BLD-Blower Door Test Results | 10/25/2018 | 10/26/2018 | 10/26/2018 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Jaysen Porter,, 2.87
|
DOC - Permit Finaled | 10/26/2018 | 10/26/2018 | 10/26/2018 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 10/25/2018 | 10/25/2018 | 10/25/2018 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Jaysen Porter
|
BLD-Energy code compliance | 7/18/2018 | 7/19/2018 | 7/19/2018 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Jaysen Porter
|
BLD-Framing/Rough-in | 7/12/2018 | 7/13/2018 | 7/13/2018 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Jaysen Porter,, ok to insulate
|
BLD-Wall Bracing | 7/12/2018 | 7/12/2018 | 7/12/2018 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Jaysen Porter,, fix painted areas, then ok
|
Plan Modification Accepted | | | 7/6/2018 | | DONE |
|
|
|
Revised manual J
|
Routing - MECHANICAL | 7/6/2018 | | 7/6/2018 | | PASS |
Chad Schwendiman
|
|
|
Revised Manual J
|
Plan Modification Accepted | | | 6/21/2018 | | DONE |
|
|
|
Revised acca report
|
Routing - MECHANICAL | 6/21/2018 | | 6/21/2018 | | PASS |
Chad Schwendiman
|
|
|
|
BLD-Foundation | 5/18/2018 | 5/18/2018 | 5/18/2018 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Jaysen Porter
|
BLD-Footing | 5/17/2018 | 5/18/2018 | 5/18/2018 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Jaysen Porter
|
OVERRIDE | | | 5/16/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 4/12/2018 | 4/12/2018 | 5/16/2018 | | DONE |
Brian McGowan
|
|
|
1st review complete - FAIL- 4-25 sfd L1 ePlan
|
Issue PAID IN FULL permit | | | 5/16/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/16/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/16/2018 | | 5/16/2018 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/16/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 5/16/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/10/2018 | | 5/10/2018 | | PASS |
Brian McGowan
|
|
|
Did not resolve all the corrections
|
1st review completed | | | 4/25/2018 | | FAIL |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 4/12/2018 | | 4/25/2018 | | FAIL |
Brian McGowan
|
|
|
|
Plan Modification Accepted | | | 4/18/2018 | | DONE |
|
|
|
Revised acca report
|
Routing - MECHANICAL | 4/18/2018 | | 4/18/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Route to Impact Fee Review | 4/12/2018 | 4/15/2018 | 4/13/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 4/12/2018 | | 4/13/2018 | | FAIL |
Chad Schwendiman
|
|
|
2nd floor windows don't match the submitted plans. Emailed contractor
|
Routing - PLANNING | 4/12/2018 | | 4/12/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 4/12/2018 | | 4/12/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 4/12/2018 | | 4/12/2018 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/12/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/12/2018 | | DONE |
|
|
|
|
Intake Approval | | | 4/12/2018 | | PASS |
|
|
|
|
Application received | | | 4/5/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 5 2018 12:28PM
|