Change Expiration Date Only | | | 4/3/2020 | | DONE |
Jason Blais
|
|
|
A 180 day extension is approved. This is the first extension request for an issued permit.
|
Telephone call | | | 4/3/2020 | | DONE |
|
|
|
Email from Kyle requesting an extension forwarded to Jason T
|
Extend Review Timeline | | | 4/3/2020 | | DONE |
|
|
|
1st Approved 180 Extension per Jason B. See documents
|
BLD-Aging Inspection | 2/20/2020 | 2/20/2020 | 2/21/2020 | | PEND |
Mike Jordan
|
|
|
Ok to place pending speciial inspection.
|
BLD-Framing/Rough-in | 10/7/2019 | 10/8/2019 | 10/8/2019 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Kernin,, wall bracing and roof ok to cover,, will acquire an electrical permit and inspection prior to scheduling a frame inspection
|
BLD-Foundation | 1/17/2019 | 1/18/2019 | 1/18/2019 | A | PASS |
Mike Jordan
|
|
|
Eric Phone #: ###-####. Vertical steel added at #4 @32"o.c. with 2 #4's at top of stemwall.
|
BLD-Footing | 1/15/2019 | 1/17/2019 | 1/17/2019 | A | PART |
Mike Jordan
|
|
|
Eric Phone #: ###-####. Footings ok. Per engineer, vertical reinforcement is equired.
|
OVERRIDE | | | 11/30/2018 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 11/30/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/30/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 11/29/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 11/28/2018 | 11/28/2018 | 11/29/2018 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 11/29/2018 | | 11/29/2018 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 11/29/2018 | | DONE |
Brian McGowan
|
|
|
|
Inspection Record Card- Bld | | | 11/29/2018 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/29/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 11/29/2018 | | DONE |
|
|
|
|
Telephone call | | | 11/29/2018 | | DONE |
|
|
|
left message that permit is ready and the fee amount due for issuance
|
Routing Walk-In (BLD) | 11/28/2018 | 11/28/2018 | 11/28/2018 | A | PASS |
Brian McGowan
|
|
|
took in for BJM
|
Plan Reviewer's activity | | | 11/28/2018 | | DONE |
Brian McGowan
|
|
|
Needed updated engineering sheet for footings. Will email them to me. Took in paper plans to final when I get them.
|
Routing Walk-In (Zoning) | 11/27/2018 | 11/27/2018 | 11/27/2018 | P | PASS |
Jeff Lowe
|
|
|
|
Routing Walk-In (BLD) | 11/27/2018 | 11/27/2018 | 11/27/2018 | P | FAIL |
Brian McGowan
|
|
|
|
1st review completed | | | 11/27/2018 | | FAIL |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 11/27/2018 | | 11/27/2018 | | FAIL |
Brian McGowan
|
|
|
Plans were not dimensioned. need a wall section, engineering details not on drawings.
|
Routing Walk-In (Zoning) | 3/30/2018 | 3/30/2018 | 3/30/2018 | P | PASS |
Josh Bogle
|
|
|
Needs C of shop of 1500 sq. ft.
|
Application received | | 3/30/2018 | | | |
|
|
|
|