Permit Information
Permit NumberBLD18-01160
StatusFinaled
Name JEH CONSTRUCTION
Site Address 5941 W FAIRVIEW AVE
Project NameTrucks and Cars Unlimited
Customer Number 
ePlanReviewYes
Description
(TRUCKS AND CARS UNLIMITED – PARTIAL DEMOLITION AND BUILDING ADDITION) (DRH17-00563) (10-5-18 PLAN MODIFICATION TO REVISE THE PARKING LOT, MODIFY THE LANDSCAPING, PLACE A NEW EXTERIOR CONCRETE SLAB ON GRADE, REMOVE THE INTERIOR DOOR BETWEEN THE SHOP AND A STORAGE ROOM CREATING AN OPEN HALLWAY, AND TO ADD A CLOSET FOR THE COMPUTER SERVER.) (8-20-18 PLAN MODIFICATION TO ADD AND RELOCATE WALLS AND DOORS TO CREATE ADDITIONAL OFFICE SPACES AND A RECEPTION AREA WITHIN AN EXISTING INTERIOR SPACE. THE LOCATION OF EXTERIOR WINDOWS WILL BE ADJUSTED TO ACCOMMODATE THE NEW INTERIOR PARTITIONS.) This building does not have a fire sprinkler system. About 1,619 square feet of an existing 3,174 square foot building will be demolished and about 1,555 square feet will remain. To construct an 1,898 square foot addition to the remaining 1,555 square foot building. After the addition, this building will have a total floor area of about 3,453 square feet. The net increase in building floor area is about 279 square feet. For the portion of the existing building that will remain, work includes concrete footings, concrete stem wall, a wood stud bearing wall with headers and trimmers that is also a shear wall, R-30 rigid insulation installed on top of the roof deck, a new membrane roof covering, steel siding, wood siding, and exterior rock veneer. For the metal building addition, work includes concrete footings, concrete foundations, steel beams and columns that are also rigid frames, steel roof purlins and steel roof deck, cross bracing in the plane of the roof structure, end wall and side wall framing with cross bracing, steel siding, liner roof insulation system with thermal blocks, and wall insulation. Special Inspection is required for anchors in concrete, anchors post installed in hardened concrete, welding, and bolting. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Meeting  2/10/2020 DONE
Received revised final cert of value.
Telephone call  2/6/2020 DONE
Emailed John to check on the new final values and when they were going to send them to us. (since they were submitted incorreclty).
Telephone call  1/14/2020 DONE
spoke with Jonathan Yorgason, and he informed me that he email Tisha regarding the outstanding fees. He said that the owner was going to looked into the fees that are due.
Telephone call  1/14/2020 DONE
spoke to Jon Yorgason (JEH Const). He said final value submitted online was incorrect because he added up all values instead of breaking out trades as portions. He said owner Joe Blumberg has final numbers. Emailed Jon and Joe to fill out new 306 form to submit final values correctly.
Meeting  1/8/2020 DONE
sent statement
Telephone call  12/31/2019 DONE
left message at ###-#### to informed them that there is an ounstanding balance on this permit for the final values that were submitted
Print Statement  5/1/2019  
Second Notice 1/18/20191/25/2019 DONE
This permit finaled on the web by Jon Yorgason
First Notice 12/27/20181/8/2019 DONE
mailed 1-11-19
PubWorks Occupancy Approval12/17/201812/17/201812/17/2018 DONE
DetailsTiffany Lowery
Permanent Occupancy  12/17/2018 DONE
BLD-Final12/3/201812/4/201812/4/2018PPASS
DetailsMike Jordan
joseph Phone #: ###-####. Ok for temp occ. Will be ok for perm occ. once public works signs perm.
Temporary Occupancy12/4/20183/4/201912/4/2018 DONE
DetailsTiffany Carson-Herker
Zoning Approval12/4/201812/4/201812/4/2018 PASS
DetailsKatelyn Menuge
FIRE-Final Inspection11/30/201812/3/201812/3/2018APASS
DetailsTroy Cobbley
Life safety passed.

joesph Phone #: ###-####
FIRE-Final Inspection11/29/201811/29/201811/29/2018PFAIL
DetailsTroy Cobbley
Provide address as discussed and provide door hardware as discussed. All other items appear ok.

Joseph Phone #: ###-####
FIRE-Final Inspection11/29/201811/29/201811/29/2018PCANC
DetailsTroy Cobbley
duplicate inspection.

Joseph Phone #: ###-####
BLD-Framing/Rough-in11/19/201811/19/201811/19/2018PPASS
DetailsMike Jordan
Joseph-grid wire Phone #: ###-####. ceiling grid ok.
