Meeting | | | 2/10/2020 | | DONE |
|
|
|
Received revised final cert of value.
|
Telephone call | | | 2/6/2020 | | DONE |
|
|
|
Emailed John to check on the new final values and when they were going to send them to us. (since they were submitted incorreclty).
|
Telephone call | | | 1/14/2020 | | DONE |
|
|
|
spoke with Jonathan Yorgason, and he informed me that he email Tisha regarding the outstanding fees. He said that the owner was going to looked into the fees that are due.
|
Telephone call | | | 1/14/2020 | | DONE |
|
|
|
spoke to Jon Yorgason (JEH Const). He said final value submitted online was incorrect because he added up all values instead of breaking out trades as portions. He said owner Joe Blumberg has final numbers. Emailed Jon and Joe to fill out new 306 form to submit final values correctly.
|
Meeting | | | 1/8/2020 | | DONE |
|
|
|
sent statement
|
Telephone call | | | 12/31/2019 | | DONE |
|
|
|
left message at ###-#### to informed them that there is an ounstanding balance on this permit for the final values that were submitted
|
Print Statement | | | 5/1/2019 | | |
|
|
|
|
Second Notice | | 1/18/2019 | 1/25/2019 | | DONE |
|
|
|
This permit finaled on the web by Jon Yorgason
|
First Notice | | 12/27/2018 | 1/8/2019 | | DONE |
|
|
|
mailed 1-11-19
|
PubWorks Occupancy Approval | 12/17/2018 | 12/17/2018 | 12/17/2018 | | DONE |
Tiffany Lowery
|
|
|
|
Permanent Occupancy | | | 12/17/2018 | | DONE |
|
|
|
|
BLD-Final | 12/3/2018 | 12/4/2018 | 12/4/2018 | P | PASS |
Mike Jordan
|
|
|
joseph Phone #: ###-####. Ok for temp occ. Will be ok for perm occ. once public works signs perm.
|
Temporary Occupancy | 12/4/2018 | 3/4/2019 | 12/4/2018 | | DONE |
Tiffany Carson-Herker
|
|
|
|
Zoning Approval | 12/4/2018 | 12/4/2018 | 12/4/2018 | | PASS |
Katelyn Menuge
|
|
|
|
FIRE-Final Inspection | 11/30/2018 | 12/3/2018 | 12/3/2018 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
joesph Phone #: ###-####
|
FIRE-Final Inspection | 11/29/2018 | 11/29/2018 | 11/29/2018 | P | FAIL |
Troy Cobbley
|
|
|
Provide address as discussed and provide door hardware as discussed. All other items appear ok.
Joseph Phone #: ###-####
|
FIRE-Final Inspection | 11/29/2018 | 11/29/2018 | 11/29/2018 | P | CANC |
Troy Cobbley
|
|
|
duplicate inspection.
Joseph Phone #: ###-####
|
BLD-Framing/Rough-in | 11/19/2018 | 11/19/2018 | 11/19/2018 | P | PASS |
Mike Jordan
|
|
|
Joseph-grid wire Phone #: ###-####. ceiling grid ok.
|
BLD-Energy code compliance | 10/5/2018 | 10/5/2018 | 10/5/2018 | P | PASS |
Mike Jordan
|
|
|
Joseph Blumberg ###-####
|
OVERRIDE | | | 10/5/2018 | | |
|
|
|
|
Plan assigned to (CJW) | 9/18/2018 | 9/18/2018 | 10/5/2018 | | PASS |
Carl Westfall
|
|
|
Plan Mod - Cars and trucks unlimited (drawings routed)
|
Plan Reviewer's activity | | | 10/5/2018 | | PASS |
|
|
|
2nd plan mod approved
|
Permit Ready to Issue | | | 10/5/2018 | | DONE |
|
|
|
Plan Mod Approved
Do not reissue ( plan mod fees due)
|
CHANGE STATUS TO (ISS) | | | 10/5/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/5/2018 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 10/2/2018 | 10/2/2018 | 10/2/2018 | P | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####
|
Routing PW Drainage | 10/1/2018 | | 10/2/2018 | | PASS |
Brian Murphy
|
|
|
Please move your approval stamp to the most recent version
|
Plan resubmittals received | | | 10/1/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/1/2018 | | 10/1/2018 | | PASS |
Carl Westfall
|
|
|
Routed drawings
|
Routing - Design Review | 10/1/2018 | | 10/1/2018 | | PASS |
Katelyn Menuge
|
|
|
|
BLD-Framing/Rough-in | 9/25/2018 | 9/28/2018 | 9/28/2018 | P | FAIL |
Mike Jordan
|
|
|
jeff Phone #: ###-####.. Needs to complete airseal. Construct new wall as per the engineering or have engineer approve in place contruction.
