2018 | | FAIL |
Melissa Jannusch
|
|
|
See changemarks in ePlan. Incorrect documents and plans uploaded see ePlan for more detail.
|
Routing - FIRE | 4/2/2018 | 4/2/2018 | 4/5/2018 | | PASS |
Erika Akin
|
|
|
Plans were reviewed for FD access, availability of hydrants and defensible space. Thirty feet defensible space must be maintained between the structure and undeveloped land per BMC 7-1-69.
|
1st review completed | | | 4/5/2018 | | FAIL |
Rob Patrick
|
|
|
Hillside correction req'd. Beam sizing and roofing materials req'd.
|
Routing - PLAN CHECK | 4/2/2018 | | 4/5/2018 | | FAIL |
Rob Patrick
|
|
|
4/5 Failed: Roofing materials required
|
Routing - MECHANICAL | 4/2/2018 | | 4/4/2018 | | PASS |
Troy James
|
|
|
|
Routing - Erosion and Sediment | 4/2/2018 | | 4/4/2018 | | PASS |
Michael Zawacki
|
|
|
Harris North. Site prep inspection required.
|
Routing PW Grading-Hillside | 4/3/2018 | | 4/4/2018 | | FAIL |
Melissa Jannusch
|
|
|
see changemarks in ePlan
|
Route to Impact Fee Review | 4/2/2018 | 4/5/2018 | 4/3/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 4/2/2018 | | 4/3/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - PUBLIC WORKS | 4/2/2018 | | 4/3/2018 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/2/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/2/2018 | | DONE |
|
|
|
|
Intake Approval | | | 4/2/2018 | | PASS |
|
|
|
|
Routing - Addressing | 4/2/2018 | | 4/2/2018 | | PASS |
Doug Chausow
|
|
|
|
Application received | | | 3/29/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 29 2018 1:23PM
|
PubWorks Subgrade Approval | 5/25/2018 | | | | DONE |
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. A footing inspection may now be scheduled with the Building Department.
|