BLD-Energy code compliance10/5/201810/5/201810/5/2018PPASS
DetailsMike Jordan
Joseph Blumberg ###-####
OVERRIDE  10/5/2018  
Plan assigned to (CJW)9/18/20189/18/201810/5/2018 PASS
DetailsCarl Westfall
Plan Mod - Cars and trucks unlimited (drawings routed)
Plan Reviewer's activity  10/5/2018 PASS
2nd plan mod approved
Permit Ready to Issue  10/5/2018 DONE
Plan Mod Approved
Do not reissue ( plan mod fees due)
CHANGE STATUS TO (ISS)  10/5/2018 DONE
Print Occupancy Form  10/5/2018 DONE
BLD-Framing/Rough-in10/2/201810/2/201810/2/2018PPASS
DetailsMike Jordan
Jeff Phone #: ###-####
Routing PW Drainage10/1/2018 10/2/2018 PASS
DetailsBrian Murphy
Please move your approval stamp to the most recent version
Plan resubmittals received  10/1/2018 DONE
Routing - PLAN CHECK10/1/2018 10/1/2018 PASS
DetailsCarl Westfall
Routed drawings
Routing - Design Review10/1/2018 10/1/2018 PASS
DetailsKatelyn Menuge
BLD-Framing/Rough-in9/25/20189/28/20189/28/2018PFAIL
DetailsMike Jordan
jeff Phone #: ###-####.. Needs to complete airseal. Construct new wall as per the engineering or have engineer approve in place contruction.
Plan resubmittals requested  9/28/2018 DONE
Routing PW Drainage9/24/2018 9/27/2018 PASS
DetailsBrian Murphy
Please stamp the most recent version
Routing - Design Review9/19/2018 9/24/2018 FAIL
DetailsKatelyn Menuge
Changes needed to site plan.
Routing - PLAN CHECK9/19/2018 9/24/2018 PASS
DetailsCarl Westfall
Routed to other agencies
Routing PW Street Lights9/24/2018 9/24/2018 PASS
DetailsTom Marshall
Routing - PUBLIC WORKS9/24/2018 9/24/2018 PASS
DetailsRachael Beierle
Routing - PLAN CHECK9/18/2018 9/19/2018 PASS
DetailsCarl Westfall
2nd plan mod plan intake approved
Plan Modification Accepted  9/18/2018 DONE
Plan Modification #2 application accepted. Adjust property line back to original location per ACHD's rescind, and modify parking to accommodate. Modify landscaping per owner. Show new concrete replacing existing. Remove door between shop and storage, add closet for server per owner.
BLD-Framing/Rough-in9/6/20189/6/20189/6/2018PCANC
DetailsMike Jordan
Jeff Phone #: ###-####
BLD-Wall Bracing9/6/20189/6/20189/6/2018PPASS
DetailsMike Jordan
Jeff Phone #: ###-####
BLD-Wall Bracing9/5/20189/5/20189/5/2018PCANC
DetailsMike Jordan
BLD-Framing/Rough-in9/4/20189/5/20189/5/2018ANR
DetailsMike Jordan
Jeff Phone #: ###-####. Need wall beracing plan from engineer.
CHANGE STATUS TO (ISS)  8/22/2018 DONE
Print Occupancy Form  8/22/2018 DONE
OVERRIDE  8/20/2018  
Plan assigned to (CJW)8/9/20188/9/20188/20/2018 PASS
DetailsCarl Westfall
Plan mod - Trucks and Cars Unlimited (1st IBC review done - routed)
Permit Ready to Issue  8/20/2018 DONE
Plan Mod Approved
DO NOT REISSSUE

(change back to issued status once plan mod fees are paid)
Routing - Design Review8/11/2018 8/14/2018 PASS
DetailsKatelyn Menuge
Modifications okay
Routing - PLAN CHECK8/11/2018 8/11/2018 PASS
DetailsCarl Westfall
Plan mod approved
Routing - PLAN CHECK8/9/2018 8/10/2018 PASS
DetailsCarl Westfall
Plan mod plan intake review approved
Plan Modification Accepted  8/9/2018 DONE
Plan mod workflow started to add walls and add doors to create four office spaces and a reception area. Adjust exterior windows as needed.
