BLD-Final | 6/5/2019 | 6/6/2019 | 6/6/2019 | A | PASS |
Brandon Shaw
|
|
|
Re-inspection for final for C of O Original final inspection done by Dave Hannah Branden out Phone #: ###-#### Inspection requested via web by Robert Bruno
|
DOC - Permit Finaled | 6/6/2019 | 6/6/2019 | 6/6/2019 | P | PASS |
Brandon Shaw
|
|
|
|
PubWorks Occupancy Approval | 5/2/2019 | 5/2/2019 | 5/2/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Final | 4/29/2019 | 4/30/2019 | 4/30/2019 | A | FAIL |
Dave Hannah
|
|
|
Call Builder for access or use garage code of 4908.00 Phone #: ###-#### Inspection requested via web by Admin Assistant needs hillside final air seal sign off and egress window in master bedroom
|
BLD-Aging Inspection | 4/4/2019 | 4/4/2019 | 4/4/2019 | | CANC |
Brandon Shaw
|
|
|
|
BLD-Conference | 4/3/2019 | 4/3/2019 | 4/3/2019 | A | DEFR |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Aging Inspection | 4/3/2019 | 4/3/2019 | 4/3/2019 | | DEFR |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Energy code compliance | 11/19/2018 | 11/20/2018 | 11/20/2018 | A | PASS |
Brandon Shaw
|
|
|
Wall Insulation Inspection. Please schedule for the morning. Phone #: ###-#### Inspection requested via web by Admin Assistant
|
BLD-Energy code compliance | 11/19/2018 | 11/20/2018 | 11/19/2018 | P | CANC |
Brandon Shaw
|
|
|
Section Wall Insulation Inspection. Please call with any questions. Phone #: ###-#### >> Inspection requested via web by Admin Assistant Inspection cancelled from web by: Admin Assistant
|
BLD-Framing/Rough-in | 11/16/2018 | 11/19/2018 | 11/19/2018 | A | CANC |
Jim Sly
|
|
|
Please schedule this first thing and call Robert with any questions or issues. ###-#### Phone #: ###-#### >> Inspection requested via web by Admin Assistant Inspection cancelled from web by: Admin Assistant
|
BLD-Framing/Rough-in | 11/16/2018 | 11/16/2018 | 11/16/2018 | P | PASS |
Jim Sly
|
|
|
|
BLD-Framing/Rough-in | 11/16/2018 | 11/19/2018 | 11/16/2018 | A | CANC |
Brandon Shaw
|
|
|
Please call with any questions. Phone #: ###-#### >> Inspection requested via web by Admin Assistant Inspection cancelled from web by: Admin Assistant
|
Plan Modification Accepted | | | 10/31/2018 | | DONE |
|
|
|
New manual j report
|
Routing - MECHANICAL | 10/31/2018 | | 10/31/2018 | | PASS |
Troy James
|
|
|
Resubmitted manual j report
|
BLD-Wall Bracing | 10/1/2018 | 10/2/2018 | 10/2/2018 | A | PASS |
Mike Jordan
|
|
|
Steve Phone #: ###-####
|
BLD-Footing | 6/27/2018 | 6/27/2018 | 6/27/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Foundation | 6/1/2018 | 6/1/2018 | 6/1/2018 | P | PART |
Brandon Shaw
|
|
|
Work in progress
Basement walls
|
BLD-Footing | 5/24/2018 | 5/24/2018 | 5/24/2018 | P | PART |
Brandon Shaw
|
|
|
Set backs taken from Lots 1/2 property line only, pour at own risk. Basement footing
|
Inspection Record Card- Bld | | | 5/23/2018 | | DONE |
|
|
|
|
PubWorks Subgrade Approval | 5/11/2018 | 5/11/2018 | 5/11/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
OVERRIDE | | | 5/3/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 4/17/2018 | 4/17/2018 | 5/3/2018 | | DONE |
Brian McGowan
|
|
|
5-4 sfd L2 ePlan
|
Routing - PLAN CHECK | 4/17/2018 | | 5/3/2018 | | PASS |
Brian McGowan
|
|
|
|
Issue PAID IN FULL permit | | | 5/3/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/3/2018 | | DONE |
|
|
|
|
1st review completed | | | 5/3/2018 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/3/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 5/3/2018 | | DONE |
|
|
|
met
|
Routing PW Grading-Hillside | 4/18/2018 | | 4/26/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
|
Routing - FIRE | 4/17/2018 | 4/17/2018 | 4/23/2018 | | PASS |
Tim Frost
|
|
|
5/04 House e paln
Passed - No written review required.
|
Routing - PLANNING | 4/17/2018 | | 4/20/2018 | | PASS |
Todd Tucker
|
|
|
|
Routing - MECHANICAL | 4/17/2018 | | 4/19/2018 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 4/17/2018 | 4/20/2018 | 4/18/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 4/17/2018 | | 4/18/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 4/17/2018 | | 4/18/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 4/17/2018 | | 4/18/2018 | | PASS |
Michael Zawacki
|
|
|
Hillside lot. Site preperation inspection required.
|
Plans ACCEPTED BY PLAN TECH | | | 4/17/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/17/2018 | | DONE |
|
|
|
|
Intake Approval | | | 4/17/2018 | | PASS |
Candy A. Nichols
|
|
|
|
Intake Approval | | | 4/13/2018 | | FAIL |
|
|
|
Update to 2015 IRC codes
|
Application received | | | 4/9/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 9 2018 1:01PM
|