Permit Information
Permit NumberBLD18-01117
StatusFinaled
Name AURIC SOLAR
Site Address 6006 W ROBERTSON DR
Project Name176106 - Adell
Customer Number 
ePlanReviewYes
Description
Permit for 455sq' of roof-mounted, grid-tied Photo-voltaic panels with micro-inverters; 26 panels in 2 arrays tying into a SquareD panel. One array (20 panels) will be on the detached garage, one array (6 panels) will be on the residence. No work needed to strengthen the existing roof structure per engineer’s roof evaluation. All work per plans, engineering, manufacturer’s specs, & local code. Separate electrical permit required. **JAB**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/10/20187/11/20187/11/2018ADONE
DetailsMike Jordan
Pls contact Brad (Foreman) @ ###-#### or Preston (Electrician) @ ###-#### one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes
DOC - Permit Finaled7/11/20187/11/20187/11/2018PPASS
DetailsMike Jordan
BLD-Final7/3/20187/9/20187/9/2018ANR
DetailsMike Jordan
Pls contact Brad (Foreman) @ ###-#### or Preston (Electrician) @ ###-#### one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes
Plan assigned to (RDP)6/25/20186/25/20186/29/2018 DONE
DetailsRob Patrick
6/28 P/V Plan Mod
Routing - PLAN CHECK6/29/2018 6/29/2018 PASS
DetailsRob Patrick
no fees due
PLANS/APPL TAKEN TO FRONT DESK  6/29/2018 DONE
DetailsRob Patrick
Permit Ready to Issue  6/29/2018 DONE
CHANGE STATUS TO (ISS)  6/29/2018 DONE
(F) Reprint permit  6/29/2018 DONE
Plan Modification Accepted  6/25/2018 DONE
as per JAR-start plan mod per Rob P in e plan
Plan assigned to (JAB) Josh3/30/20183/30/20184/2/2018 PASS
DetailsJosh Bogle
due 4/5 - PV
Routing - PLAN CHECK3/30/2018 4/2/2018 PASS
DetailsJosh Bogle
1st review completed  4/2/2018 DONE
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  4/2/2018 DONE
DetailsJosh Bogle
ESC no - Energy no
Permit Ready to Issue  4/2/2018 DONE
Met
Issue PAID IN FULL permit  4/2/2018 DONE
Application received  3/30/2018 DONE
Application submitted via PDS Online on Mar 30 2018 8:52AM
Plans ACCEPTED BY PLAN TECH  3/30/2018 DONE
Intake Approval  3/30/2018 PASS
Recd Pcfee & Taken To Pln CK  3/30/2018 DONE
no fees paid at intake
Routing - PLANNING3/30/2018 3/30/2018 PASS
DetailsSue Cummings