BLD-Foundation8/6/20188/7/20188/7/2018APASS
DetailsMike Jordan
Wall // Cameron Phone #: ###-####
BLD-Footing8/1/20188/2/20188/2/2018PPASS
DetailsMike Jordan
Cameron Phone #: ###-####
Issue PAID IN FULL permit  7/11/2018 DONE
Print Occupancy Form  7/11/2018 DONE
OVERRIDE  7/6/2018  
Plan assigned to (CJW)5/16/20185/16/20187/6/2018 PASS
DetailsCarl Westfall
* (2nd done) (June 14 - 25 days) (26 sheets) Trucks and Cars Unlimited addition
PLANS/APPL TAKEN TO FRONT DESK  7/6/2018 DONE
Permit Ready to Issue  7/6/2018 DONE
MET
Need:
ACHD-met
GC form
Revised value from GC
Verify RP-Met
Routing Off Site - STRUCTURAL6/27/2018 7/4/2018 PASS
DetailsCarl Westfall
Dave Haugland (AHJ)
Routing PW Drainage6/27/2018 7/2/2018 PASS
DetailsBrian Murphy
Routing - Design Review6/27/2018 6/28/2018 PASS
DetailsKatelyn Menuge
Routing - PLUMBING6/27/2018 6/28/2018 PASS
DetailsBill VanDegrift
See notes and install per ISPC
Routing - PLAN CHECK6/26/2018 6/27/2018 PASS
DetailsCarl Westfall
Pending structural - remember to upload the plan review report
Plan resubmittals received  6/26/2018 DONE
Route to Impact Fee Review6/18/20186/21/20186/19/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Plan resubmittals requested  6/18/2018 DONE
1st review completed  6/18/2018 DONE
Routing - FIRE5/16/20185/16/20186/14/2018 PASS
DetailsErika Akin
Attached comments to case
Routing - PLAN CHECK5/16/2018 6/8/2018 FAIL
DetailsCarl Westfall
Revised drawings required
Routing Off Site - STRUCTURAL5/16/2018 5/31/2018 FAIL
DetailsCarl Westfall
Dave Haugland (AHJ)
Routing - MECHANICAL5/16/2018 5/22/2018 PASS
DetailsTroy James
Routing - Design Review5/16/2018 5/18/2018 FAIL
DetailsKatelyn Menuge
DRH17-00563 Corrections Required
Routing - Erosion and Sediment5/16/2018 5/18/2018 PASS
DetailsAndy J. Long
ESC plan approved. Certified RP and PD. Site preparation inspection is required.
Routing PW Drainage5/17/2018 5/18/2018 FAIL
DetailsBrian Murphy
FAIL NEEDS DRAINAGE PLAN.
Routing PW Solid Waste5/17/2018 5/17/2018 PASS
DetailsEvan Carpenter
Routing PW Environmental5/17/2018 5/17/2018 PASS
DetailsRick Christenson
Oil/sediment interceptor noted in plans.
Routing PW Street Lights5/17/2018 5/17/2018 PASS
DetailsTom Marshall
Routing - PLUMBING5/16/2018 5/17/2018 FAIL
DetailsBill VanDegrift
1) R.P. required on hose connections in the garage.
2) indirect waste receptors may not be in cabinets.
3) downstream interceptor vent is to be in downstream piping, see detail.
4) flammable vepor vent and sanitary vent may not be combined.
5) trap and vent interior flammable liquids fixtures.
Routing - PLANNING5/16/2018 5/17/2018 PASS
DetailsDavid Moser
See DRH17-00563
Routing - Addressing5/16/2018 5/17/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS5/16/2018 5/17/2018 PASS
DetailsRachael Beierle
Plans ACCEPTED BY PLAN TECH  5/16/2018 DONE
DetailsChristina Prado
Recd Pcfee & Taken To Pln CK  5/16/2018 DONE
Intake Approval  5/11/2018 PASS
Plan Reviewer's activity  5/10/2018 PASS
Plan intake review approved
Intake Approval  5/9/2018 FAIL
(5-9-18) All pages of the entire Form 310 that apply need to be filled out and uploaded. Special Inspection is required for high strength bolting, etc. as required by the 2015 IBC and acknowledged by the project engineer. CJW
Intake Approval  4/27/2018 FAIL
(4-27-18) All pages of the entire Form 310 that apply need to be filled out and uploaded. Special Inspection is required for high strength bolting, etc. as required by the 2015 IBC and acknowledged by the project engineer.
Intake Approval  4/24/2018 FAIL
(4-24-18) Please refer to the circled items in the Plan Intake checklist. Please resolve each item as directed. If you do not understand what is required, please call me at ###-#### to discuss. CJW
Intake Approval  4/10/2018 FAIL
(4-10-18) Please refer to the circled items in the Plan Intake checklist. Please resolve each item as directed. CJW
Application received  4/4/2018 DONE
Application submitted via PDS Online on Apr 4 2018 12:16PM