|
Plan resubmittals requested | | | 9/28/2018 | | DONE |
|
|
|
|
Routing PW Drainage | 9/24/2018 | | 9/27/2018 | | PASS |
Brian Murphy
|
|
|
Please stamp the most recent version
|
Routing - Design Review | 9/19/2018 | | 9/24/2018 | | FAIL |
Katelyn Menuge
|
|
|
Changes needed to site plan.
|
Routing - PLAN CHECK | 9/19/2018 | | 9/24/2018 | | PASS |
Carl Westfall
|
|
|
Routed to other agencies
|
Routing PW Street Lights | 9/24/2018 | | 9/24/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing - PUBLIC WORKS | 9/24/2018 | | 9/24/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLAN CHECK | 9/18/2018 | | 9/19/2018 | | PASS |
Carl Westfall
|
|
|
2nd plan mod plan intake approved
|
Plan Modification Accepted | | | 9/18/2018 | | DONE |
|
|
|
Plan Modification #2 application accepted. Adjust property line back to original location per ACHD's rescind, and modify parking to accommodate. Modify landscaping per owner. Show new concrete replacing existing. Remove door between shop and storage, add closet for server per owner.
|
BLD-Framing/Rough-in | 9/6/2018 | 9/6/2018 | 9/6/2018 | P | CANC |
Mike Jordan
|
|
|
Jeff Phone #: ###-####
|
BLD-Wall Bracing | 9/6/2018 | 9/6/2018 | 9/6/2018 | P | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####
|
BLD-Wall Bracing | 9/5/2018 | 9/5/2018 | 9/5/2018 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 9/4/2018 | 9/5/2018 | 9/5/2018 | A | NR |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Need wall beracing plan from engineer.
|
CHANGE STATUS TO (ISS) | | | 8/22/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/22/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 8/20/2018 | | |
|
|
|
|
Plan assigned to (CJW) | 8/9/2018 | 8/9/2018 | 8/20/2018 | | PASS |
Carl Westfall
|
|
|
Plan mod - Trucks and Cars Unlimited (1st IBC review done - routed)
|
Permit Ready to Issue | | | 8/20/2018 | | DONE |
|
|
|
Plan Mod Approved
DO NOT REISSSUE
(change back to issued status once plan mod fees are paid)
|
Routing - Design Review | 8/11/2018 | | 8/14/2018 | | PASS |
Katelyn Menuge
|
|
|
Modifications okay
|
Routing - PLAN CHECK | 8/11/2018 | | 8/11/2018 | | PASS |
Carl Westfall
|
|
|
Plan mod approved
|
Routing - PLAN CHECK | 8/9/2018 | | 8/10/2018 | | PASS |
Carl Westfall
|
|
|
Plan mod plan intake review approved
|
Plan Modification Accepted | | | 8/9/2018 | | DONE |
|
|
|
Plan mod workflow started to add walls and add doors to create four office spaces and a reception area. Adjust exterior windows as needed.
|
BLD-Foundation | 8/6/2018 | 8/7/2018 | 8/7/2018 | A | PASS |
Mike Jordan
|
|
|
Wall // Cameron Phone #: ###-####
|
BLD-Footing | 8/1/2018 | 8/2/2018 | 8/2/2018 | P | PASS |
Mike Jordan
|
|
|
Cameron Phone #: ###-####
|
Issue PAID IN FULL permit | | | 7/11/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/11/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 7/6/2018 | | |
|
|
|
|
Plan assigned to (CJW) | 5/16/2018 | 5/16/2018 | 7/6/2018 | | PASS |
Carl Westfall
|
|
|
* (2nd done) (June 14 - 25 days) (26 sheets) Trucks and Cars Unlimited addition
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/6/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/6/2018 | | DONE |
|
|
|
MET
Need:
ACHD-met
GC form
Revised value from GC
Verify RP-Met
|
Routing Off Site - STRUCTURAL | 6/27/2018 | | 7/4/2018 | | PASS |
Carl Westfall
|
|
|
Dave Haugland (AHJ)
|
Routing PW Drainage | 6/27/2018 | | 7/2/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing - Design Review | 6/27/2018 | | 6/28/2018 | | PASS |
Katelyn Menuge
|
|
|
|
Routing - PLUMBING | 6/27/2018 | | 6/28/2018 | | PASS |
Bill VanDegrift
|
|
|
See notes and install per ISPC
|
Routing - PLAN CHECK | 6/26/2018 | | 6/27/2018 | | PASS |
Carl Westfall
|
|
|
Pending structural - remember to upload the plan review report
|
Plan resubmittals received | | | 6/26/2018 | | DONE |
|
|
|
|
Route to Impact Fee Review | 6/18/2018 | 6/21/2018 | 6/19/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Plan resubmittals requested | | | 6/18/2018 | | DONE |
|
|
|
|
1st review completed | | | 6/18/2018 | | DONE |
|
|
|
|
Routing - FIRE | 5/16/2018 | 5/16/2018 | 6/14/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - PLAN CHECK | 5/16/2018 | | 6/8/2018 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Routing Off Site - STRUCTURAL | 5/16/2018 | | 5/31/2018 | | FAIL |
Carl Westfall
|
|
|
Dave Haugland (AHJ)
|
Routing - MECHANICAL | 5/16/2018 | | 5/22/2018 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 5/16/2018 | | 5/18/2018 | | FAIL |
Katelyn Menuge
|
|
|
DRH17-00563 Corrections Required
|
Routing - Erosion and Sediment | 5/16/2018 | | 5/18/2018 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Certified RP and PD. Site preparation inspection is required.
|
Routing PW Drainage | 5/17/2018 | | 5/18/2018 | | FAIL |
Brian Murphy
|
|
|
FAIL NEEDS DRAINAGE PLAN.
|
Routing PW Solid Waste | 5/17/2018 | | 5/17/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Environmental | 5/17/2018 | | 5/17/2018 | | PASS |
Rick Christenson
|
|
|
Oil/sediment interceptor noted in plans.
|
Routing PW Street Lights | 5/17/2018 | | 5/17/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing - PLUMBING | 5/16/2018 | | 5/17/2018 | | FAIL |
Bill VanDegrift
|
|
|
1) R.P. required on hose connections in the garage.
2) indirect waste receptors may not be in cabinets.
3) downstream interceptor vent is to be in downstream piping, see detail.
4) flammable vepor vent and sanitary vent may not be combined.
5) trap and vent interior flammable liquids fixtures.
|
Routing - PLANNING | 5/16/2018 | | 5/17/2018 | | PASS |
David Moser
|
|
|
See DRH17-00563
|
Routing - Addressing | 5/16/2018 | | 5/17/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 5/16/2018 | | 5/17/2018 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/16/2018 | | DONE |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/16/2018 | | DONE |
|
|
|
|
Intake Approval | | | 5/11/2018 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 5/10/2018 | | PASS |
|
|
|
Plan intake review approved
|
Intake Approval | | | 5/9/2018 | | FAIL |
|
|
|
(5-9-18) All pages of the entire Form 310 that apply need to be filled out and uploaded. Special Inspection is required for high strength bolting, etc. as required by the 2015 IBC and acknowledged by the project engineer. CJW
|
Intake Approval | | | 4/27/2018 | | FAIL |
|
|
|
(4-27-18) All pages of the entire Form 310 that apply need to be filled out and uploaded. Special Inspection is required for high strength bolting, etc. as required by the 2015 IBC and acknowledged by the project engineer.
|
Intake Approval | | | 4/24/2018 | | FAIL |
|
|
|
(4-24-18) Please refer to the circled items in the Plan Intake checklist. Please resolve each item as directed. If you do not understand what is required, please call me at ###-#### to discuss. CJW
|
Intake Approval | | | 4/10/2018 | | FAIL |
|
|
|
(4-10-18) Please refer to the circled items in the Plan Intake checklist. Please resolve each item as directed. CJW
|
Application received | | | 4/4/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 4 2018 12:16PM
|